HomeMy WebLinkAboutRes2010-100 Sponsored by: Oates
CITY OF SEWARD, ALASKA
RESOLUTION 2010 -100
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD,
ALASKA, APPROVING EMERGENCY REPAIRS IN THE AMOUNT OF
$330,886 FOR FLOOD DAMAGE AT THE LOWELL CREEK BRIDGE
AND APPROPRIATE FUNDS
WHEREAS, Seward and the surrounding vicinity experienced extreme flooding in 2006
causing damaged infrastructure throughout the community; and
WHEREAS, the City declared this event a disaster; and
WHEREAS, the event resulted in a federal disaster that enabled the City to qualify for
FEMA assistance for damaged infrastructure; and
WHEREAS, during the incident period, severe storm flood waters and debris from the
tunnel above Lowell Creek Bridge caused substantial bridge damage; and
WHEREAS, the City installed temporary jersy barriers to replace the damaged guard rail
at this location; and
WHEREAS, the City does not have the staff expertise in bridge engineering and design
to manage these repairs; and
WHEREAS, PND was hired shortly after the flood incident to help the City inspect and
assess the damage and costs associated with the flooding event; and
WHEREAS, PND Engineers, Inc. has provided excellent services at competitive prices
for the City of Seward; and
WHEREAS, PND has provided a project cost of $330,886 to complete the damaged
bridge prior to the grant deadline of December 8, 2010; and
WHEREAS, the City desires to enter into a contract with PND to develop bid
documents, coordinate ordering of materials, and manage construction of the bridge
replacement /repairs; and
WHEREAS, it is in the City's best interest to utilize PND's services in a timely fashion
to avoid project delays; and
WHEREAS, the City, after four years, was recently notified that FEMA funding is
available but if we do not complete the bridge repair prior to December 8, 2010 the City is at risk
of losing the FEMA reimbursable funding of not less than $136,189; and
CITY OF SEWARD, ALASKA
RESOLUTION 2010 -100
WHEREAS, to meet the federal funding time constraints, it is necessary to move quickly
to authorize the purchase and delivery of materials for the project; and
NOW, THEREFORE, BE IT RESOLVED BY THE COUNCIL OF THE CITY OF
SEWARD, ALASKA:
Section 1. The City Manager is authorized to enter into a sole source agreement between
the City of Seward and PND Engineering Inc. for professional services in the amount of
$49,086.00, in substantially the form presented at this meeting.
Section 2. The City Manager is authorized to purchase the necessary materials and
supplies described as "Owner Provided Materials" on the project cost estimate from PND
(presented at this meeting) subject to the following conditions: At least three competitive bids
will be obtained and the City will select the lowest bid for purchase of materials and supplies and
delivery to Seward at a location approved by the City Manager or his designee. All materials
and supplies are to be delivered on or before November 23, 2010 or such other date approved by
the City Manager or his designee that will not adversely impact the ability to have all work
completed by December 8, 2010. The cost for all materials and supplies will not exceed
$108,400, provided that the City Manager may amend this amount so long as the total project
cost does not exceed $330,886.
Section 3. The City Manager is authorized to seek bids for the construction and repair of
the Lowell Creek Bridge for an amount not -to- exceed $173,400 not including a contingency.
Section 4. The total project cost will be an amount not -to- exceed $330,886 and FEMA
will reimburse not less than $136,189.
Section 5. The recitals above are incorporated by reference. The severe flooding and
delay in receipt of reimbursable funding support the conclusion that the repairs to the Lowell
Creek Bridge constitute an emergency situation.
Section 6. The City Council hereby appropriates $330,886 from the General Fund
reserves account 101- 0000 -3050 to the General Fund roads /streets contracted services account
no. 101 - 1310 -5390 for the purposes of performing emergency repairs on the Lowell Creek
Bridge resulting from storm damage.
Section 7. This resolution shall take affect immediately upon its adoption.
CITY OF SEWARD, ALASKA
RESOLUTION 2010 -100
PASSED AND APPROVED by the City Council of the City of Seward, Alaska, and this 25th
day of October, 2010.
THE CIT ,,,IISEWARD, ALASKA
AO
illard E Dunham, Mayor
AYES: Valdatta, Bardarson, Smith, Keil, Shafer, Casagranda, Dunham
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST:
Jea i Lewis, CkIC
_ mow,
City Clerk 0.4j � ,',
(City Seal) .•
•
0
A �
*
w
• b
Y r
• N ° �" ♦ ♦
* **" I t OF� ar 44 *
s
Council Agenda Statement
Meeting Date: October 25, 2010 SEA
To: Phillip Oates, City Manager N qF
From: William Casey, Public Works qt P
Agenda Item: Approving Emergency Repairs in the amount of
$331,000 for Flood Damage at the Lowell Creek
Bridge and Appropriate Funds
BACKGROUND & JUSTIFICATION:
Seward and the surrounding vicinity experienced extreme flooding in 2006 causing damaged
infrastructure throughout the community. The City declared this event a disaster and the event
resulted in a federal disaster that enabled the City to qualify for FEMA assistance for damaged
infrastructure. The City has sought federal funding since 2006 and was recently notified that
$131,189.00 is available but must be used by December 8, 2010.
During the incident period, severe storm flood waters and debris from the tunnel above Lowell
Creek Bridge caused substantial bridge damage. The City installed temporary jersy barriers to
replace the damaged guard rail at this location. The City does not have the staff expertise in
bridge engineering and design to manage these repairs. PND was hired shortly after the flood
incident to help the City inspect and assess the damage and costs associated with the flooding
event. PND Engineers, Inc. has provided excellent services at competitive prices for the City of
Seward. PND has provided a project cost of $330,886 to complete the damaged bridge prior to
the grant deadline of December 8, 2010. It is in the City's best interest to utilize PND's services
in a timely fashion to avoid project delays. If we do not complete the bridge repair prior to
December 8, 2010 the City is at risk of losing the FEMA reimbursable funding of $136,189. To
meet FEMA's deadline, PN &D began working on this project and therefore council is asked to
approve the professional services agreement retroactively to October 6, 2010. The purchase of
materials and bids for a construction contract will be subject to the conditions set forth in the
resolution. A construction contract is expected to be presented for council approval in
November.
INTENT: Council authorizing the City Manager to 1) enter into a sole source agreement between the
City of Seward and PND Engineering Inc. for professional services in the amount ofNTE $49,086, 2)
purchase the necessary supplies and 3) seek bids for the construction and repair of the bridge. The
total construction cost is estimated at for an amount not -to- exceed $281,800 including no
contingency for a total project cost not -to- exceed $330,886 and not less than $136,189 will be
reimbursed by FEMA.
FISCAL NOTE:
The City Council hereby appropriates $330,886 from the General Fund reserves account 101 -0000-
3050 to the General Fund roads /streets contracted services account no. 101 - 1310 -5390 or the
purposes of performing emergency repairs on the Lowell Creek Bridge resulting from storm damage.
Approved by Finance Department: ‘2113
6
ATTORNEY REVIEW: Yes X No
RECOMMENDATION:
Council supports Resolution 2010- 100 authorizing the City Manager to enter into a sole source
agreement between the City of Seward and PND Engineering Inc. for professional services in the
amount of $49,086, purchase the necessary materials and bid the construction to complete emergency
repairs on Lowell Creek Bridge for an amount not -to- exceed $281,800 including not contingency a
for a total project cost not -to- exceed $330,886. FEMA will reimburse the City no less than $136,189.