A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
SEWARD, ALASKA, ESTABLISHING RATES AND CHARGES FOR
ELECTRIC POWER FOR THE PERIOD COMMENCING JULY 15, 1987
WHEREAS, Section 22.6 of the Seward City Code requires
that electric rates and charges be fixed by resolution; and
WHEREAS, Section 22.40 (c) requires the payment of a
monthly television service charge; and
WHEREAS,
recommended a
and
1987 Cost of Service and Rate
adjustment effective July 15,
Study
1987;
a May
revenue
WHEREAS, the Seward Ci ty Counc i 1 wi she s to amend the
electric rate to effect a revenue decrease and a more
equitable distribution of charges to customers;
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF SEWARD, ALASKA, that:
Section 1. The schedule of rates for electric power is
hereby established by class as follows:
GROUP
$ COST/KWH
$ DEMAND/KWH
INSIDE
CITY
OUTS IDE
CITY
Residential
$
$17.90
$19.69
$ 0.0808
Small General
Service (Less
than 50KW)
0.0980
36.25
45.49
Large General 0.0259
Service (Great-
er than 50KW)
28.31
45.49
36.25
Street Lights
36.25
0.1188
Special Contracts -- to be determined to meet requirements
of user and subject to approval of City Council.
Section 2. Special Contracts may be negotiated by the
Utilities Manager with customers that have a demand in
excess of 750 KW or that have unique power requirements that
cannot be reasonably addressed by the large general service
tariff. Special Contracts may include, but are not limited
to, provisions for instantaneous demand charges, time of
-1-
.
.
.
CITY OF SEWARD, ALASKA
RESOLUTION NO. 87-048
service, interruptible power, minimum and maximum demand,
adjustment of demand level, ownership and payment of new
distribution facilities, termination charges, and power
factor. Special contracts will be approved by the Council.
Section 3. Demand charges will be based on the maximum
demand recorded over a 30-minute period, except if other
provisions are included in a special contract.
Section 4. Existing large general service customers
will be charged an energy rate of $0.1006 per KWH without a
demand charge until demand meters are installed and at least
3 months of demand data has been recorded. The utility will
provide a sample demand base billing during the 3-month
period, and demand billing will begin with the fourth
billing month. If the demand bill is unreasonably high or
low (t 10%), the test period will continue for an additional
3 months. If the bill cannot be resolved after 6 months,
the utility may request Council to approve a special con-
tract. In any case, a large general customer with demand
metering will be charged according to the demand tariff
within 12 months from the date the demand meter was in-
stalled.
Section 5. New large general service customers con-
nected to service following the effective date of this
resolution will be charged according to the demand tariff.
Section 6. Monthly fuel adjustment surcharges will be
charged to all customers to reflect the fuel adjustment
factor charge by CEA and the cost of operating the city of
Seward standby power plant. These will be in two separate
surcharges as follows:
A.
from CEA
customers
customers
CEA Fuel Adjustment. The fuel adjustment charge
directly distributed to Seward Electric Utility
prorated according to the number of KWH the
consumed during the billing period.
B. Seward Fuel Adjustment. The cost of operating the
standby generation plant, including fuel, labor, maintenance
and repair when it exceeds the amount budgeted to date for
the fiscal year. The cost will be prorated according to the
number of KWH the customer consumed during the billing
period.
Section 7. The cost of operating the standby gen-
eration plant to meet a specific customer I s need will be
charged directly to that customer. Such cost will be the
total cost of operating the plant, including fuel, labor,
overtime, maintenance, repair and overhead, less the
-2-
.
.
.
CITY OF SEWARD, ALASKA
RESOLUTION NO. 87-048
ATTACHMENT "A"
EXISTING FACILITIES
SCHEDULE OF FEES AND CHARGES
ZONE I Inside City Limits (Excluding Small Boat Harbor)
ZONE II City Limits to Mile 12, Seward Highway, and all
roads connecting Highway within this area
ZONE III - Mile 12 to Lawing
ZONE FEE OR CHARGE
I
Meter Testing-Each Test-When
Previous Test Occurred within
24 Months..................... $ 50.00
Reconnection to Approved Exist-
ing Meter Installation........ 20.00
Reconnection to Approved Exist-
ing Meter Installation Outside
Regular Business Hours........ 140.00
New Connection Fee............ 150.00
Deposit-Residential Account... 100.00
Deposit-Commercial or Indus-
trial Account................. 200.00
Deposit-Interruptible, Off-
Peak Account, twice estimated
monthly bill, whichever lS
larger........................ 200.00
Tampering with or unauthorized
breaking of meter seal........ 500.00
Per Annum Interest on Delin-
quent Account................. 12%
Dishonored Check Fee.......... 10.00
Reconnection during Regular
Business Hours (After Discon-
nection of Delinquent Account) 40.00
Reconnection Outside Regular
Business Hours (After Discon-
nection of Delinquent Account) 140.00
-4-
III
II
$ 70.00
$ 90.00
25.00
30.00
170.00
200.00
150.00
150.00
100.00
100.00
200.00
200.00
200.00
200.00
500.00
500.00
12%
12%
10.00
10.00
50.00
60.00
170.00
200.00
I.
CITY OF SEWARD, ALASKA
RESOLUTION NO. 87-048
ATTACHMENT "B"
NEW FACILITIES
ENGINEERING SERVICE CHARGE
SCHEDULE OF FEES AND CHARGES
ZONE FEE OR CHARGE
Non-refundable until the service is
service is constructed and connected,
actual cost of engineering service.
connected. If the
the charge will be
I II III
Temporary Secondary Service. . . $ 50.00 $ 60.00 $ 70.00
Primary Overhead Extensions
(Residence) . . . . . . . . . . . . . . . . . . . 50.00 60.00 70.00
Primary Underground Extensions
(Residence) . . . . . . . . . .. . . . . . . . . 50.00 60.00 70.00
Secondary Service. . . . . . . . . . . . . 50.00 60.00 70.00
. Primary Overhead Extensions
(Subdivision, Mobile Home
Park, Multi-residence)........ 100.00 120.00 140.00
Primary Overhead Extensions
(Commercial and Industrial)... 200.00 240.00 260.00
Primary underground Exten-
sions (Commercial and Indus-
tr ia l) . . . . . . . . . . . . . . . . . . . . . . . . 200.00 240.00 260.00
Modifications of Existing
Facilities.................... 100.00 120.00 140.00
Street Lighting Systems and
Yard Lights. . . . . . . . . . . . . . . . . . . 50.00 60.00 70.00
.
-5-
.
.
.
CITY OF SEWARD, ALASKA
RESOLUTION NO. 87-048
wholesale value of energy generated in excess of the custom-
er's need.
Section 8. The monthly yard light charge for 175 watts
shall be $6.75 and for 250 watts shall be $10.00.
Section 9. Miscellaneous charges shall be assessed in
accordance with Attachments A and B, incorporated herein by
reference.
Section 10.
$4.00.
The monthly television charge shall be
Section 11. The rates, charges and provisions set
forth in this resolution shall become effective July 15,
1987.
Section 12.
hereby appealed.
City of Seward Resolution No. 85-55 is
PASSED AND APPROVED BY THE CITY COUNCIL OF THE CITY OF
SEWARD, ALASKA, this 22 day of June , 19 87 .
THE CITY OF SEWARD, ALASKA
~.c~~
Hf!{RRY GIESEL, MAYOR
AYES:
NOES:
ABSENT:
ABSTAIN:
DUNHAM, GIESELER, HILTON, MEEHAN, NOLL & SIMUTIS
NONE
BOOHER
NONE
ATTEST:
APPROVED AS TO FORM:
HUGHES, THORSNESS, GANTZ,
POWELL & BRUNDIN, Attorneys
for the City of Seward, AK
7~N~.
Fred B. Arvidson
City Attorney
(City Seal)
-3-