Loading...
HomeMy WebLinkAboutRes2018-101 Sponsored by: City Attorney CITY OF SEWARD, ALASKA RESOLUTION 2018-101 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA, PROVIDING FOR FINAL CONTRACT SETTLEMENT WITH ORION MARINE CONTRACTORS, INC. WHEREAS,the City of Seward secured grant funding in 2015 to construct a breakwater at the Seward Marine Industrial Complex (SMIC) and put the project out for public bidding; and WHEREAS, Orion Marine Contractors was the lowest bidder and awarded the four-phase breakwater construction contract; and WHEREAS, Orion requested and was granted a termination for convenience after only completing the first phase of the contract; and WHEREAS, a dispute arose as to whether Orion was entitled to its entire bid amount for mobilization/demobilization, or only sums paid to date; and WHEREAS,the United States District Court for Alaska found in favor of the City of Seward in regard to this dispute; and WHEREAS, the Ninth Circuit Court of Appeals reversed the District Court's decision in favor of Orion; and WHEREAS,the Ninth Circuit Court of Appeals has denied rehearing on this matter; and WHEREAS, the case has been remanded to enter judgment in favor of Orion on the principle amount of$380,776; and WHEREAS, as the prevailing party, Orion is entitled to prejudgment interest, costs, and partial attorney's fees by law, with a total potential exposure to Seward of approximately 485,000; and WHEREAS,Orion has agreed to compromise its claim for the amount of$450,000 in order to avoid any further litigation; and WHEREAS, Due to substantially lower than expected construction costs, the remaining grant funds are sufficient to pay for the full mobilization/demobilization claim of Orion. NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA that: CITY OF SEWARD, ALASKA RESOLUTION 2018-101 Section 1.The litigation with Orion Marine Contractors in regard to the SMIC breakwater is to be fully and finally resolved by settlement. Section 2. A payment to Orion of$450,000 in exchange for dismissal of all claims between the parties is hereby approved. Section 3. Funding in the amount of $450,000 for payment to Orion is appropriated as follows: 1) $380,776 to contracted services Account No. 12333-0000-7009; and $69,224 to contracted services Account No. 12000-0000-7009. Section 4. This resolution shall take effect immediately. PASSED AND APPROVED by the City Council of the City of Seward, Alaska, this 10th day of December, 2018. THE CITY OF SEWARD,ALASKA Sue McClure, Vice Mayor AYES: Lane, Osenga, Horn, Towsley, McClure NOES: None ABSENT: Seese, Squires ABSTAIN: None ATTEST: Brenda J. Ballou/ MC City Clerk (City SAA OF SES; , c> eijitP • • a SEAL . e • "oad).,fie A ', . .• %ti z..OF .g.t° •rrr�rr0{r S..es 1 507486\1006\00771675 Agenda Statement Meeting Date: December 10, 2018 To: City Council From: City Attorney Agenda Item: Orion Settlement BACKGROUND & JUSTIFICATION: This matter was discussed with Council in executive session on November 26. Attached are the appeal briefs of the parties to provide a factual and procedural summary as to the settlement of the Orion lawsuit. In short, Seward prevailed at the trial court level on Orion’s claim for payment of an additional $381,000 for mobilization/ demobilization after the contract was terminated. The Ninth Circuit Court of Appeals reversed the trial court decision. Seward asked for a re-hearing which was denied. Orion is therefore entitled to prejudgment interest, costs, and partial attorneys fees on the principal amount of $381,000. Judgment has not been entered, but appears likely, with a total exposure of approximately $485,000. Orion has agreed to compromise on fees and costs and is willing to settle for $450,000. This settlement in is the City’s best interest as a compromise on the total exposure and in order to avoid further costs and fees, not to mention avoiding additional exposure relating to Orion’s fees, and continuing prejudgment interest. INTENT: To resolve the outstanding construction claim of Orion Marine Contractors arising out of work performed in the initial phase of SMIC breakwater construction. CONSISTENCY CHECKLIST: Yes No N/A 1. Comprehensive Plan (document source here): X 2. Strategic Plan (document source here):X 3. Other (list): 101 Res 18-101 102 4833-9877-8433v.5 0104668-000001 NO. 16-35919 _________________________________________ UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT __________________________________________________________________ ORION MARINE CONTRACTORS, INC., Plaintiff-Appellant, v. CITY OF SEWARD, Defendant-Appellee. _____________________________________ On Appeal from the United States District Court for Alaska at Anchorage The Honorable Sharon L. Gleason Case No. 3:15-cv-00151-SLG _______________________________________________________________________________ APPELLANTS’ OPENING BRIEF ___________________________________________ Traeger Machetanz Conner G. Peretti DAVIS WRIGHT TREMAINE LLP 1201 Third Avenue, Suite 2200 Seattle, Washington 98101 Tel: 206-757-8337/Fax: 206-757-7337 Attorneys for Plaintiff-Appellant Orion Marine Contractors, Inc. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 1 of 38 103 i 4833-9877-8433v.5 0104668-000001 CORPORATE DISCLOSURE STATEMENT Appellant Orion Marine Contractors, Inc., a non-governmental corporate party, states that it is wholly owned by Orion Marine Group, Inc., and no publicly held corporation owns 10 percent or more of Orion Marine Contractors, Inc.’s stock. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 2 of 38 104 ii 4833-9877-8433v.5 0104668-000001 TABLE OF CONTENTS Page JURISDICTIONAL STATEMENT .......................................................................... 1  A. District Court Jurisdiction ..................................................................... 1  B. Timeliness of Appeal ............................................................................ 1  STATEMENT OF THE ISSUE ................................................................................. 1  STATEMENT OF THE CASE .................................................................................. 2  A. Introduction ........................................................................................... 2  B. Statement of Facts ................................................................................. 3  1. The Project and Orion’s Bid. ...................................................... 3  A. Orion’s Base Bid Performance and Termination of the Contract for Convenience. ................................................................................... 6  B. Orion’s Demobilization and Seward’s Failure to Pay. ......................... 7  C. Procedural History ................................................................................. 9  SUMMARY OF ARGUMENT ............................................................................... 10  ARGUMENT ........................................................................................................... 11  A. Standard of Review ............................................................................. 11  B. The District Court Erred in Granting Summary Judgment to Seward and Not to Orion. .................................................................... 12  1. The District Court Erred by Misinterpreting the Scope of Orion’s Duty to Provide “All Submittals Required Under the Contract” ............................................................................. 12  2. The Language and Structure of the Contract Support the Interpretation That the Termination for Convenience Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 3 of 38 105 iii 4833-9877-8433v.5 0104668-000001 Meant Further Submittals Were Not “Required Under the Contract” ................................................................................... 18  3. Extrinsic Evidence of the Parties’ Intent Contradicts the District Court’s Interpretation. .................................................. 20  4. The District Court Erred by Relying on the General Termination for Convenience Section and Quality Asphalt. ..................................................................................... 24  CONCLUSION AND RELIEF REQUESTED ....................................................... 28  STATEMENT OF RELATED CASES ................................................................... 30  Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 4 of 38 106 iv 4833-9877-8433v.5 0104668-000001 TABLE OF AUTHORITIES Page(s) Cases Casey v. Semco Energy, Inc., 92 P.3d 379 (Alaska 2004) ................................................................................. 12 Cook v. Cook, 249 P.3d 1070 (Alaska 2011) ............................................................................. 17 Gasperini v. Center for Humanities, Inc., 518 U.S. 415, 116 S.Ct. 2211, 135 L.Ed.2d 659 (1996) .................................... 20 Estate of Hutchinson, 577 P.2d 1074 (Alaska 1978) ............................................................................. 24 Lingley v. Alaska Airlines, Inc., 373 P.3d 506 (Alaska May 13, 2016) ................................................................. 20 Monzingo v. Alaska Air Grp., Inc., 112 P.3d 655 (Alaska 2005) ............................................................................... 12 Nautilus Marine Enterprises, Inc. v. Exxon Mobil Corp., 305 P.3d 309 (Alaska 2013) ......................................................................... 12, 20 Ness v. National Indem. Co. of Nebraska, 247 F. Supp. 944 (D. Alaska 1965) .................................................................... 13 Norville v. Carr-Gottstein Foods Co., 84 P.3d 996 (Alaska 2004) ................................................................................. 24 Peterson v. Wirum, 625 P.2d 866 (Alaska 1981) ............................................................................... 18 Providence Washington Ins. Co. of Alaska v. Fireman’s Fund Ins. Companies, 778 P.2d 200 (Alaska 1989) ................................................................... 12, 13, 14 Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 5 of 38 107 v 4833-9877-8433v.5 0104668-000001 Quality Asphalt Paving, Inc. v. State, Dep’t of Transp. & Pub. Facilities, 71 P.3d 865 (Alaska 2003) ..........................................................................passim Rockstad v. Glob. Fin. & Inv. Co., 41 P.3d 583 (Alaska 2002) ................................................................................. 12 Snead v. Metro. Prop. & Cas. Ins. Co., 237 F.3d 1080 (9th Cir. 2001) ............................................................................ 20 Stordahl v. Government Employees Ins. Co., 564 P.2d 63 (Alaska 1972) ................................................................................. 18 Teva Pharm. USA, Inc. v. Sandoz, Inc., 135 S. Ct. 831 (2015) .......................................................................................... 11 Wessells v. State Dep't of Highways, 562 P.2d 1042, 1046 (Alaska 1977) ................................................................... 12 Williams v. Crawford, 982 P.2d 250 (Alaska 1999) ............................................................................... 20 Wright v. Vickaryous, 598 P.2d 490 (Alaska 1979) ............................................................................... 18 Yu v. Albany Ins. Co., 281 F.3d 803 (9th Cir. 2002) .............................................................................. 11 Statutes 28 U.S.C. § 1332(a) ................................................................................................... 1 Other Authorities 2 Philip L. Bruner and Patrick J. O’Connor, Jr., Bruner & O’Connor on Construction Law § 5:270 (1st ed. 2002) ...................................................... 14 Fed. R. App. P. 4(a)(1)(A) & (a)(4) ........................................................................... 1 Fed. R. Civ. P. 59(e) ............................................................................................... 1, 9 Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 6 of 38 108 1 4833-9877-8433v.5 0104668-000001 JURISDICTIONAL STATEMENT A. District Court Jurisdiction The District Court properly exercised jurisdiction over this action under 28 U.S.C. § 1332(a). ER 188. B. Timeliness of Appeal After hearing oral argument on June 21, 2016, the district court (Judge Sharon L. Gleason, presiding) denied Orion’s summary judgment motion and granted Seward’s summary judgment motion by order on August 3, 2016. ER 1. On August 30, 2016, Orion moved to amend the judgment under Fed. R. Civ. P. 59(e), which the district court denied on October 28, 2016. On November 3, 2016, Orion filed its Notice of Appeal of the summary judgment order. ER 15; Fed. R. App. P. 4(a)(1)(A) & (a)(4). STATEMENT OF THE ISSUE Did the district court err by holding that submittals following a termination for convenience were “required under the Contract,” despite the termination ending Orion’s submittal obligations, as supported by the contract’s plain language, structure, and the reasonable expectations of the parties? Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 7 of 38 109 2 4833-9877-8433v.5 0104668-000001 STATEMENT OF THE CASE A. Introduction Orion Marine Contractors, Inc., contracted with the City of Seward for the production of rock for use in constructing a new breakwater for Seward. Seward originally intended to make four separate awards of the contract’s four phases: the Base Bid and Additive phases A, B and C. Orion submitted its bid for all four phases, which included an amount for mobilization and demobilization from the project site (“Mob/Demob”). Shortly before the bid deadline, Seward decided to award all phases at once, with phases after the Base Bid phase contingent on adequate rock production from previous phases. Seward selected Orion, which had the lowest bid. Orion completed the Base Bid phase, but the parties mutually agreed to terminate the contract for convenience at that time because rock production had fallen below expectations. Section 01505 of the contract provided for full payment of the Mob/Demob bid item—$873,000—once Orion provided “all submittals required under the Contract.” ER 150, Part 4 § 4.1(C). Seward did not pay the full Mob/Demob bid item even though Orion provided all submittals required by the contract following the termination for convenience. Orion attempted to recover the full Mob/Demob bid item in the District Court of Alaska (Judge Sharon L. Gleason, presiding). The parties both moved for Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 8 of 38 110 3 4833-9877-8433v.5 0104668-000001 summary judgment on the issue of whether Seward had to pay Orion the full Mob/Demob bid item. The district court granted Seward’s motion and denied Orion’s, finding that “all submittals required under the Contract” meant all submittals required under all four phases, ER 11, so Orion had to complete every phase to recover the full bid item. In so holding, the district court erred by failing to account for the fact the termination for convenience changed what submittals Orion was “required” to provide. After the termination, the submittals “required under the Contract” were only those for the Base Bid phase. Orion provided, and Seward accepted, the Base Bid submittals. The contract’s plain language, its structure, the language of other provisions, and the reasonable expectations of the parties all support this interpretation. This Court should therefore reverse the district court’s award in Seward’s favor based on the district court’s erroneous interpretation of the contract. B. Statement of Facts 1. The Project and Orion’s Bid. In early 2014, Seward invited bids for the production of armor rock and core rock from the City of Seward Quarry for use in constructing a new breakwater at the City’s Seward Marine Industrial Center. ER 53 ¶ 2. Seward’s bid documents split the contract for the project (“the contract”) into four separate phases: the Base Bid phase and three Additive phases, A, B and C, ER 59; with each Additive phase Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 9 of 38 111 4 4833-9877-8433v.5 0104668-000001 awarded following satisfactory rock production from the prior phase. The contract documents reflect this phased approach. ER 59; ER 160 ¶ F; ER 69; ER 158 ¶ I. As Mr. Erickson repeatedly testified during his deposition, it was Orion’s expectation during the RFP phase that “only the Base Bid would be awarded to start with.” ER 20 (Erickson Dep. 32:6-7; 41:10-17; 57:4-9; 58:9-12; 60:5-9; 60:21-61:8; 64:5-6). Thus, the bidders reasonably understood that Mob/Demob would be paid in full if the project ended after the Base Bid phase. After the Base Bid, the City would award the Additive phases as separate awards: “[The City] would go to the [City Council]1 . . . and then they would award additive alternate one. And then if that got done and contractor [and Seward] on [Additive phase A] both were agreeable, then it would go to additive . . . [B] . . . and so forth.” Id. (Erickson Dep. 62:11-63:2). During the RFP phase, the City therefore requested bids for all four phases to assess bidders, but intended to make four separate awards if rock production proceeded apace. Id. (Erickson Dep. 60:7-9); ER 59; ER 160 ¶ F; ER 69; ER 158 ¶ I. However, that is not how the City proceeded, instead opting for an award of all phases at once, with the three Additive phases contingent on satisfactory rock production from the previous phase. On August 12, 2014, two days before Orion 1 Mr. Erickson referred to “the assembly,” which is the legislative body for the Kenai Peninsula Borough, on which Seward has one seat of nine. The body that would approve any contract for the City of Seward is the Seward City Council. ER 59. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 10 of 38 112 5 4833-9877-8433v.5 0104668-000001 submitted its bid, Seward issued Addendum No. 3 to the contract, stating, “A request for termination of the contract may be initiated by the contractor after the Base Bid is completed.” ER 166. Mr. Erickson recalled a conversation with the City that it changed the plan because each phase award would need approval by the City Council, which would be too time-consuming: We prepared the bid anticipating we would do only the Base Bid like the RFP said. We would only [be] awarded the Base Bid, and then if everything checked out with the owner and the contractor, then you’d go onto the additive of alternate one, they would award that. But then we became in the middle – caught between a rock and a hard place when [Seward] said, well, if we do it that way, it’s going to be a long delay, because the [City Council] has to award each additional piece. And the . . . sub[contractor] schedule wouldn’t allow it, so we ended up with a $6.1 million [contract price] when the RFP said it was just going to be the Base Bid. ER 20 (Erickson Dep. 60:21-61:8). Mr. Erickson also described this post-bid about-face on Seward’s part as putting Orion under pressure to accept the change and sign the contract with limited time to consider all the implications. Id. (Erickson Dep. 64:10-16). Orion submitted its bid for the Project on August 14, 2014, on a Bid Form created by Seward. ER 168. The Bid Form reflected the four phases, with separate pages for each. ER 169-172. Only the Base Bid portion of Seward’s Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 11 of 38 113 6 4833-9877-8433v.5 0104668-000001 Form included the Mob/Demob bid item. 2 Id. Orion’s bid item for Mob/Demob totaled $873,000 and was included only in the Base Bid phase portion of the Bid Form. ER 169. Orion was the low bidder and was awarded the Project Contract. ER 54.3 Orion’s Base Bid amount was $125,000 lower than the second lowest bidder. Id. A. Orion’s Base Bid Performance and Termination of the Contract for Convenience. Orion performed the contract’s Base Bid phase, blasting armor rock from the quarry for use in constructing the breakwater, completing the phase on November 17, 2014. ER 54 ¶ 7. However, the rock yield was lower than expected during the Base Bid phase, making performance of later phases economically unfeasible under the terms of the contract. Id. Orion proposed a price modification to make performing the Additive phases feasible, but Seward declined. Id. In a November 24, 2014, letter, Seward reminded Orion that Orion could terminate the contract for convenience under Addendum No. 3. ER 174. Orion requested termination for convenience under Addendum No. 3 in a letter dated the next day. ER 176. Orion did not request termination for any reason other than that rock yield fell below expectations. ER 54 ¶ 9. Seward accepted the 2 This was the only location in the bid documents where a Mob/Demob item was listed, which makes sense since most of the equipment would be mobilized before contract performance and demobilized after contract performance, which could end after the Base Bid if the project were terminated for convenience. 3 Orion was the low bidder for the Base Bid and the combined bid (Base Bid and Addititves A, B and C). Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 12 of 38 114 7 4833-9877-8433v.5 0104668-000001 termination and sent Orion its Notice of Convenience Termination on December 2, 2014, effective as of November 25, 2014. ER 179. In that letter, Seward advised Orion that “[a]ll rock production will cease and Additives A, B, and C will not be performed.” Id. Seward further advised Orion that “[o]ther convenience termination items will be further clarified and the requirements for contract closeout will be presented to you no later than December 5, 2014.” Id. B. Orion’s Demobilization and Seward’s Failure to Pay. Seward instructed Orion in a December 4, 2014, letter to “perform closeout procedures,” which contained a list of required submittals. ER 183. Orion fulfilled these obligations. ER 59. Orion provided, and Seward approved, the required submittals. ER 55, ER 187. Seward acknowledged that it received and approved all submittals required under the contract in a January 16, 2015, letter: “The closeout submittals provided were accepted on January 5, 2015. . . . The referenced contract with the City of Seward is closed.” Id. In the December 4, 2014, letter, Seward also instructed Orion to “complete demobilization from the project site,” which Orion did. ER 55, ER 183. Seward’s letter instructed Orion to “[r]efer to contract specification Section 01505 Mobilization and Demobilization” regarding payment of the Mob/Demob bid item. ER 187. Section 01505 Part 4 governs payment of the Mob/Demob bid item ($873,000) and formed the basis for Orion’s claim, the district court’s opinion, and Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 13 of 38 115 8 4833-9877-8433v.5 0104668-000001 the present appeal. ER 150. It has three sections: A, B and C. Section A provides that, “[w]hen 4% of the original contract amount from other bid items is earned, 40% of the amount bid for mobilization and demobilization, or 4% of the original contract amount, whichever is less, will be paid.” Id. Part B provides for an additional 4% of the original contract amount, or 40% of the amount bid for Mob/Demob, whichever is less, when Orion earned another 4% of the original contract amount from other bid items. Id. Here, 4% of the original contract amount was always less than 40% of the Mob/Demob bid item, so the provision is simple: Orion receives 4% of the original contract amount after earning 4% of the contract amount from items other than Mob/Demob, and another 4% of the original contract amount after earning another 4% of the contract amount from items other than Mob/Demob. This comprises Sections A and B of Part 4.1. However, there is a third portion: Section C. Section C states that Seward must pay Orion the remaining balance of the Mob/Demob bid item—$873,000 in total—after approving all submittals required by the contract: The remaining balance of the amount bid for Mobilization and Demobilization will be paid after all submittals required under the Contract4 are received and approved. 4 The agreement defines “Contract” as “[t]he written agreement between [Seward] and [Orion] setting forth the obligations of the parties and covering the Work to be performed, all as required by the Contract[] Documents.” ER89. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 14 of 38 116 9 4833-9877-8433v.5 0104668-000001 Id. (emphasis added). Seward triggered its obligation to pay the remaining balance of the Mob/Demob bid item by receiving and approving all submittals required following the termination for convenience. Seward completed the Base Bid and demobilized, but Seward refused to perform its payment obligations. ER 55. Rather, Seward paid Orion only $492,072 for Mob/Demob, a difference of $380,928 from the full $873,000 Mob/Demob bid item the contract required Seward pay Orion. Id. ¶ 14. C. Procedural History Orion filed its Complaint for breach of contract on August 26, 2015, alleging that Seward failed to pay Orion the full amount due for Mob/Demob as required by Section 01505. ER 188. After limited discovery, Orion moved for summary judgment on March 23, 2016. Seward opposed Orion’s motion and moved for summary judgment on the contract claim on April 15, 2016. After hearing oral argument on June 21, 2016, the district court (Judge Sharon L. Gleason, presiding) denied Orion’s motion and granted Seward’s. ER 1. On August 30, 2016, Orion moved to amend the judgment under Fed. R. Civ. P. 59(e), which the district court denied on October 28, 2016. On November 3, 2016, Orion filed its Notice of Appeal of the summary judgment order and asks this Court to reverse the district court’s Order with instructions to find in favor of Orion. ER 15. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 15 of 38 117 10 4833-9877-8433v.5 0104668-000001 SUMMARY OF ARGUMENT The district court committed four principal errors: First, the termination for convenience changed what submittals were “required under the Contract,” excusing Orion from providing submittals for later phases. After the termination, submittals for later phases were no longer “required;” at that point, only submittals for the Base Bid phase and contract closing were “required.” Orion provided its Base Bid submittals, triggering Seward’s obligation to pay the balance of the Mob/Demob bid item. Second, the structure of the contract and the language of other provisions show that the Additive phases were contingent, so the contract scope was flexible from the start. “[A]ll submittals required under the Contract” accounted for this flexibility because a termination before completing every phase would change which submittals were required. Thus, Orion’s provision of all submittals required by the Base Bid alone triggered Seward’s Mob/Demob payment obligations under Section 01505. Third, relevant extrinsic evidence supports Orion’s interpretation that “all submittals required under the Contract” meant “all submittals required under the Contract” at the time performance concluded, whether Orion’s required performance included just the Base Bid or any number of Additive phases. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 16 of 38 118 11 4833-9877-8433v.5 0104668-000001 Fourth, the district court erred by interpreting Section 01505 as controlled by an inapplicable, general provision regarding payments following a termination for convenience, especially after holding that provision did not apply. The court then relied on Quality Asphalt, a distinguishable case that does not resolve the central question of this case and appeal: whether providing “all submittals required under the Contract” meant submittals for every phase or submittals for any number of phases. As Orion shows below, the termination for convenience of a multi-phase contract after the first phase meant only those submittals for the Base Bid phase were “required under the Contract,” so Orion must be paid the full amount bid for Mob/Demob. This is the only interpretation that reasonably reconciles the plain language of the contract, its structure, the language of other provisions, and the reasonable expectations of the parties. ARGUMENT A. Standard of Review “The interpretation and meaning of contract provisions are questions of law reviewed de novo.” Yu v. Albany Ins. Co., 281 F.3d 803, 807 n.2 (9th Cir. 2002). Any findings of fact are reviewed for clear error. Teva Pharm. USA, Inc. v. Sandoz, Inc., 135 S. Ct. 831, 841 (2015). Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 17 of 38 119 12 4833-9877-8433v.5 0104668-000001 B. The District Court Erred in Granting Summary Judgment to Seward and Not to Orion. 1. The District Court Erred by Misinterpreting the Scope of Orion’s Duty to Provide “All Submittals Required Under the Contract.” The district court wrongly concluded that “all submittals required under the Contract” meant all submittals required for every phase. ER 150. Instead, the termination for convenience changed what submittals were “required,” excusing Orion from providing submittals for later phases. After the termination, submittals for later phases were no longer “required;” at that point, only submittals for the Base Bid phase and contract closing were “required.” Contract interpretation “must . . . begin by examining the plain language” of the contract. Monzingo v. Alaska Air Grp., Inc., 112 P.3d 655, 661 (Alaska 2005). Courts may use extrinsic evidence to determine “what the contract means,” regardless of whether it is ambiguous. Nautilus Marine Enterprises, Inc. v. Exxon Mobil Corp., 305 P.3d 309, 315–16 (Alaska 2013). On the one hand, “[i]f the [contract] is clear and unambiguous, we construe it solely according to its written terms.” Rockstad v. Glob. Fin. & Inv. Co., 41 P.3d 583, 586 (Alaska 2002) (citing Wessells v. State Dep't of Highways, 562 P.2d 1042, 1046 (Alaska 1977)). On the other, “extrinsic evidence is generally admissible to interpret the meaning of the Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 18 of 38 120 13 4833-9877-8433v.5 0104668-000001 language of a contract.” Casey v. Semco Energy, Inc., 92 P.3d 379, 383 (Alaska 2004). Here, both the contract and extrinsic evidence support Orion’s position. In Providence Washington Ins. Co. of Alaska v. Fireman’s Fund Ins. Companies, the Alaska Supreme Court affirmed the lower court’s grant of summary judgment for breach of an unambiguous payment provision in a contract. 778 P.2d 200, 203 (Alaska 1989). The lower court interpreted a provision in an insurance policy that required Providence Washington to pay post-judgment interest on a judgment against it. Id. The provision stated that Providence Washington must pay “all interest on the entire amount of any judgment therein which accrues after entry of the judgment . . . .” Id. The Court affirmed the lower court’s plain reading of the payment provision, reasoning that, “[w]here no ambiguity exists the court ‘should not do violence to the plain terms of a contract.’” Id. (quoting Ness v. National Indem. Co. of Nebraska, 247 F. Supp. 944, 947 (D. Alaska 1965)). Here, the district court misinterpreted the plain terms of the contract. Specifically, the district court erred by interpreting the following Mob/Demob payment provision too narrowly: The remaining balance of the amount bid for Mobilization and Demobilization will be paid after all submittals required under the Contract are received and approved. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 19 of 38 121 14 4833-9877-8433v.5 0104668-000001 ER 150. The agreement defines “Contract” as “[t]he written agreement between [Seward] and [Orion] setting forth the obligations of the parties and covering the Work to be performed, all as required by the Contract[]5 Documents.” ER 89. “Contract Documents” is a broad term for the contract and contract-attendant documents like addenda and change orders. Id. The term “Contract” is therefore a flexible term that can change with the evolution of the project. The district court was right to note that “a new contract did not arise when the original contract was terminated for convenience,” but the district court erred by not taking into account how the termination ended Orion’s performance obligations. ER 11. The Court found that, “because a new contract did not arise when the original contract was terminated for convenience, the term ‘Contract’ as used [in the above provision] . . . can only rationally be read to refer to that original contract.” Id. “Likewise,” the court continued, “it follows that the term ‘all submittals’ refers to the submittals required under these additive phases as well.” Id. As the court reasoned, because Orion never completed the Additive phases, and necessarily never provided submittals for those phases, Orion never provided “all submittals required under the Contract.” Id. But simply looking to the 5 The definition reads “Contractor Documents,” but there is only a definition for “Contract Documents,” not “Contractor Documents,” so this is likely a typographical error. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 20 of 38 122 15 4833-9877-8433v.5 0104668-000001 universe of possible future submittals at the time of contract formation fails to account for the effect of the early termination. The termination for convenience changed which submittals were “required” under the contract. When two parties terminate a contract for convenience, further performance of the contract ends. 2 Philip L. Bruner and Patrick J. O’Connor, Jr., BRUNER & O’CONNOR ON CONSTRUCTION LAW § 5:270 (1st ed. 2002) (“Bruner & O’Connor”) (noting that the purpose of a termination-for-convenience clause is to “permit a party receiving services to unilaterally cancel its contractual obligations and still avoid committing a breach that would expose it to damages”). Submittals for further phases are no longer required, because the parties terminated performance that would necessitate further submittals. After the termination, the contract did not require Orion to perform Additive Phase A or provide submittals therefor; after termination, the contract did not require Orion to perform of Additive Phase B or submittals therefor; nor must Orion have performed or provided submittals for Phase C following termination for convenience after the Base Bid was complete. The termination for convenience thus changed what performance, and therefore what submittals, were “required under the Contract,” cutting off any obligation to provide submittals for phases after termination. ER 150. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 21 of 38 123 16 4833-9877-8433v.5 0104668-000001 The district court erred by not sufficiently accounting for the effect of a termination for convenience on what performance was “required under the Contract.” The Court narrowly focused on the contract’s requirements at formation, as though what Orion was contractually required to do would never change as a result of a termination for convenience. When the district court interpreted Section 01505, it focused solely on the submittal requirements on the date of contract formation, which overlooked the change to the scope of required performance resulting from the termination for convenience. The court was right that the contract at formation included work for all four phases, even if the Additive phases were contingent on sufficient rock production. However, the court erred by not taking into account the effect of a termination for convenience on what the contract required. Termination for convenience changes what the contract requires by cutting off post-termination performance obligations. See Bruner and O’Connor § 5:270. As a result, Orion did not have to provide submittals for the Additive phases because the termination for convenience narrowed the submittals “required under the Contract.” ER 150. The district court also erred by finding that the “specific amortized payments [sic] provisions of A and B of Part 4 of Section 01505 would be largely superfluous if at the end of the Base Bid phase the contractor was entitled to receive the entire Mob/Demob payment,” because “the last two payments would Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 22 of 38 124 17 4833-9877-8433v.5 0104668-000001 likely be in such rapid succession that the three separate timing provisions serve little purpose.” ER 11. The district court is referring to the provisions which provide for partial payments toward Mob/Demob costs after completing 4% and 8% of the “original contract amount from other bid items.” ER 150. However, the district court read too much into the fact that Orion submitted its invoice for the second 4% the day before exercising its right to terminate. This is a coincidence that the contract drafters, writing before receiving any bids, would not have been able to foresee. Seward had to draft the contract before receiving bids in order for the contractors to calculate their bids. This step-wise payment of Mob/Demob is simply an inexact means of providing for partial, then full, payment of a bid item in the contract. It could just as easily have been 3% and 6%, which would nullify the district court’s argument, since the 6% invoice would have come sooner than the day before termination. The district court thus erred by drawing conclusions about the purpose of this step-wise payment of Mob/Demob when no one drafting the contract could have known how the payment timing would proceed before receiving bids. The district court therefore erred by not concluding the contract entitled Orion to the full Mob/Demob bid item for submitting all required submittals following termination. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 23 of 38 125 18 4833-9877-8433v.5 0104668-000001 2. The Language and Structure of the Contract Support the Interpretation That the Termination for Convenience Meant Further Submittals Were Not “Required Under the Contract.” The structure of the contract and the language of other provisions show that the Additive phases were contingent, so the contract scope was flexible. “[A]ll submittals required under the Contract” accounted for this flexibility because it could mean all submittals required after completing the Base Bid or any number of phases. Thus, Orion’s provision of all submittals required by the Base Bid alone triggered Seward’s Mob/Demob payment obligations under Section 01505. A contract’s structure informs a court’s interpretation of its terms’ meaning. Cook v. Cook, 249 P.3d 1070, 1079 (Alaska 2011). “In interpreting a contract, the object is to give effect to the reasonable expectations of the parties,” including by looking to “the language of other provisions of the contract.” Peterson v. Wirum, 625 P.2d 866, 872 (Alaska 1981) (citing Wright v. Vickaryous, 598 P.2d 490, 497 (Alaska 1979). “It is established that a contract should be interpreted to give effect, if possible, to all of its provisions.” Id. (citing Stordahl v. Government Employees Ins. Co., 564 P.2d 63 (Alaska 1972)). The language and structure of the contract show the contingent nature of the Additive phases, making “all submittals required under the Contract” a flexible provision that could trigger, as here, the full payment of the Mob/Demob bid item after only the Base Bid phase. For instance, as stated in the contract: “The contract Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 24 of 38 126 19 4833-9877-8433v.5 0104668-000001 is set up with Additive bid amounts which will be added to the contract if the rock being produced continues to meet these specifications.” ER 160 ¶ F (emphasis added). Here, the phrase “will be added to the contract” shows that “the contract” could mean the agreement to perform only the Base Bid phase, since the Additive phases may or may not have been “added.” Id. This provision would have been meaningless if, as the district court reasoned, “the Contract” only meant the agreement to perform all four phases and nothing less. ER 11. This pattern continues in other portions of the contract. In the City’s Public Notice – Invitation to Bid, the contract contemplated the contingent nature of the phases: To ensure that the armor rock produced for this contract conforms to the gradation and quality specifications required for this project . . . [t]he City intends to award all phases of work . . . pending satisfactory results of previous phases and continued conformance with the armor rock specification.” ER 59 (emphasis added). The contract again reiterated the contingent nature of the Additive phases in the Bid Schedule: “The following Additive Bid Amounts will be awarded in alphabetical order to the maximum possible [sic] upon confirmation that the material being produced meets the project specifications.” ER 69 (emphasis added). In the section on rock production: “Additive bid amounts will be awarded upon confirmation that the material produced from the quarry meets these specifications.” ER 158 ¶ I (emphasis added). Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 25 of 38 127 20 4833-9877-8433v.5 0104668-000001 These structural features of the contract and the language of these provisions show that “the Contract” as used in Section 01505 could have been, like here, for the Base Bid portion alone. The Additive phases were contingent on adequate rock production from previous phases. As a result, the contract contemplated that the work may have ended after the Base Bid phase. The phrase “all submittals required under the Contract” is therefore flexible enough to account for different performance requirements, whether of one phase, two or all four. If the drafters wanted to have it apply only after completing all four phases, they could have written, “The remaining balance of the amount bid for Mobilization and Demobilization will be paid after all submittals for all four phases are received and approved,” instead of “after all submittals required under the Contract are received and approved.” ER 150. The district court therefore erred by not sufficiently acknowledging the flexible nature of the contract and how Section 01505 accounted for it. 3.Extrinsic Evidence of the Parties’ Intent Contradicts the District Court’s Interpretation. As the district court correctly noted, “[t]he Alaska Supreme Court interprets contracts so as to give effect to the parties’ reasonable expectations,” including “extrinsic evidence.” ER 6 (citing Lingley v. Alaska Airlines, Inc., 373 P.3d 506, Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 26 of 38 128 21 4833-9877-8433v.5 0104668-000001 512 (Alaska May 13, 2016); Williams v. Crawford, 982 P.2d 250, 253 (Alaska 1999))6. “Extrinsic evidence” is a broad category that includes the parties’ intent: Extrinsic evidence is evidence other than the language of the contract that bears on the parties’ intentions. The extrinsic evidence that may be considered includes the language and conduct of the parties, the objects sought to be accomplished and the surrounding circumstances at the time the contract was negotiated . . . . Trial courts have broad latitude in looking at extrinsic evidence. Nautilus Marine Enters. v. Exxon Mobil Corp., 305 P.3d 309, 316 (Alaska 2013) (internal citations omitted). Here, relevant extrinsic evidence supports Orion’s interpretation that “all submittals required under the Contract” meant “all submittals required under the Contract,” whether Orion’s required performance included the Base Bid alone or any number of Additive phases. Orion’s reasonable expectation, grounded in pre-award discussions with the City, was that the City was first going to make four separate awards. However, the City changed the contract scheme to a single award of one required Base Bid and three contingent Additive phases just before bid submission. It was therefore Orion’s expectation that “all submittals required under the Contract” was a flexible phrase at contract signing that, informed by the original intent of four separate 6 Because the district court sat in diversity, the substantive law of Alaska applies. See Snead v. Metro. Prop. & Cas. Ins. Co., 237 F.3d 1080, 1090 (9th Cir. 2001) (citing Gasperini v. Center for Humanities, Inc., 518 U.S. 415, 426, 116 S.Ct. 2211, 135 L.Ed.2d 659 (1996)). Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 27 of 38 129 22 4833-9877-8433v.5 0104668-000001 awards and supported by other contract provisions, could account for full payment of Mob/Demob after completing any of the four phases. The set of submittals required under the contract would expand if the work progressed past the Base Bid or remained limited to the Base Bid phase only, as here. As the district court noted, Seward asserted that there were not separate contracts for each different phase. The Court adopted this view in concluding “[the Additive] phases were not contingent, separate contracts.” ER 10. These positions, while technically valid, present a factually incomplete picture. Before contract signing, and during the RFP phase, the City intended to make four separate awards. ER 59; ER 160 ¶ F; ER 69; ER 158 ¶ I. During the RFP phase, the City therefore requested bids for all four phases to assess bidders, but intended to make four separate awards if rock production proceeded apace. (Erickson Dep. 60:7-9); ER 68-71. If the City had proceeded with its original plan, then the parties would likely not be here. Rather, the “Contract” would, without question, include just the Base Bid and no Additive phases, and Section 01505 would trigger complete payment of the Mob/Demob bid item because Seward would have awarded only the Base Bid phase. However, that is not how Seward proceeded, instead opting for an award of one contract with three contingent Additive phases. In light of the original intent to make four separate awards, Orion’s interpretation that Section 01505 would permit payment of the full Mob/Demob after completing Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 28 of 38 130 23 4833-9877-8433v.5 0104668-000001 the Base Bid was reasonable. And it was certainly what Orion believed at the time of contract signing, as Mr. Erickson expressed his “shock” that Seward would not pay the full amount: “When [the City] said we weren’t going to get paid any more [for Mob/Demob], I was shocked. I couldn’t believe it was coming from Seward.” Id. (Erickson Dep. 56:18-20). Seward’s communications around the time of termination and closeout also show that Seward believed the only submittals required were those for the Base Bid. On December 4, 2014, after it accepted termination, Seward provided a “CONTRACT CLOSEOUT LIST,” with a list of “Submittals (required prior to final payment request).” ER 185. After Orion provided those submittals, Seward wrote back: “The closeout submittals provided were accepted on January 5, 2015 . . . . The referenced contract with the City of Seward is closed.” ER 187. Seward therefore cannot argue that more submittals were required following the termination for convenience. Seward acknowledged that “all submittals required under the Contract” had been submitted, otherwise it would not have accepted them and closed the contract. The district court therefore erred when it concluded that Orion had to provide submittals for all four phases to recover the Mob/Demob bid item. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 29 of 38 131 24 4833-9877-8433v.5 0104668-000001 4. The District Court Erred by Relying on the General Termination for Convenience Section and Quality Asphalt. The district court rightly concluded that the contract’s general termination- for-convenience section (Section 14.4.2) would not apply to the payment of Mob/Demob, but then contradicted itself by wrongly applying Section 14.4.2 to its interpretation of Section 01505. The district court pointed out that Section 14.4.2 only applies to the “‘part of the job start-up and phase-out costs not amortized by the amount of Work accomplished shall be paid by the CITY.’” ER 8 (quoting ER 127). The district court rightly found that “the parties appear to agree that mob/demob is amortized” under Section 01505, “such that it would not be payable under Section 14.4.2.” ER 8. “Certainly a fair reading of the three sections of Part 4 of Section 01505 would support [that] conclusion,” it noted. Id. “Thus,” the court held, “the Court finds that under the contract, the mob/demob bid item is payable only under the specific mob/demob provision set forth at Part 4 of Section 01505.” Id. However, the district court later states that Orion’s interpretation of Section 01505 “would appear to conflict with [payment under Section 14.4.2].” ER 12. The district court rightly found that the only controlling payment provision for Mob/Demob is Section 01505. ER 8. It should not have interpreted payment under Section 01505 as controlled by an inapplicable provision, Section 14.4.2. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 30 of 38 132 25 4833-9877-8433v.5 0104668-000001 Moreover, Section 01505’s specific provision for payment of Mob/Demob controls over any general provision in Section 14.4.2. See Norville v. Carr- Gottstein Foods Co., 84 P.3d 996, 1004 (Alaska 2004) (quoting Estate of Hutchinson, 577 P.2d 1074, 1075 (Alaska 1978)) (“In contracts, as in statutes, ‘where one section deals with a subject in general terms and another deals with a part of the same subject in a more detailed way, the two should be harmonized if possible; but if there is a conflict, the specific section will control over the general.’”). The district court erred by rightly concluding the general termination- for-convenience provision did not apply but then applied it to the interpretation of Section 01505. The district court then further erred by analogizing to Quality Asphalt, a distinguishable case. Quality Asphalt Paving, Inc. v. State, Dep’t of Transp. & Pub. Facilities, 71 P.3d 865 (Alaska 2003). In that case, Quality Asphalt Paving (QAP) provided road-paving services for the state, but the state terminated the contract for its convenience after encountering problems at the project site. Id. at 868. The contract did not have any contingent phases. Id. The contract had a general termination-for-convenience clause and no specific section regarding paying the mobilization and demobilization bid item. Id. at 869-870. However, the contract provided for payment upon termination of convenience of work performed at an “agreed price.” Id. The contract restricted application of this Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 31 of 38 133 26 4833-9877-8433v.5 0104668-000001 provision with an explicit requirement that QAP “perform all the work.’” Id. (quoting the QAP contract). QAP argued that the amount it bid on mobilization and demobilization was an “agreed price.” Id. The Alaska Supreme Court rejected this argument, pointing to the requirement that QAP “perform all the work” before triggering the payment provision. Id. (“But Quality did not deliver all the materials, and it did not perform all the work. It was therefore permissible for the hearing officer to base Quality’s award on costs incurred rather than the ‘agreed price’ for complete performance.”). The Alaska Supreme Court therefore held that substantial evidence supported the hearing officer’s award of costs incurred, rather than of the amount bid for Mob/Demob. Here, the district court erred by finding Quality Asphalt “sufficiently analogous” to bar Orion’s interpretation that it should be fully paid for Mob/Demob under Section 01505. ER 13. The district court found that “QAP asserted, like Orion here, that its mob/demob item was an ‘agreed price’ that should be fully recoverable under the specific ‘agreed price’ term of the termination provision.” Id. But this is not a reasonable conclusion, since Orion has never mentioned “agreed price,” or any similar argument, because there is no “agreed price” provision in the parties’ contract. The district court went on to state that, in Quality Asphalt, “the Alaska Supreme Court upheld the use of cost incurred because QAP had not reached the ‘complete performance’ that the court found Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 32 of 38 134 27 4833-9877-8433v.5 0104668-000001 necessary to trigger application of the ‘agreed price.’” ER 13 (quoting Quality Asphalt, 71 P.3d at 870). The court continued, “based on Quality Asphalt Paving, the Court finds that Orion could not have had a reasonable expectation that it would be paid its entire mob/demob bid item when it had completed only one of the four phases of the contract.” ER 13. However, the district court misunderstands the holding in Quality Asphalt. The Alaska Supreme Court did not find that “complete performance” is always or even usually required to trigger full payment of Mob/Demob. Quality Asphalt, 71 P.3d at 870. Rather, the Quality Asphalt court found that the contract in that case had an explicit requirement of complete performance before triggering full payment of Mob/Demob, and QAP failed to meet it. 71 P.3d at 870 (QAP contract allowed for full payment of Mob/Demob only after QAP “‘perform[ed] all the work’ . . . . But Quality did not deliver all the materials, and it did not perform all the work. It was therefore permissible for the hearing officer to base Quality’s award on costs incurred rather than the ‘agreed price’ for complete performance.”). There is no such explicit provision in the parties’ contract here. Instead, the question for the district court and this Court is whether providing “all submittals required under the Contract” meant submittals for every phase or submittals for any number of phases. Simply analogizing to Quality Asphalt begs the question of whether Section 01505 requires performance of, and Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 33 of 38 135 28 4833-9877-8433v.5 0104668-000001 submittals from, every phase. Quality Asphalt would control if there was an explicit provision in Orion and Seward’s contract that required performance of all four phases before the full payment of Mod/Demob would trigger. The QAP contract did not have contingent phases and did not have an ambiguous phrase about “all submittals required” by a multi-phase contract where work stopped after the first phase. Quality Asphalt, while it dealt with mobilization and demobilization costs, does not help resolve the relevant question in this case, and the district court should not have relied on it in construing Orion’s expectations in finding Section 01505 required submittals from all phases. As Orion has shown above, the termination for convenience of a multi-phase contract after the first phase meant only those submittals for the Base Bid phase were “required under the Contract,” so Orion must be paid the full amount bid for Mob/Demob since it provided those required submittals. CONCLUSION AND RELIEF REQUESTED For the reasons stated above, Appellant respectfully requests that the Court reverse the district court’s decision granting Seward’s motion for summary judgment and denying Orion’s motion for summary judgment. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 34 of 38 136 29 4833-9877-8433v.5 0104668-000001 RESPECTFULLY SUBMITTED this 27th of February, 2017. DAVIS WRIGHT TREMAINE LLP TRAEGER MACHETANZ By TRAEGER MACHETANZ Attorneys for Plaintiff-Appellant ORION MARINE CONTRACTORS, INC. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 35 of 38 137 30 4833-9877-8433v.5 0104668-000001 STATEMENT OF RELATED CASES Pursuant to Circuit Rule 28-2.6, Appellants are not aware of any other related cases pending in this Court within the meaning of the Rule. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 36 of 38 138 4833-9877-8433v.5 0104668-000001 CERTIFICATE OF COMPLIANCE This brief complies with the length limits permitted by Ninth Circuit Rule 32-1. The brief is 6,468 words or 29 pages, excluding the portions exempted by Fed. R. App. P. 32(f). The brief’s type size and type face comply with Fed. R. App. P. 32(a)(5) and (6). DATED this 27th day of February, 2017. DAVIS WRIGHT TREMAINE LLP TRAEGER MACHETANZ By TRAEGER MACHETANZ Attorneys for Plaintiff-Appellant ORION MARINE CONTRACTORS, INC. Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 37 of 38 139 Case: 16-35919, 02/27/2017, ID: 10334535, DktEntry: 12, Page 38 of 38 140 No. 16-35919 UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT ORION MARINE CONTRACTORS, INC., Appellant, V. CITY OF SEWARD, Appellee, On Appeal from an Order of the United States District Court for the District of Alaska The Honorable Sharon L. Gleason Case No. 3:15-cv-00151-SLG BRIEF OF APPELLEE, CITY OF SEWARD William A. Earnhart BIRCH HORTON BITTNER & CHEROT 510 L Street, Suite 700 Anchorage, Alaska 99501 (907) 276-1550 Counsel for Appellee ____ Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 1 of 38 141 i CORPORATE DISCLOSURE STATEMENT The City of Seward is a home rule city formed under the laws of the State of Alaska. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 2 of 38 142 ii TABLE OF CONTENTS CORPORATE DISCLOSURE STATEMENT ........................................................i TABLE OF CONTENTS ........................................................................................ ii TABLE OF AUTHORITIES ................................................................................. iv STATEMENT OF JURISDICTION........................................................................ 1 STATEMENT OF ISSUES PRESENTED FOR REVIEW .................................... 1 STATEMENT OF THE CASE ................................................................................ 1 A. The Breakwater Rock Production Project ............................................... 1 B. Addressing Low Yields ............................................................................ 2 C. Compensation for Mobilization and Demobilization .............................. 5 D. Termination for Convenience Option ...................................................... 7 E. Orion’s Bid ............................................................................................... 8 F. Orion’s Contract is Terminated ................................................................ 9 G. The Parties’ Dispute .............................................................................. 11 H. Procedural History ................................................................................. 12 SUMMARY OF ARGUMENT ............................................................................. 14 ARGUMENT ......................................................................................................... 15 A. Standard of Review ................................................................................ 15 Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 3 of 38 143 iii B. The District Court Properly Considered the Contract Clear Language and Intent and Denied that Orion had Provided “All Submissions Required Under the Contract,” when the Contract was Less than 25% Complete ...................................................................... 16 C. Orion’s Termination for Convenience Did Not Create a New Contract ............................................................................................... 21 D. The Court was Correct to Disregard Orion’s Late-Submitted Extrinsic Evidence ....................................................................................... 27 CONCLUSION ...................................................................................................... 30 STATEMENT OF RELATED CASES ................................................................. 30 CERTIFICATE OF COMPLIANCE WITH RULE 32(a) .................................... 31 CERTIFICATE OF SERVICE .............................................................................. 32 Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 4 of 38 144 iv TABLE OF AUTHORITIES CASES Ah Quin v. County of Kauai Dept. of Transp., 733 F.3d 267, 280 (9th Cir. 2013) ............................................................... 15 AmerisourceBergen Corp. v. Dialysist W., Inc., 465 F.3d 946, 949 (9th Cir. 2006) ............................................................... 15 Carroll v. Nakatani, 342 F.3d 934, 945 (9th Cir. 2003) ........................................ 28 Culinary & Service Emp. Union v. Hawaii Emp. Benefit Administration, 688 F.2d 1228, 1230 (9th Cir. 1982) ........................................................... 16 Easley v. Cromartie, 532 U.S. 234, 242 (2001)) ................................................... 16 Estate of Polushkin ex rel. Polushkin v. Maw, 170 P.3d 162, 167 (Alaska 2007) ................................................................ 17 Hiken v. Dep't of Def., 836 F.3d 1037, 1042 (9th Cir. 2016) ................................ 15 In re Aslan, 909 F.2d 367 (9th Cir. 1990) .............................................................. 16 Kona Enters., Inc. v. Estate of Bishop, 229 F.3d 877, 890 (9th Cir.2000) ................................................................ 28 Lingley v. Alaska Airlines, Inc., 373 P.3d 506, 512 (Alaska 2016) ....................... 17 Mason & Dixon Intermodal, Inc. v. Lapmaster Int'l LLC, 632 F.3d 1056, 1060 (9th Cir. 2011) ........................................................... 15 Nautilus Marine Enters., Inc. v. Exxon Mobil Corp., 305 P.3d 309, 316 (Alaska 2013) ................................................................ 17 Peterson v. Wirum, 625 P.2d 866, 870 (Alaska 1981) .......................................... 29 Philbin v. Matanuska-Susitna Borough, 991 P.2d 1263, 1271 (Alaska 1999) ...... 29 Quality Asphalt Paving, Inc. v. State, Department of Transportation and Public Facilities, 71 P.3d 865 (Alaska 2003). ............................... 23, 24 Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 5 of 38 145 v Taylor-Edwards Warehouse v. Burlington Northern, 715 F.2d 1330, 1333 (9th Cir. 1983) ........................................................... 15 Trishan Air, Inc. v. Fed. Ins. Co., 635 F.3d 422, 427 (9th Cir. 2011) ................... 15 United States ex rel. Lindenthal v. General Dynamics Corp., 61 F.3d 1402 (9th Cir. 1995) ....................................................................... 16 United States v. 1.377 Acres of Land, More or Less, situated in City of San Diego, Cty. of San Diego, State of Cal., 352 F.3d 1259, 1264 (9th Cir. 2003) ........................................................... 16 Williams v. Crawford, 982 P.2d 250, 253 (Alaska 1999) ...................................... 17 Winmar, Inc. v. Al Jazeera Int’l, 741 F.Supp.2d 165 (D.D.C. 2010) .................... 21 Zamani v. Carnes, 491 F.3d 990, 995 (9th Cir. 2007) ........................................... 15 STATUTES 28 U.S.C. § 1291 ...................................................................................................... 1 28 U.S.C. § 1332(a) ................................................................................................. 1 OTHER AUTHORITIES 12 James Wm. Moore et al., Moore's Federal Practice § 59.30[4] (3d ed.2000). .............................................................................. 27 5 BRUNER & O’CONNOR, CONSTRUCTION LAW § 18:45 (2016) .............. 21 Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 6 of 38 146 1 STATEMENT OF JURISDICTION The district court properly exercised diversity jurisdiction under 28 U.S.C. § 1332(a) and this Court has jurisdiction under 28 U.S.C. § 1291 over appeals from all final decisions of the district courts. Appellant’s appeal is untimely in so far as it relies primarily on arguments and evidence submitted at Docket 61, after the district court entered summary judgment at Dockets 45 and 46. STATEMENT OF ISSUES PRESENTED FOR REVIEW Was the district court correct in finding that when appellant Orion Marine Contractors, Inc. (“Orion”) knowingly agreed to perform a $6.1 million contract but requested a “termination for convenience” after completing less than 1/18th of the total rock production, that Orion had not completed “all submissions required under the contract” and was not entitled to any additional sums above what had already been paid for the work completed. STATEMENT OF THE CASE A. The Breakwater Rock Production Project In 2014, the City of Seward (the “City”) began operations to construct a new breakwater in Resurrection Bay and in July 2014, the City advertised its request for bids for the Breakwater Rock Production Project (the “Project”). [ER 59] The City’s engineer, R&M Consultants, Inc., provided the bid package that was ultimately executed by the City and its contractor for the Project. See the Contract Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 7 of 38 147 2 Documents and Technical Specifications Bid Set (“contract”). [ER 57-162] Construction of the breakwater would require almost two hundred thousand (200,000) tons of “armor rock,” which the City anticipated would be mined from the City of Seward Quarry (the “Quarry”) outside of town; conditions in the Quarry required that rock extraction for the Project would have to be sourced from previously-untested areas. [ER 59] B. Addressing Low Yields The City recognized that the primary concern for any contractor bidding to mine armor rock out of the Quarry was the Quarry’s yield, on account of the need to mine from untested areas. Although the City had used the Quarry to obtain armor rock before, and previous geotechnical reports indicated that a contractor could get the rock it would need for the Project from the Quarry, there was no guarantee that a contractor could expect a particular quantity or quality of rock to match the contractor’s level of effort once operations began. See Invitation to Bid. [ER 59] Simply put, quality rock might prove too hard to get, necessitating the importation of armor rock from other quarries elsewhere in Alaska. The City addressed this uncertainty by breaking the Project into phases. The contractor would start by mobilizing to the Quarry and producing ten thousand (10,000) tons of armor rock. [ER 59] This was called the “Base Bid phase.” Id. Following the conclusion of the Base Bid phase, the City would assess whether the Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 8 of 38 148 3 rock yields were satisfactory to justify proceeding with the remainder of the work. [ER 59] If yields were satisfactory, the work would proceed to the next of three phases, each of which would conclude with another assessment until Project completion; these three subsequent phases were referred to as “Additive Amounts” and covered the production and stockpiling of the rock, the total production of which was to be 196,090 tons. [ER 59] The City was clear that it planned to award one contract encompassing all four phases: “The City intends to award all phases of work (Base Bid and Additive Amounts) pending satisfactory results of previous phases and continued performance with the armor rock specification.” [ER 59] The contract also provided the contractor with room to renegotiate the contract terms in the event that a “yield analysis” during the first phase of the Project demonstrated that future work was likely to be unprofitable: The yield analysis will be used to evaluate achievable quantities for future phases of work (Additive Amounts). . . Re-negotiation of bid prices and/or termination of the contract may be warranted if the CONTRACTOR and the ENGINEER agree that the quarry materials have changed significantly enough to warrant a 25% reduction in yield. See Specifications. [ER 158] The contract deliberately set the production requirements low for the first phase of work, in keeping with this “wait and see” approach to rock yields, limiting the contractor’s risk. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 9 of 38 149 4 Prior to receipt of bids, the City modified the Invitation to Bid on August 12, 2014 with Addendum No. 3. [ER 166] Part of the addendum answered a question posed by the prospective contractors: “how is our risk limited if we assume a yield that is much higher than we are able to produce?” Id. The contract had stated that in such a situation “re-negotiation of bid prices and/or termination of the contract may be warranted,” but was not clear whether contractors could be sure what would happen in the event of low yields. [ER 158] (emphasis added). The addendum thus provided contractors with more certainty: A request for termination of the Contract may be initiated by the Contractor after the Base Bid is completed. The quarry development plan will initially establish the blasting plan, etc. and this will be reviewed by the City’s Consultant. If the Plan is not achievable during the first phase, the Contractor may request termination of the contract. This will be subject to additional review by the City. [ER 166] The added provision was unique because a “termination for convenience” had been a remedy previously available only to the City in the event that the City decided it would be in its best interests to terminate the work. [ER 126-127] Addendum No. 3 gave the contractor the option of requesting a termination for convenience at the conclusion of the Base Bid phase, and obligated the City to terminate the contract forthwith. Addendum No. 3 thus empowered the contractor to walk away from the Project at the conclusion of the Base Bid phase no matter how bad the numbers were. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 10 of 38 150 5 C. Compensation for Mobilization and Demobilization One substantial cost item for the Project contractor was the mobilization and demobilization from the Quarry (“mob/demob”). Contractors were asked to present a lump sum for the total cost of mob/demob as part of the pay items for the Base Bid phase work. [ER 164; 169] But even though the contractor’s total cost of mob/demob was described in the Base Bid as a pay item, the contract was abundantly clear that the contractor could not A. When 4% of the original contract amount from other bid items earned, 40% of the amount bid for mobilization and demobilization, or 4% of the original contract amount, whichever is less will be paid [for mobilization/demobilization]. expect full reimbursement of that sum once it had completed the Base Bid work. Instead, the contractor could only expect full compensation for mob/demob when it completed all four phases of the Project. Entitlement to compensation for mob/demob is addressed by Part 4 of Section 01505 of the contract: B. When you earn a total of 8% of the original contract amount from other bid items, an additional 40% of the amount bid for mobilization and demobilization, or an additional 4% of the original contract amount, whichever is less, will be paid. C. The remaining balance of the amount bid for Mobilization and Demobilization will be paid after all submittals required under the Contract are received and approved. [ER 164] (hereafter “Section 01505”). The term “Contract” is defined elsewhere as the “written agreement between the CITY and CONTRACTOR setting forth the Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 11 of 38 151 6 obligations of the parties and covering the Work to be performed, all as required by the Contractor Documents.” [ER 89], see also [ER 7] at pg. 7 (concluding that “Contractor Documents” in this provision is a typographical error otherwise referring to the “Contract Documents”). In turn, the term “Work” is contractually defined as: the act of, and the result of, performing services, furnishing labor, furnishing and incorporating materials and equipment into the Project and performing other duties and obligations, all as required by the Contract Documents. Such Work, however incremental, will culminate in the entire completed Project, or the various separately identifiable parts thereof. [ER 91] Thus, by way of example, if the total contract price was $10 million, and the contractor progressed to the point of submitting pay requests totaling $400,000 (4% of the total contract price), the contractor would receive either 40% of the total amount of mob/demob described in the Base Bid or $400,000 (4% of the total contract price) toward the total amount of mob/demob costs described in the Base Bid or, whichever was less. In the event the contractor then proceeded to perform work and submit pay requests totaling an additional 4% of the original contract price (for a total of 8%), the contractor would be entitled to an additional payment totaling either 40% of the mob/demob costs stated in the Base Bid or an additional $400,000, whichever was less. But the contractor would not be entitled to full reimbursement of mob/demob until it completed 100% of the work described in Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 12 of 38 152 7 the contract. At that point, the contractor would receive a final payment covering the difference between the amount paid to-date for mob/demob and the total price of mob/demob as set forth in the Base Bid. D. Termination for Convenience Option The Project’s contract scheme admittedly put potential contractors at risk of failing to recover their full mob/demob costs if they could not finish the project completely due to economic realities. But, as noted above, the contract contained a “safety valve” for contractors that needed to cut their losses and get out of the project, in the form of termination for convenience. [ER 166], [ER 126-27]. If the contractor encountered poor yields but could not renegotiate contract terms with the City, it could simply request termination and the City would oblige. The contractor would then walk away with whatever money it had earned to date, without further obligation to prosecute what it considered unprofitable work. The contract was abundantly clear as to what a contractor could expect following a termination for convenience. The contractor would need to stop all work, terminate all subcontracts, transmit any drawings to the City, and take whatever steps necessary to preserve the jobsite conditions. [ER 126-27]. Within 90 days of the termination, the contractor would submit a “termination claim” to the City under section 14.4.3 of the contract. [ER 127] The termination claim would be a demand for payment of the following: Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 13 of 38 153 8 a.All costs and expenses reimbursable in accordance with the Contract not previously paid to the CONTRACTOR for the performance of the Work prior to the effective date of the “Notice of Termination.” b.So far as not included under “a” above, the cost of settling and paying claims arising out of the termination of the Work under subcontracts or orders which are properly chargeable to the terminated portions of the Contract; c.The reasonable costs of settlement with respect to the terminated portion of the Contract heretofore, to the extent that these costs have not been covered under the payment provisions of the Contract. [ER 127] Importantly, this provision entitles the contractor to only two sources of reimbursement following termination: (1) payment for work performed prior to the date of termination, and (2) “closeout” costs related to wrapping-up the work, e.g. the cost of cancelling orders for materials and returning materials no longer needed. [ER 127] A contractor is not entitled to costs “covered under the payment provisions of the Contract,” such as mob/demob. [ER 127] at 14.4.3(c). E.Orion’s Bid Orion was among the bidders at the close of bids on August 14, 2014. As directed by the City, Orion established lump sum bids for each phase of the work. Orion structured its bid as follows: Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 14 of 38 154 9 Base Bid: $1,520,000 Mobilization and Demobilization: $873,000 Site Preparation: $92,000 Primary Armor Rock, Class A $410,000 Primary Armor Rock, Class B $145,000 Add-Alternate A: $1,516,290 Add-Alternate B: $1,526,320 Add-Alternate C: $1,588,290 [ER 169-172] The combined price of the Base Bid and three additives was the total contract price as shown in the “Bid Summary and Basis for Award” signed by Orion; its total bid, consisting of the Base Bid and all Add-Alternates (i.e. additional phases), was $6,150,900. [ER 172] Orion’s bid was deemed the lowest responsible and responsive bid, and the City informed Orion that it intended to award Orion the contract based on the amount of Orion’s total bid. On August 22, 2014 Orion signed the City’s contract, wherein it agreed to “provide all materials and perform all labor” for the project “as bid by the contractor.” [ER 8] [SER 31- 32] F. Orion’s Contract is Terminated Orion mobilized to the Quarry and began production in the fall of 2014. By late November, Orion had completed the Base Bid phase rock production of 10,000 tons. But, Orion was encountering low yields. The yields however were Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 15 of 38 155 10 not a 25% reduction, low enough to trigger the renegotiation of bid prices under Section 02371 of the contract, [ER 158] section E, and were within the risk of uncertainty assumed by Orion. This was precisely the scenario anticipated by the City and the bidders when the City agreed to the terms of the Addendum No. 3 during the bidding process, which provided a remedy for a contractor’s termination for convenience. However, rather than immediately requesting termination for convenience, Orion first proposed a change order increasing the total Contract price by 25% and extending the completion date. [ER 174] The City declined the request, instead reminding Orion that the City would terminate the contract for convenience if Orion requested it. [ER 174] On November 25, 2014, Orion submitted a certified pay application certifying that it had put in a total of $483,453 of work on bid items other than mob/demob. See Certified Pay Application, [SER 23-24] Although such amount of work did not quite represent 8% of the total contract amount (it was in fact 7.86%), Orion nonetheless claimed that it was entitled to payment of 8% of the total contract amount as partial compensation for mob/demob and requested $492,072 (which did represent 8% of the total contract amount) for the two submittals, which the City paid.1 1 Section 01505 provided that at 8% completion, Orion would have been cumulatively entitled to either 80% of the amount bid for mobilization and demobilization ($698,400) or 8% of the original contract amount ($492,072), whichever was less. Orion received the latter. [ER 164] [SER 25-26]. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 16 of 38 156 11 On the same day, November 25, 2014, Orion requested termination for convenience on the grounds that it was not achieving “satisfactory” rock yields under Addendum No. 3. [ER 180] On December 4, 2014, the City granted the request, stating: “the recently approved payment for Mob/Demob of $492,072.00 from Pay Request 2 will be the full amount for this category since full mobilization was not performed to support the contract Additive production requirements.” See Letter from R. Wise to B. Erickson, dated December 4, 2014, [SER 20]; [ER 183] In other words, Orion had not performed to 100% of the original Contract amount, and thus, under Section 01505, Orion would not be paid 100% of its mob/demob costs. Orion confirmed that this would be a termination for convenience under Section 14.4 of the contract and upon the effective date of the termination “all rights and obligations of the parties toward one another will end…” [ER 176], second paragraph. The date of termination was November 25, 2014. [ER 179]. G. The Parties’ Dispute Orion wrote the City on February 17, 2015, submitting a claim for “the full amount of its mobilization and demobilization fees.” See Orion Claim Letter, Docket 31-12 at 4 [SER 14]. The numbers for mob/demob were as follows: Full Mob/Demob Costs per Orion’s Bid $873,000 Actual Mob/Demob Costs as of Termination $278,974 Amount of Mob/Demob Paid By City $492,072 Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 17 of 38 157 12 [ER 169]; [SER 16]; [SER 29] Orion wanted an additional $380,928, the difference between what it had been paid in its mob/demob bid ($873,000). Of course, Orion had already received more than 175% of its actual Orion’s request flew in the face of Section 01505, wherein Orion agreed that it would not receive the full $873,000 it had bid for mob/demob until it had finished the Project. [ER 150] at Part 4.1.C. Orion had only invoiced $975,525 – far less than the original contract amount of $6,195,900. Put simply, the work described in the Contract, and in Section 01505, was mob/demob costs ($278,974), but it wanted the large “contingency” that it had built into its base bid. not The City denied Orion’s claim for full mob/demob costs on March 2, 2015. See Claim Denial Letter [SER 9-10] The City stressed that there was nothing in the bid documents or contract documents describing payment of “rock contingencies.” Orion appealed the decision to the city manager, and the City Manager affirmed the project manager’s determination. Orion filed this suit, seeking $380,928: the difference between the amount paid by the City for mob/demob and the total cost described in Orion’s bid. complete. H. Procedural History Orion’s complaint was filed on August 26, 2015, [ER 188], and after brief discovery, Orion moved for summary judgment and the City opposed and cross Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 18 of 38 158 13 moved for summary judgment; both parties agreed that the contract was “unambiguous.” [ER 6] citing Docket 22 at 8 and Docket 25 at 1-2, 15-16. To that extent, both counsel agreed at oral argument that there were no issues of fact and that the court could interpret the Contract as a matter of law. [SER 6-8] The district court granted summary judgment in favor of Seward. Finding that the only reasonable interpretation of the phrase “all submittals under the contract” means the entire contract, not just the first phase and that Orion was not entitled to further payments under the contract. [ER 1-14] After the Court ruled, Orion moved to amend the judgment under Fed. R. Civ. P. 59 asking the court to consider additional extrinsic evidence which was not in the record. This “evidence” consisted of self serving deposition testimony by Orion officers as to what they now think they were thinking when the contract was signed. Orion also advocated that the court rely on out of circuit case law in making its decision, arguing that the result was somehow a financial hardship requiring reconsideration. All of Orion’s arguments were denied. [SER 1-5]. Nonetheless, Orion bases much of its appeal on extrinsic evidence which was not before the district court when it decided summary judgment, and the City has accordingly filed a separate motion to strike this evidence from the appellate record. And while Orion failed to appeal the district court’s denial of its motion to Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 19 of 38 159 14 amend the judgment, insofar as its appeal incorporates such arguments, the City will also address such procedural impropriety below. SUMMARY OF ARGUMENT Orion knowingly signed a $6.1 million contract to provide rock to build a breakwater. When Orion’s production was not as efficient as projected, and not enough to trigger an automatic renegotiation, the City, pursuant to the parties’ contractual rights, granted Orion a termination for convenience, thereafter ending Orion’s obligations under its contract and precluding damages for lost profits or anticipatory damages. Accordingly, and pursuant the contract terms, for its mob/demob work during the Base Bid phase of the contract, Orion was paid 8% ($492,072) of the total contract price ($6,150,900), which was a sum well in excess of Orion’s actual mobilization and demobilization costs of $278,974. The district court properly considered the clear language and intent of Section 01505 and found that Orion had failed to provide “all submissions required under the contract” – the condition upon which full payment of Orion’s mob/demob bid price was due. [ER 11-14] As such, this Court should affirm the district court’s ruling and should additionally disregard any extraneous evidence (and arguments based thereupon) improperly submitted by Orion. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 20 of 38 160 15 ARGUMENT A. Standard of Review An order granting or denying summary judgment is reviewed de novo.2 Review of a trial court’s interpretation of a contract pursuant to state contract law is also de novo, so long as the interpretation is confined to an analysis of the contract language.3 A district court's denial of a Rule 59(e) motion to amend judgment is reviewed for abuse of discretion.4 Generally speaking, federal courts sitting in diversity apply state substantive law and federal procedural law. 5 As to contractual interpretation, when interpreting state law, a federal court is bound by the decisions of a state's highest court.6 Additionally, here, the district court’s August 3, 2016 decision made use of extrinsic evidence in its interpretation of the parties’ Contract. [ER 11] (The court analyzed a pay application submitted by Orion to the City near the end of Orion’s work, for evidence of Orion’s subjective belief as to the overall value of the 2 Ah Quin v. County of Kauai Dept. of Transp., 733 F.3d 267, 280 (9th Cir. 2013). 3 Taylor-Edwards Warehouse v. Burlington Northern, 715 F.2d 1330, 1333 (9th Cir. 1983). 4 Hiken v. Dep't of Def., 836 F.3d 1037, 1042 (9th Cir. 2016). 5 Mason & Dixon Intermodal, Inc. v. Lapmaster Int'l LLC, 632 F.3d 1056, 1060 (9th Cir. 2011); Zamani v. Carnes, 491 F.3d 990, 995 (9th Cir. 2007). 6 Trishan Air, Inc. v. Fed. Ins. Co., 635 F.3d 422, 427 (9th Cir. 2011); AmerisourceBergen Corp. v. Dialysist W., Inc., 465 F.3d 946, 949 (9th Cir. 2006). Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 21 of 38 161 16 Contract work.) When a trial court renders an opinion on a contract’s language which is premised on extrinsic evidence, the court’s findings of fact must be upheld unless clearly erroneous. 7 Thus the district court’s use of extrinsic evidence triggers the stricter “clearly erroneous” standard of review, and its decision must be accorded “great deference” during review.8 As shown below, under these standards of review, the clear language of the contract means Orion is not entitled to its bid amount for mob/demob. B. The District Court Properly Considered the Contract’s Clear Language and Intent and Denied that Orion had Provided “All Submissions Required Under the Contract,” when the Contract was Less than 25% Complete Orion appeals the district court’s determination that “the City does not owe [Orion] the entire mob/demob bid amount when only the Base Bid was completed.” [ER 14] As this appeal concerns the construction of a contract, Alaska state law governing contract interpretation controls the analysis.9 7 United States v. 1.377 Acres of Land, More or Less, situated in City of San Diego, Cty. of San Diego, State of Cal., 352 F.3d 1259, 1264 (9th Cir. 2003) (citations omitted); (confirming that if the court’s decision is based upon the evaluation of extrinsic evidence, the court's decision will be upheld unless there is a “definite and firm conviction that a mistake has been committed.” Citing Easley v. Cromartie, 532 U.S. 234, 242 (2001)). The Alaska Supreme Court interprets contracts so as to give effect to the parties’ 8 Culinary & Service Emp. Union v. Hawaii Emp. Benefit Administration, 688 F.2d 1228, 1230 (9th Cir. 1982); see also United States ex rel. Lindenthal v. General Dynamics Corp., 61 F.3d 1402 (9th Cir. 1995). 9 In re Aslan, 909 F.2d 367 (9th Cir. 1990) (“State law controls both the construction of the contract and the question of breach.”). Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 22 of 38 162 17 reasonable expectations.10 “Those expectations are discerned from the language of the disputed provisions, other provisions, and relevant extrinsic evidence, with guidance from case law interpreting similar provisions.”11 When interpreting a contract, a court's duty is to “ascertain and give effect to the reasonable intentions of the contracting parties.” 12 In their summary judgment briefing, the parties did not disagree that Section 01505, Part 4 amortizes Orion’s reimbursement for mob/demob, making the amount of Orion’s entitlement conditional on the owner’s receipt and approval of “all submittals under the Contract.” Appellant’s Brief p. 2. Interpretation of that phrase became the lynchpin of the district court’s analysis. [ER 7] The City has always maintained, and the trial court agreed, that “Contract” refers to all four phases of the contract, and not only to the first phase of the contract. Returning to the issue of interpretation of the contract language, the district court rightly seized on defining the word “Contract,” and focused on related defined terms; it ultimately found that the four phases – the Base Bid and the three additive phases – were all part of the parties’ contract. [ER 10] A reasonable interpretation of the contract, along with Orion’s own conduct, supports the district court’s decision. 10 Lingley v. Alaska Airlines, Inc., 373 P.3d 506, 512 (Alaska 2016); Williams v. Crawford, 982 P.2d 250, 253 (Alaska 1999). 11 Williams, 982 P.2d at 253; see also Nautilus Marine Enters., Inc. v. Exxon Mobil Corp., 305 P.3d 309, 316 (Alaska 2013). 12 Estate of Polushkin ex rel. Polushkin v. Maw, 170 P.3d 162, 167 (Alaska 2007) (internal quotation marks omitted). Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 23 of 38 163 18 Part 4(C) of Section 01505 states, “[t]he remaining balance of the amount bid for Mobilization and Demobilization will be paid after all submittals required under the Contract are received and approved.” [ER 164] In turn, the contract very clearly explains what submittals are “required under the Contract,” and not all the listed submittals were completed. For instance, Section 1700 of the Specifications sets the requirement for a submittal stating that the contractor has achieved “substantial project completion for Additional Amounts listed in the bid schedule and included in the contract.” [ER 151] Orion had not completed any of the “additive” phases of the work, so this submittal was obviously never sent to the City, and all submittals required under the Contract were patently not The payment scheme for mob/demob, which amortized the City’s payments according to the progress of the work, made sense given the uncertainty of the Project’s duration. Under other circumstances, if the parties agreed that a contractor would be reimbursed for mob/demob simply upon proving that mob/demob was accomplished and submitting a pay request, the contractor would be guaranteed full reimbursement no matter what, because mob/demob will always occur regardless of the success or failure of the project. For example, a contractor could mobilize to the Project, immediately determine that the work is unprofitable, demobilize, and then receive a windfall in the form of its mob/demob costs plus a in at the time of termination. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 24 of 38 164 19 substantial markup, despite doing no work and providing the City with no value. Amortized payment on the basis of the percentage of work actually performed prevents that from happening. Tellingly, Orion’s own certified pay request submitted contemporaneously with its request for termination of the contract indicates that Orion also understood the terms of Section 01505 as relating to the total contract amount: [SER 23] When Orion requested reimbursement for mob/demob, it had requested 8% of the “Original Contract Amount” of $6.15 million, and not 8% of its Base Bid amount of $1,645,000. In doing so, Orion acknowledged it was performing a larger contract than just the Base Bid; the stated “Balance to Complete” was $5.2 million. [SER 23] Orion was agreeing that its work would not be “complete” until it invoiced another $5.2 million. From the pay request it is clear that Orion also understood that the full contract price defined the scope of the parties’ reimbursement conditions and obligations under the contract. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 25 of 38 165 20 Additional evidence in the record before the district court on summary judgment supports Orion’s own, pre-termination belief that “the contract” included all four phases when it: (1) submitted its bid, [ER 172]; (2) when it signed the contract [SER 31-32]; (3) and when it submitted for partial payment. [SER 23] However, Orion now asserts it could perform only a small fraction of the work but collected the entire mob/demob amount so long as the City paid any submittals presented to it, making the amortization provision superfluous, as the court noted. [ER 11] It is clear from the contract and correspondence that the contract was for the Base Bid phase as well as the three additional phases; there were not separate contracts for each different phase. Noting Orion’s own conduct, the district court did not confine its analysis to the plain language of the writing. The court noted that Orion’s certified requests for payment were made against the entire $6.1 million contract, and even Orion expressly confirmed $6,150,900 as the full contract amount in its first and second mob/demob invoices submitted under Section 01505 when it sought mob/demob payment for completion of 4% of the project. [SER 23] Orion’s reimbursement was not paid based on 4% and 4% of the Base Bid phase, but on the entire contract price. For these reasons, the district court’s interpretation of the contract should not be disturbed absent a showing that it was “clearly erroneous.” Orion simply has not carried this burden. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 26 of 38 166 21 C. Orion’s Termination for Convenience Did Not Create a New Contract Orion argues that the specifications of the contract had control over the bid forms, so the inclusion of the mob/demob in only the Base Bid page of Orion’s bid is not relevant. The termination for convenience simply amended the contract down to one phase, creating a new, smaller contract. See Appellant’s Brief at 15. A new contract did not arise when the original contract was terminated for convenience; the term “Contract” as used in Section 01505, Part 4(C) can only rationally be read to refer to the original contract. Likewise, it follows that the term “all submittals” refers to the submittals required under these additive phases as well. Orion’s assertion that because it was able to terminate the contract early for convenience. The three additive phases were contingencies and not part of the original contract is contrary to the meaning of the term “termination for convenience.” The use of a termination for convenience provision results in the early termination of a contract, with only partial performance, but without a remedy for breach.13 13 See 5 BRUNER & O’CONNOR, CONSTRUCTION LAW § 18:45 (2016) (“The thrust of the termination for convenience clause is to convert the contractor’s compensatory damages interest from ‘expectancy’ to ‘reliance’ damages.”); Winmar, Inc. v. Al Jazeera Int’l, 741 F.Supp.2d 165 (D.D.C. 2010) (noting that the purpose of a termination clause is to “permit a party receiving services to unilaterally cancel its contractual obligations and still avoid committing a breach that would expose it to damages”). Termination for convenience is a method by which a party may limit its exposure for the risk of being unable to perform an entire contract, not a means by Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 27 of 38 167 22 which a party may create a new contract with a decreased scope. The plain language of the contract between the City and Orion makes it clear that the parties contracted for the Base Bid and the three additive phases, not solely for the Base Bid; these three phases were not contingent, separate contracts. Upon signing the contract, Orion became obligated to perform all of the contract, unless and until the entire contract was completed or terminated for convenience. After the termination for convenience, Orion was only entitled to unreimbursed costs incurred. The termination for convenience clause “changes what the contract requires by cutting off all post termination performance obligations.” Bruner and O’Connor supra section 5:270, as cited by Orion. Appellant’s Brief at p. 16. The obligations of both parties are terminated; the contractor performs no additional work other than leaving the site and the owner makes no further payments other than costs incurred. Orion would have the termination for convenience only end its obligation to make “all submittals required” but still have the City make payments not yet accrued. Section 14.4 termination for convenience ends all obligations other than the close out items listed in section 14.4.1 and 14.4.2.[ER 127] There is controlling Alaska law directly on point. The Alaska Supreme Court addressed this exact factual scenario.14 14 Quality Asphalt Paving, Inc. v. State, Department of Transportation and Public Facilities, 71 P.3d 865 (Alaska 2003). The State of Alaska retained Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 28 of 38 168 23 contractor, Quality Asphalt Paving (“QAP”) for a road-paving project. Early in the project, the state terminated the contract for convenience. QAP then sought to recover the entire mob/demob line item in the contract as an “agreed price”.15 However, the State refused to pay any more than the actual mob/demob costs incurred by QAP Based on the termination for convenience clause payment provisions, because QAP had not completed the project. The Alaska Supreme Court held that the amount of mob/demob that the parties had agreed to must be read in light of the fact that QAP had “covenant[ed] and agree[ed] to furnish and deliver all the materials and to do and perform all the work.”16 Because QAP did not complete the work, the termination for convenience clause required only an “award on costs incurred rather than the ‘agreed price’ for complete performance.”17 Orion again argues that Quality Asphalt Paving is inapplicable because the Seward/Orion contract contained a specific provision controlling the payment of the mob/demob bid item, while the operative provision in Quality Asphalt Paving was only a “general payment” clause. However, in both cases the contractor is/was asserting the mob/demob item was an “agreed price” that should be fully Orion’s actual mob/demob costs were substantially less than it had already been paid on that item. [SER 29] 15 Id. at 71 P3d at 869-70. 16 Id. at 71 P3d at 870. 17 Id. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 29 of 38 169 24 recoverable under the specific “agreed price” term of the termination provision. The Alaska Supreme Court upheld the use of “cost incurred” because QAP had not reached the “complete performance” that the court found necessary to trigger application of the “agreed price.”18 Orion mischaracterizes the district court’s finding in regard to the applicability of Section 14.4.2, the pay provision under termination for convenience. The district court found 14.4.2 relevant to the termination of the contract, but not controlling as to payment of “costs amortized …” [ER 8] Section 14.4.2 states the Contractor will be paid for “all work in place as of that date…” [ER 127] Section 14.4.3 (a) limits the contractor’s recovery to reimbursable expenses “not previously paid to the CONTRACTOR;”; and Section 14.4.3(c) is clear that the contractor only recover for costs that “have not been covered under the payment provisions of the contract.” [ER 127] Orion’s actual mob/demob costs of $278,974 were less than the $492,072 Orion had already been paid under Section 1505. [SER 29]. Any actual costs (including mark up) incurred by Orion due to the unexpected cancellation of the contract had already been paid. The district court was correct when it found “Orion could not have had a reasonable expectation that it would be paid its entire mob/demob bid item when it had completed only one of the four phases of the contract.” [ER 13] 18 Id. at 870. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 30 of 38 170 25 It is important to note that section 14.4.3(c) uses the term “have not been covered…,” meaning “up to now.” Orion’s interpretation would require the present progressive tense “are not covered under the payment provisions…,” meaning “currently.” Payment under 14.4.3 is not applicable because Orion had already recovered its costs (and a tidy profit) under Section 1505 when the contract terminated for convenience ending the contract. Any claim for unpaid mob/demob costs or added mob/demob costs incurred due to the termination are offset by “All previous payments made to the contractor…” and “All progress payments made to the contractor…” under section 14.4.4 (a) and (d) respectively. Appellant argues that the payment clause for mob/demob should take precedence over the general clause for termination for convenience. The termination for convenience takes precedence over all other clauses in the contract as it terminates the contract and by definition voids all other payment provisions. On the matter of “closeout costs” the provision later goes out of its way to explicitly state that the amortized repayment for mob/demob described in Section 01505 would remain in force notwithstanding the contractor’s entitlement to “reasonable costs of settlement:” The CONTRACTOR shall be paid 10% of the cost, freight not included, of materials canceled without changes, to the extent that the CONTRACTOR can establish them. The extra costs due to cancellation of bonds and insurances and that part of the job start-up and phase-out costs not amortized by the amount of Work accomplished shall be paid by the CITY. Charges for loss of profit or Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 31 of 38 171 26 consequential damages shall not be recoverable except as provided above.” [ER 127] at Section 14.4.2 (emphasis added). Although the terms are not specifically defined in the contract, the most reasonable interpretation of “job start-up and phase-out costs” is those costs prior to actual production and following completion of the work, including mob/demob. This interpretation is bolstered by the fact that the only costs “amortized by the amount of Work” that were not part of actual rock production were mob/demob. By limiting the cost entitlement of the contractor at termination to those costs not amortized by the amount of work, the contract termination provision specifically limited the contractor’s recovery for mob/demob to the payment scheme set forth in Section 01505 and quoted above. Termination for convenience explicitly did not Here again Orion has not carried its burden of demonstrating that the district court’s analysis was “clearly erroneous.” The court was correct when it held: change whether the contractor was entitled to 4% of the total contract, 8% of the total contract price, or the full amount bid for mob/demob. Orion received the portion of mob/demob “amortized by the amount of work accomplished,” and in fact made a profit on that portion of the contract. Orion was not entitled to its expected additional profit on mob/demob. … the City has proposed the only reasonable interpretation of the phrase “all submittals under the contract” in Part (C) of Section 1505 given the plain language of the parties’ contract, the circumstances of Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 32 of 38 172 27 the formation of the contract, and the surrounding contract provisions. Under that interpretation, the City does not owe the entire mob/demob bid amount when only the Base Bid was completed. [ER 13-14] D. The Court was Correct to Disregard Orion’s Late-Submitted Extrinsic Evidence Orion submitted a Rule 59 Motion to amend a number of pages of deposition testimony from which it attempts to submit two new arguments that the contract language was not in fact clear on its face. Both arguments are not properly before this court and both fail on the merits. While Rule 59(e) permits a district court to reconsider and amend a previous order, the rule offers an “extraordinary remedy, to be used sparingly in the interests of finality and conservation of judicial resources.”19 Indeed, “a motion for reconsideration should not be granted, absent highly unusual circumstances, unless the district court is presented with newly discovered evidence, committed clear error, or if there is an intervening change in the controlling law.”20 A Rule 59(e) motion may not be used to raise arguments or present evidence for the first time when they could reasonably have been raised earlier in the litigation.21 19 12 James Wm. Moore et al., Moore's Federal Practice § 59.30[4] (3d ed.2000). The district court denied Orion’s motion to amend. [SER 1-5]. The district court's denial of a 20 Carroll v. Nakatani, 342 F.3d 934, 945 (9th Cir. 2003) citing Kona Enters., Inc. v. Estate of Bishop, 229 F.3d 877, 890 (9th Cir.2000). (citations omitted). 21 Id. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 33 of 38 173 28 motion for reconsideration is reviewed for an abuse of discretion.22 Orion’s first new argument is that Seward changed the bid request at the last second from four separate contracts to one, and that Orion was forced to make a quick decision to sign the contract without considering all implications. Appellant’s Brief at p.11. Initially, this is an admission that Orion knew this was one contract, not four – a fact confirmed by Orion’s Vice President, Bryce Erickson, who signed the contract: Orion did not appeal the denial of it motion to amend, and should not be allowed to present the evidence and arguments made in that motion. As such, Appellant’s entire third argument, found at pp. 20-23 of its brief, must be stricken. 12· ·Q.· In fact, you wound up signing a contract for the 13· ·whole thing, right? 14· ·A.· Right. [ER 36] at pg. 60 lines 12-14. Orion knowingly signed and submitted its bid on August 14, two days after the addendum that allegedly changed the terms of the bid. [ER 168], [ER 166] Nothing in Addendum No. 3 indicates more than a clarification that a termination for convenience could be granted after the Base Bid phase. [ER 166] The unsubstantiated argument that the City amended the project to avoid going repeatedly to the “assembly” (City Council) was not before the court on summary 22 Id. Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 34 of 38 174 29 judgment. [SER 6-8] And as noted above, if a change in the project was made, and whatever the reason or timing of the change, Orion still voluntarily entered into the full contract. The second new argument is that extrinsic evidence in the form of the testimony of an Orion officer after this lawsuit was filed, but before the summary judgment briefing was completed, should be considered. See e.g. Appellant’s brief at pg. 23. Orion’s Motion for Summary Judgment was supported by parts of the same deposition of Bryce Erickson as it later tried to introduce under Fed. R. Civ. P. 59. [ER 17-18] Again, much of this extrinsic evidence was not before the court. The deposition testimony of Bryce Erickson as to what he thought the contract meant has no value in interpreting the contract. After-the-fact subjective assertions of intent in contract situations are entitled to no evidentiary weight.23 This Court should not consider the unappealed denial of Orion’s Motion to Amend and the related evidence and arguments. Even if this Court were to consider the newly raised extrinsic evidence, it must uphold the district court’s decision as not clearly erroneous. Bryce Erickson has admitted Orion agreed to the full $6.1 million contract and the only probative extrinsic evidence shows that this was one contract not four. [ER 31-10] 23 Philbin v. Matanuska-Susitna Borough, 991 P.2d 1263, 1271 (Alaska 1999) citing Peterson v. Wirum, 625 P.2d 866, 870 (Alaska 1981). Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 35 of 38 175 30 CONCLUSION The district court was correct in finding that the language of the contract is clear and that after termination for convenience, Appellant could only recover actual unreimbursed costs and is thus not entitled to any additional sums under the agreement. STATEMENT OF RELATED CASES City of Seward is not aware of any related cases pending in this Court. DATED this 21st day of April, 2017. BIRCH HORTON BITTNER & CHEROT Attorneys for Appellant City of Seward By: /s/ William A. Earnhart Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 36 of 38 176 31 CERTIFICATE OF COMPLIANCE WITH RULE 32(A) This brief complies with the type-volume limitation of Federal Rule of Appellate Procedure 32(a)(7)(B)(i) because this brief contains 6,499 words, excluding the parts of the brief exempted by FRAP 32(a)(7)(B)(iii). This brief complies with the typeface requirements of Federal Rule of Appellate Procedure 32(a)(5) and (6) because this brief has been prepared in a proportionally spaced typeface using Microsoft Word 2010 in 14-point Times New Roman font. DATED this 21st day of April, 2017. BIRCH HORTON BITTNER & CHEROT Attorneys for City of Seward By: /s/ William A. Earnhart Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 37 of 38 177 32 CERTIFICATE OF SERVICE I certify that on April 21, 2017, I electronically filed the foregoing Brief of Appellee with the Clerk of Court for the Ninth Circuit Court of Appeal by using the appellate CM/ECF system. I certify that all participants in the case are registered CM/ECF users and that service will be accomplished by the appellate CM/ECF system. DATED this 21st day of April, 2017. BIRCH HORTON BITTNER & CHEROT Attorneys for Appellee City of Seward By: /s/ William A. Earnhart Case: 16-35919, 04/21/2017, ID: 10406477, DktEntry: 25, Page 38 of 38 178 4821-9022-0103v.4 0104668-000001 NO. 16-35919 _________________________________________ UNITED STATES COURT OF APPEALS FOR THE NINTH CIRCUIT __________________________________________________________________ ORION MARINE CONTRACTORS, INC., Plaintiff-Appellant, v. CITY OF SEWARD, Defendant-Appellee. _____________________________________ On Appeal from the United States District Court for Alaska at Anchorage The Honorable Sharon L. Gleason Case No. 3:15-cv-00151-SLG _______________________________________________________________________________ ORION’S REPLY ___________________________________________ Traeger Machetanz Conner G. Peretti DAVIS WRIGHT TREMAINE LLP 1201 Third Avenue, Suite 2200 Seattle, Washington 98101 Tel: 206-757-8337/Fax: 206-757-7337 Attorneys for Plaintiff-Appellant Orion Marine Contractors, Inc. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 1 of 19 179 i 4821-9022-0103v.4 0104668-000001 TABLE OF CONTENTS INTRODUCTION ..................................................................................................... 1  ARGUMENT ............................................................................................................. 2  A. Seward Misstates the Standard of Review. ........................................... 2  B. The Termination for Convenience Provision Does Not Preclude Recovery Under Section 01505. ............................................................ 4  1. The contract’s termination for convenience section does not prevent recovery under Section 01505 and the district court’s arguments to the contrary are unavailing. ...................... 4  2. Seward’s arguments that the termination for convenience provision precludes recovery of Mob/Demob costs under Section 01505 are unavailing. ..................................................... 8  C. Seward’s Other Arguments Regarding Orion’s Recovery Are Unavailing. .......................................................................................... 10  D. Orion Has Not Made New Arguments, and Leaves the Disposition of the Motion to Strike to the Parties’ Briefing on That Issue. ........................................................................................... 12  CONCLUSION ........................................................................................................ 13  Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 2 of 19 180 ii 4821-9022-0103v.4 0104668-000001 TABLE OF AUTHORITIES Page(s) Cases Conrad v. Ace Prop. & Cas. Ins. Co., 532 F.3d 1000 (9th Cir. 2008) .............................................................................. 2 Estate of Hutchinson, 577 P.2d 1074, 1075 (Alaska 1978) ..................................................................... 6 Japanese Vill., LLC v. Fed. Transit Admin., 843 F.3d 445, 455 (9th Cir. 2016) ...................................................................... 11 Mateo v. M/S KISO, 41 F.3d 1283 (9th Cir. 1994) ................................................................................ 3 Norville v. Carr-Gottstein Foods Co., 84 P.3d 996 (Alaska 2004) ................................................................................... 6 Quality Asphalt Paving, Inc. v. State, Dep’t of Transp. & Pub. Facilities, 71 P.3d 865, 870 (Alaska 2003) ..................................................................... 9, 10 Rockstad v. Global Fin. & Inv. Co., 41 P.3d 583, 592-93 (Alaska 2002) ...................................................................... 8 S. Cal. Painters & Allied Trade Dist. Council No. 36 v. Best Interiors 359 F.3d 1127, 1130 (9th Cir. 2004) ..................................................................... 2 Tamen v. Alhambra World Investment, Inc. 22 F.3d 199, 203 (9th Circ. 1994) .......................................................................... 2 United States v. 1.377 Acres of Land, More or Less, situated in City of San Diego, Cty. of San Diego, State of Cal., 352 F.3d 1259, 1264 (9th Cir. 2003) ....................................................................... 2, 3 Zeman v. Lufthansa German Airlines, 699 P.2d 1274, 1282 (Alaska 1985) ..................................................................... 9 Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 3 of 19 181 1 4821-9022-0103v.4 0104668-000001 INTRODUCTION After misstating the standard of review, Seward does not directly address Orion’s primary argument: that the termination for convenience changed what submittals were “required.” ER 150 (Section 01505, Part 4 § 4.1(C)). The termination excused Orion from providing submittals for phases following the Base Bid; in other words, submittals for later phases were no longer “required.” Orion provided all submittals Seward requested in correspondence following termination. ER 183-187. Seward attempts to sidestep the plain meaning of Section 01505 by arguing that the general termination for convenience section precludes recovery under Section 01505. But the termination for convenience provision includes an express carve-out for items “covered under the payment provisions of the Contract.” Section 01505 is one such “payment provision” that the more general termination for convenience section, by its terms, does not control. The district court therefore erred in finding the termination for convenience provision and Section 01505 would conflict under Orion’s reading. Despite Seward’s arguments, addressed in detail below, the district court erred by holding that submittals following a termination for convenience were “required under the Contract,” because the termination ended Orion’s submittal obligations. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 4 of 19 182 2 4821-9022-0103v.4 0104668-000001 ARGUMENT A. Seward Misstates the Standard of Review. “‘In general, interpretation of the language of a contract is a question of law which is reviewed on a de novo basis, with no deference accorded to the decision of the district court.’” United States v. 1.377 Acres of Land, More or Less, situated in City of San Diego, Cty. of San Diego, State of Cal., 352 F.3d 1259, 1264 (9th Cir. 2003) (quoting Tamen v. Alhambra World Investment, Inc. (In re Tamen), 22 F.3d 199, 203 (9th Cir.1994)). “The district court’s grant of summary judgment on a contract claim is reviewed de novo, as is its interpretation and meaning of contract provisions.” Conrad v. Ace Prop. & Cas. Ins. Co., 532 F.3d 1000, 1004 (9th Cir. 2008) (citing 1.377 Acres of Land, 352 F.3d 1259, 1264 (9th Cir. 2003); S. Cal. Painters & Allied Trade Dist. Council No. 36 v. Best Interiors, 359 F.3d 1127, 1130 (9th Cir. 2004)). While the Court of Appeals gives greater deference to a district court’s factual findings, “[the district court’s] application of legal principles to those facts involves a question of law subject to de novo review.” Id. (citing In re Tamen, 22 F.3d at 203). The district court’s summary judgment order essentially relies only on its interpretation of the language of the contract. The Court therefore reviews the decision de novo, “with no deference accorded to the decision of the district court.” United States v. 1.377 Acres of Land, 352 F.3d at 1264. The only extrinsic Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 5 of 19 183 3 4821-9022-0103v.4 0104668-000001 evidence even mentioned is one sentence of dicta, where the district court said that an invoice from Orion to Seward “strengthened” the district court’s “reading” of the contractual language. ER 11. Seward wrongly argues that this one sentence transforms the entire opinion into one reviewed under the “clear error” standard. Appellee’s Brief at 16. This argument fails for two reasons. First, the district court did not base its decision on the invoice, it merely referenced it as support for its reading of the contractual language. Mateo v. M/S KISO, 41 F.3d 1283, 1286–87 (9th Cir. 1994) (“clear error” applies to decisions that “require review of extrinsic evidence”). Second, even if the “clear error” standard applied in part, it would only apply to the district court’s factual finding that Orion referenced the full contract price in two of its invoices. Thus, the only issue reviewed under the “clear error” standard is whether the invoices reference the total contract price. That is the only finding of fact. Whether this fact supports the district court’s interpretation of the contractual language under applicable case law is reviewed de novo.1 The Court should 1 Seward cites an inapplicable case for its proposition that the Court must review everything in the decision for “clear error.” In United States v. 1.377 Acres of Land, the district court interpreted two leases. 352 F.3d at 1264. As to one, the district court explicitly stated it was not considering extrinsic evidence; as to the other, it gave no reasoning at all. The Ninth Circuit held that the de novo standard applied to the district court’s interpretation of both leases. Id. This case does not stand for the proposition that a passing reference to an extrinsic fact envelops the Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 6 of 19 184 4 4821-9022-0103v.4 0104668-000001 therefore review the substantial core of the district court’s order under the de novo standard because it focuses entirely on the contractual language, only mentioning extrinsic evidence, in one sentence, as not inconsistent. B.The Termination for Convenience Provision Does Not Preclude Recovery Under Section 01505. Orion argued in its opening brief that the termination for convenience of the contract changed which submittals were “required under the Contract.” See ER 150, Section 01505, Part 4 § 4.1(C). Because the parties declined to pursue any later phases, submittals for those phases were not “required.” Orion provided its Base Bid and closeout submittals, triggering Seward’s obligation to pay the balance of the Mob/Demob bid item. Seward does not attack this interpretation. Indeed, Seward provides no alternative reading of this provision, instead arguing that the termination for convenience provision prevents recovery of Mob/Demob under Section 01505. It does not. 1.The contract’s termination for convenience section does not prevent recovery under Section 01505 and the district court’s arguments to the contrary are unavailing. Orion can recover certain costs specifically under the termination for convenience section, unless other payment provisions of the contract govern their recovery. ER 127 § 14.4.3. The termination for convenience section thus carves entire decision in the standard of review reserved only for factual findings and not legal conclusions. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 7 of 19 185 5 4821-9022-0103v.4 0104668-000001 out an allowance for other payment provisions of the contract. It does not displace them, as the district court wrongly concluded. ER 12. Section 14.4.3 provides a list of items a contractor may include in a claim following a termination for convenience. Id. These include settlement costs of work up to the date of termination (subsection a), the cost of settling and paying subcontract claims for the terminated portion (subsection b), and the costs of settlement for the terminated portion of the contract, unless other payment provisions of the contract provide for their recovery (subsection c): The reasonable costs of settlement with respect to the terminated portion of the Contract heretofore, to the extent that these costs have not been covered under the payment provisions of the Contract. Id. (emphasis added). Subsection (c) therefore excludes payments covered by other portions of the contract from the general termination-for-convenience payment mechanism. Doing so makes sense to prevent double recovery of payments made under other, more specific, payment provisions and the general termination for convenience section. Section 01505, as applied to this project, provided for payment of 4% of the original contract amount after earning 4% of the original contract amount from items other than Mob/Demob. ER 150 § 4.1. Seward would pay another 4%, for a total of 8%, after Orion earned another 4% of the original contract amount from items other than Mob/Demob. Id. Finally, Seward would pay the remainder of the Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 8 of 19 186 6 4821-9022-0103v.4 0104668-000001 Mob/Demob bid item after Orion provided “all submittals required under the Contract.” Id. Section 01505, as described above, is one example of a specific “payment provision of the Contract” mentioned in 14.4.3, subsection (c), because it “cover[s]” other “costs” (i.e. Mob/Demob). The specific method for calculating recovery of Mob/Demob costs under Section 01505 falls outside the generally applicable method for calculating recoverable costs provided in the termination for convenience provision. This conclusion is supported by the doctrine that specific provisions govern over general ones. See Norville v. Carr-Gottstein Foods Co., 84 P.3d 996, 1004 (Alaska 2004) (quoting Estate of Hutchinson, 577 P.2d 1074, 1075 (Alaska 1978)) (“In contracts, as in statutes, ‘where one section deals with a subject in general terms and another deals with a part of the same subject in a more detailed way, the two should be harmonized if possible; but if there is a conflict, the specific section will control over the general.’”). The termination for convenience provision therefore does not prevent recovery of Mob/Demob under Section 01505; rather, it expressly permits it. The district court erred by finding that Section 01505 “conflict[s]” with the termination for convenience provision. ER 12. The district court reasoned that because Mob/Demob was not included in Section 14.4.2 of the termination for convenience section, then that subsection prevents recovery for Mob/Demob. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 9 of 19 187 7 4821-9022-0103v.4 0104668-000001 ER 12 (“[Section 14.4.2] explicitly states that upon termination, the contractor receives a variety of payments for extra costs, but these payments specifically do not include the amortized amounts under the mob/demob provision.”). This conclusion is wrong for three reasons. First, the district court read too much into a particular phrase in Section 14.4.2, which is not specific enough to exclude Mob/Demob. That section provides for recovery of “extra costs due to . . . that part of job start-up and phase- out costs not amortized by the amount of Work accomplished . . . .” ER 127. The court reasoned that this provision must exclude recovery of Mob/Demob because Mob/Demob is an “extra cost due to . . . job start-up and phase-out costs” that is amortized by the amount of Work accomplished (i.e. 4%, 8%, then the balance). ER 12. But the district court took this implication too far. Mob/Demob is not an “extra cost”—it is priced into the contract from the beginning. Orion does not seek any “extra cost,” only that which is due under the terms of the contract. Moreover, “start-up and phase-out costs” is not defined and the district court should not have read it so broadly as to exclude an entire section of the contract, Section 01505, that deals specifically and explicitly with payment of Mob/Demob. Second, the rest of the termination for convenience section provides for the recovery of other costs not included in Section 14.4.2, so the district court should not have reasoned that Orion cannot recover anything not included in Section Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 10 of 19 188 8 4821-9022-0103v.4 0104668-000001 14.4.2. For instance, Section 14.4.3 provides for the recovery of costs not included in 14.4.2. The court’s reasoning would render meaningless Section 14.4.3. See Rockstad v. Global Fin. & Inv. Co., 41 P.3d 583, 592-93 (Alaska 2002) (“[T]his definition is excluded ... by the rule disfavoring interpretations that leave contract terms meaningless.”). Third, Section 14.4.3 carves out costs recoverable under other “payment provisions of the Contract.” ER 127 § 14.4.3. This provision would be meaningless if only the costs explicitly listed in the termination for convenience section were recoverable. To the contrary, the contract makes clear that other “payment provisions,” like Section 01505, can provide for recovery following a termination for convenience. The district court therefore erred by reading such a strong implication into an inapplicable, general phrase. 2. Seward’s arguments that the termination for convenience provision precludes recovery of Mob/Demob costs under Section 01505 are unavailing. Seward’s arguments against payment under Section 01505 are unavailing. Seward cannot overrule explicit contract terms by appeal to the general practice that terminations for convenience allow only for recovery of “unreimbursed costs incurred.” Appellee’s Brief at 22. Parties, especially sophisticated ones like those here, can draft their contract to follow or not follow typical practice. Here, the parties specifically provided for payment of Mob/Demob under Section 01505, and Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 11 of 19 189 9 4821-9022-0103v.4 0104668-000001 drafted the termination for convenience provision not to apply to such sections. ER 127 (Orion can recover under general termination for convenience section “to the extent these costs have not been covered under the payment provisions of the Contract”). The Court should not overrule the parties’ bargain by appeal to common practice. See Zeman v. Lufthansa German Airlines, 699 P.2d 1274, 1282 (Alaska 1985) (“Whatever the usual business practices” of a party, “they are not the issue before us,” reverting to contractual evidence instead). Seward and the district court’s analogy to Quality Asphalt Paving fails. Quality Asphalt Paving, Inc. v. State, Dep't of Transp. & Pub. Facilities, 71 P.3d 865, 870 (Alaska 2003). In that case, QAP sought payment of mobilization and demobilization costs. Id. The provision at issue conditioned payment of amounts “agreed to” on performing “all the work” required to complete the entire project: [T]he Contractor, for and in consideration of the payment or payments herein specified and agreed to by the Department, hereby covenants and agrees to furnish and deliver all the materials and to do and perform all the work and labor required in the construction of project Chena Hot Springs Road Widening. Id. (emphasis in original). QAP argued that the State had to pay it the price “agreed to” for mobilization and demobilization under this provision. Id. The Alaska Supreme Court rightly held that the second clause of the above sentence “clearly links” such payments to performing all work necessary to build the entire Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 12 of 19 190 10 4821-9022-0103v.4 0104668-000001 project. Id. (“But Quality did not deliver all the materials, and it did not perform all the work.”). Quality Asphalt therefore stands for the plain conclusion that, when a contract explicitly conditions payment on completion of the entire project, failure to complete the entire project precludes such payment. There is no such provision here. Orion does not rely on a section that explicitly predicates recovery on completion of the entire project. Nothing in the contract precludes recovery of Mob/Demob before the entire project is complete, let alone as explicitly as in Quality Asphalt. Quality Asphalt simply does not resolve the issue here: how does a termination for convenience change what “submittals [are] required under the Contract”? ER 150 (emphasis added). As Orion has argued, and which Seward has not seriously disputed, a termination for convenience limits which submittals are “required.” By Seward’s own admission, it had received all required submittals, thereby triggering its obligation to pay Orion. C. Seward’s Other Arguments Regarding Orion’s Recovery Are Unavailing. Seward’s reference to the “Original Contract Amount” listed in an Orion invoice does not mean “Orion was agreeing that its work would not be ‘complete’ until it invoiced another $5.2 million.” Appellee’s Brief at 19. All the invoice shows is the price for the entire contract, including all four phases. SER 23. The Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 13 of 19 191 11 4821-9022-0103v.4 0104668-000001 invoice has nothing to do with how Seward would pay Mob/Demob should the parties terminate the contract early and Orion provide “all submittals required under the Contract.” ER 150. It certainly does not qualify, by Seward’s reading, as Orion “agreeing” it had to provide all submittals for all four phases before receiving the balance of its Mob/Demob bid item. Rather, the termination for convenience changed which submittals were “required,” so Orion triggered full payment of Mob/Demob by providing all submittals required after completing the Base Bid phase. Seward wrongly asserts, for the first time on appeal, that Orion has not provided all required submittals. Appellee’s Brief at 18. The Court should disregard this allegation, presented for the first time on appeal. See Japanese Vill., LLC v. Fed. Transit Admin., 843 F.3d 445, 455 (9th Cir. 2016). Orion did, in fact, provide all required submittals. In its pre-closeout letter, Seward provided a list of submittals “required prior to final payment request.” ER 185 (emphasis added). Orion provided those materials, and Seward confirmed as much in its January 16, 2015, closeout letter: “The closeout submittals provided were accepted . . . . The referenced contract with the City of Seward is closed.” ER 187. In the years since then, Seward has never contended that Orion still had more submittals to provide. Seward’s argument to the contrary is not supported by the evidence and should be disregarded as untimely. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 14 of 19 192 12 4821-9022-0103v.4 0104668-000001 Seward again mischaracterizes Orion’s argument as premised on the termination for convenience creating a “new contract.” Appellee’s Brief at 21. Orion has never argued that. The termination for convenience did not create a new contract: it merely narrowed the meaning of “all submittals required under the Contract” by reducing the scope of what was “required.” ER 150. After the termination for convenience, submittals for later phases were not “required,” so providing submittals following the Base Bid phase triggered full payment of Mob/Demob under Section 01505. ER 150. Seward has consistently miscast Orion’s argument on this point. The district court erroneously adopted the flawed argument in its order by casting Orion’s argument as calling for a “new” contract. ER 11. There is no “new” contract, the termination simply reduced the number of submittals which were required. Orion provided the required submittals, so Seward must pay the balance of Mob/Demob. This argument does not depend on creating a “new” contract. D. Orion Has Not Made New Arguments, and Leaves the Disposition of the Motion to Strike to the Parties’ Briefing on That Issue. Seward’s brief closes with more argument regarding its Motion to Strike certain portions of the Excerpts of Record submitted by Orion. Briefing on that issue has closed and Seward’s additional argument is improper. Orion stands on Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 15 of 19 193 13 4821-9022-0103v.4 0104668-000001 the points it raised in its opposition to Seward’s motion. The only portion of Orion’s Argument in its opening brief that references the portions Seward has sought to strike is a short citation to Bryce Erickson’s “shock” after Seward refused to pay. Appellant’s Brief at 23. Orion’s argument does not depend on this fact, and it included it to give the Court the necessary background as required by the Circuit Rules. CONCLUSION Seward has consistently miscast Orion as making a “tidy profit.” Appellee’s Brief at 25. That is far from the case. The contract provides that Seward must pay Orion the entire amount bid for Mob/Demob after Orion completed demobilization and Seward received and approved all submittals required by the contract. Seward did so, but has refused to pay Orion the balance of the Mob/Demob bid item. Essentially, Seward has received full performance of the Base Bid work but wants to pay only 75% of the Base Bid price. The district court erred when it misinterpreted the contract and allowed Seward to retain this windfall. Orion respectfully requests that the Court reverse the district court’s // // // Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 16 of 19 194 14 4821-9022-0103v.4 0104668-000001 order decision granting Seward’s motion for summary judgment and denying Orion’s motion for summary judgment. RESPECTFULLY SUBMITTED this 5th day of May, 2017. DAVIS WRIGHT TREMAINE LLP TRAEGER MACHETANZ By s/ Traeger Machetanz TRAEGER MACHETANZ Attorneys for Plaintiff-Appellant ORION MARINE CONTRACTORS, INC. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 17 of 19 195 4821-9022-0103v.4 0104668-000001 CERTIFICATE OF COMPLIANCE This brief has 3,212 words and therefore complies with the length limits permitted by Ninth Circuit Rule 32-1. The brief’s type size and type face comply with Fed. R. App. P. 32(a)(5) and (6). DATED this 5th day of May, 2017. DAVIS WRIGHT TREMAINE LLP TRAEGER MACHETANZ By s/ Traeger Machetanz TRAEGER MACHETANZ Attorneys for Plaintiff-Appellant ORION MARINE CONTRACTORS, INC. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 18 of 19 196 4821-9022-0103v.4 0104668-000001 CERTIFICATE OF SERVICE I hereby certify that on May 5, 2017, I electronically filed the foregoing with the Clerk of the Court for the United States Court of Appeals for the Ninth Circuit by using the appellate CM/ECF system. I hereby further certify that all participants in the case are registered CM/ECF users and that service will be accomplished by the appellate CM/ECF system. DATED May 5, 2017. DAVIS WRIGHT TREMAINE LLP TRAEGER MACHETANZ By s/ Traeger Machetanz TRAEGER MACHETANZ Attorneys for Plaintiff-Appellant ORION MARINE CONTRACTORS, INC. Case: 16-35919, 05/05/2017, ID: 10424314, DktEntry: 30, Page 19 of 19 197