HomeMy WebLinkAboutRes2020-069 Sponsored
OF SEWARD,ALASKA by: Meszaros
RESOLUTION 2020-069
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD,
ALASKA,AUTHORIZING THE CITY MANAGER TO ENTER INTO A
PROFESSIONAL SERVICES CONTRACT WITH THE FINANCIAL
ENGINEERING COMPANY, TO PREPARE A RATE STUDY FOR THE
ELECTRIC ENTERPRISE FUND FOR AN AMOUNT NOT-TO-EXCEED
$40,000,AND APPROPRIATING FUNDS
WHEREAS, the City of Seward will start the process of negotiating a new Power Sales
Agreement as the contract with Chugach Electric Association(CEA)will expire the end of 2021;
and
WHEREAS, the City Electric Utility will want to have a clear understanding of the cost
of providing power to all classes of customers so that negotiations for a new power sales
agreement can be tailored to provide each class of customers with the lowest cost power
available; and
WHEREAS, the laws of the State of Alaska require public utilities to charge customers
based on the principles of cost causer, cost payer; and
WHEREAS, the City's Electric Utility should consider the need to have different rate
classes of customers so that each class can be charged according to cost causer, cost payer
principles; and
WHEREAS,the City's Electric Utility has not changed rates since 2018, and the Electric
Rate Study has not been done since 2014; and
WHEREAS, the City of Seward needs to make sure that the utility is providing reliable
power at the lowest cost possible; and
WHEREAS, a rate study will undertake a complete look at the cost of providing reliable
power to those served by the City of Seward; and
WHEREAS, a rate study will also ensure that each class of ratepayers will pay
appropriate rates for their electric service including the costs of connecting services and other
charges for connection and disconnection; and
WHEREAS, the Electric Utility has recently installed a new metering system that could
affect the fees and charges allocated to customers; and
WHEREAS, Michael Hubbard of The Financial Engineering Company has provided
professional services for City of Seward previously and is qualified and capable of performing
CITY OF SEWARD, ALASKA
RESOLUTION 2020-069
the Electric Enterprise Fund rate study; and
WHEREAS, Hubbard is available to do this study in an expeditious manner; and
WHEREAS, The Financial Engineering Company can do this study for an amount not-
to-exceed $40,000; and
WHEREAS, The Financial Engineering Company can be contracted for these services
consistent with the City's bid procedures, as read in section 6.10.120 of the City Code, which
allows for an exemption of competitive bidding for the procurement of professional services.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF SEWARD, ALASKA that:
Section 1. The City Manager is hereby authorized to enter into a Professional Services
Contract with The Financial Engineering Company to include an Electric Rate Study.
Section 2. The contract will be performed at a cost not-to-exceed $40,000.
Section 3. Funding in the amount of$40,000 is hereby appropriated from Electric Fund
unassigned fund balance account no. 15000-0000-3400 to contracted services account no 15000-
3000-7009.
Section 4. The City Manager shall have a rate study"kick off' session at a Council
meeting or at a Council work session within 30 days of the passage of this Resolution.
Section 5. This resolution shall take effect immediately upon adoption.
PASSED AND APPROVED by the City Council of the City of Seward, Alaska, this
24th day of August, 2020.
T . Y 1FS • '.i, ALASKA
1.4 „,,gar
Christy Ter , , Mayor
CITY OF SEWARD, ALASKA
RESOLUTION 2020-069
AYES: Baclaan, McClure, Seese, Osenga, Terry
NOES: None
ABSENT: None
ABSTAIN: Crites (This item was approved on consent; Council Member Crites abstained
from voting on the Agenda and Consent Agenda due to a Conflict of Interest for other items on
Consent)
ATTEST:
rends J. Ballo M
City Clerk
.•tt•. OF SE ''•,
.'�• •V�.•'•GO�°R1T•'•.Q� o,
•
• SEAL `.• • 11.
.
•
.
• •
•
F �OFP�p',it'
Agenda Statement
Meeting Date: August 24, 2020
To: City Council
Through: Scott Meszaros, City Manager
From: Cory Borgeson, Interim Electric Director
Agenda Item: A Resolution of the City Council of The City of Seward,Alaska,Authorizing
the City Manager to Enter Into a Professional Services Contract with the
Financial Engineering Company, to Prepare a Rate Study for the Electric
Enterprise Fund for an Amount Not-To-Exceed$40,000,and Appropriating
Funds.
BACKGROUND & JUSTIFICATION:
The setting of just and reasonable rates is one of the most important decisions a governing body of
utility undertakes. Since the City of Seward Electric is not subject to rate regulation by the
Regulatory Commission of Alaska,this responsibility takes on even more significance. Alaska law
requires utility rates be just and reasonable and allocate costs based on the principals of cost
causer/cost payer.
Seward's rates structure for residential users has three components;
1. Customer Charge which is supposed to represent the cost of hooking onto the
system,
2. Utility Charge which covers the operations and interest and depreciation expense of
the utility; and
3. the cost of Power which is a pass thru of energy costs which represents Seward's
costs of power from Chugach Electric.
For commercial users, there are an additional charge called the demand charge which ensures that
large users pay enough in rates to cover their peak electric usage. This rate study will look at these
rates as well as analyze the revenue requirements for the utility.
The City last did a rate review in 20I6/2017. There have been adjustments to rates based on the
consumer Price Index. The cost of power is adjusted monthly as Chugach Electric's rates for
Seward fluctuate monthly.
There are several reasons for doing a comprehensive rate study, including, but not limited to: the
need to look at industrial rates, changing costs of operations that are not reflected by CPI, and
changes in electric loads and usage that could change allocation of costs among classes of customers.
When setting electric rates, a utility's goal is twofold. First and foremost is to set rates to recover
adequate revenues. Second, the utility should strive to set rates for each customer class close to the
allocated cost of service. This helps ensure that the cost causer is the cost payer.
209
The second goal of setting rates close to the allocated cost of service,can only be achieved through a
study that requires large amounts of staff time or the expense of hiring outside consultants. For this
reason, utilities typically perform studies on an infrequent basis and implement interim rate
adjustments on an"across-the-board"basis where all rates are adjusted by the same percentage or by
the same amount.
The All Requirements Power Sales Agreement with Chugach Electric will end in December of 2021.
Performing this study will help the City understand the electric needs of Seward's citizens resulting
in fair and reasonable rates based on electric consumption. This will also allow Seward to gain
information that can help negotiate a new Power Sales Agreement that can better incorporate
Seward's industrial users. These factors indicate it is time to do a full rate case and not set interim
rates for two more years.
Mike Hubbard of Financial Engineer Company has worked with the City of Seward for the past ten
years. His proposal (which is attached)sets the cost at just under$40,000 and certainly reflects his
knowledge base. Using the Financial Engineer Company saves the City costs and will allow for an
efficient rate study process. This rate study should take between four to six months with the goal of
having it completed in four months.
Also, this contract with the Financial Engineering Company is consistent with the City's bid
procedures as quoted below in section 6.10.120 of the City Code,which allows for an exemption of
competitive bidding of professional services:
"Professional services are those that require special knowledge and judgment that
includes analysis, evaluation, prediction, planning or recommendations and which result
in the production of a report or the completion of a task. Examples of professional
services include accounting, architectural, appraisal, engineering, land surveying,
financial consultation, legal services, lobbying, planning, economic analysis, computer
programming and system analysis, insurance consultation and risk analysis, and other
specialized services."
INTENT:
Enter into a Professional Services Contract with the Financial Engineering Company, to prepare a
rate study for the Electric Enterprise Fund for an amount not-to-exceed$40,000.
CONSISTENCY CHECKLIST: Yes No NIA
1. Comprehensive Plan: x
2. Strategic Plan: x
3. Other:
FISCAL NOTE:
Funding for this contract will come from Electric Fund reserves and expended to the contracted
services account.
Approved by Finance Department:
210
ATTORNEY REVIEW: Yes X_ No Not Applicable
RECOMMENDATION:
City Council approve Resolution 2020-069, authorizing the City Manager to enter into a
Professional Services Contract of the Financial Engineering Company, to prepare a rate study for
the Electric Enterprise Fund for an amount not to exceed$40,000.
211
the 1, inanCial Engineering Company 235 Rockland Street, Rockport, Maine 04856
www,FinEngCo.com Phone: (207)593-913I
Cell/Text: (207)691-8347
E-mail: mhubbard@FinEngCo.com
August 18, 2020
Mr.,Cory Borgeson, Electric Utility Manager
City(of Seward
PO Box 167
Seward, Alaska 99664
Dear Cory.
Attached is a proposed contract for a Cost of Service/Rate Design study for the Electric
Utility. If you have any questions regarding the attached material, please do not hesitate to
call for text me at (207) 691-8347.
Very truly yours,
THE'fINANCIAL ENGINEERING COMPANY
MICHAEL D. HUBBARD
212
CONTRACT
Thq Financial Engineering Company ("FEC") shall provide the following work for the City of
Seward ("City") regarding a cost-of-service/rate study for the City's Electric Utility.
METHODOLOGY
Overall — A cost-of-service study is to be performed that properly allocates the Electric
UtiiGty's revenue requirements to each customer class. Although the utility is not rate
regulated by the Regulatory Commission of Alaska ("RCA"), the work will be performed
using the guidelines set by the RCA for regulated utilities. Thus, revenue requirements will
be allocated to each customer class using appropriate functionalization, classification, and
allobation factors set forth in the cost allocation manual developed by the National
Association of Regulatory Utility Commissioners (the "NARUC Manual"). Rates will then be
designed such that the revenues collected from each customer class will be approximately
equal to the allocated revenue requirements. In this way, the "cost causer" becomes the
`"cost payer."
The study will be similar to past studies performed for the City but will include an analysis
regarding the establishment of an Industrial rate for very large customers. The adequacy of
rates will be reviewed over a two-year period commensurate with the current budget cycle
(20�0/2021).
The City also desires to compare its electric rates with those of other Railbelt utilities as well
as various other utilities in the State. These comparisons can then be used to make
decisions regarding the need to implement budget adjustments going forward.
Task 1 - Data Request. A data request will be prepared and forwarded to the City. Once
the data is received, it will be reviewed and a preliminary analysis will be performed
regairding potential rate classes, revenue adequacy and other metrics.
Task 2 — Initial Meeting (virtual). Once the preliminary analysis is performed, a virtual
meeting (via Zoom or similar) will be held between City staff and the Financial Engineering
Company. The purpose of the meeting is to:
• Review the proposed scope of work and make necessary clarifications,
modifications, or additions.
• Review data collected from the initial data request and obtain supplemental
information as necessary.
• Discuss known factors that will change historical operating results. (This
process, referred to as normalizing revenue requirements, is discussed in greater
detail below.)
• Discuss billing history and how billing determinants may change in the near
future.
- 1 -
213
• Discuss the preliminary findings.
Task 3 — Model Update/Analysis. The Revenue Requirements/Cast-of-Service/Rate Design
model developed for previous studies will be updated and modified to provide a two-year
forecast using the preliminary budgets for 2020/2021. The model will also include actual
2078 operating expenses and expected expenses for 2019 to illustrate changes in line-item
budget amounts. Projected revenues will be based on assumed billing determinants and
existing rates. Billing determinants will be equal to recent history but modified based on
conlversations with staff.
The model will then allocate the revenue requirements to the various customer classes
basbd on industry-accepted principles. In general terms, variable costs are allocated based
on each class' respective energy requirements, fixed generation and distribution costs
allocated based on each class' contribution to coincident and non-coincident peak, and
customer-related costs based on number of customers. At times, direct assignments are
used where costs can be attributed to a specific customer class. Demand data is typically
difficult to obtain for those classes that are not demand metered, but the Financial
Engineering Company has developed methodologies for estimating these amounts, and
these methodologies have been accepted by the Regulatory Commission of Alaska.
As part of the analysis, the model shall be modified to include an option of establishing an
additional Industrial rate class for very large customers. Billing data of large customers shall
be reviewed to determine a logical threshold for this new rate class.
Options will be explored that can be implemented to smooth large swings in the monthly
Fuel Cost Adjustment will be investigated. Historical amounts will be reviewed as well as
the Cause of any large swings. From this, options can be developed and provided to the City
for consideration,
The model will be developed using the Excel platform.
Task 4 — Rate Design. The rate model will determine the adequacy of rates under several
scenarios. These scenarios include the following.
M Overall adequacy. The total utility revenues projected to be collected for 2020 and
2021 will be compared to the total utility revenue requirements for each year based
on the following rates.
o Existing rates
o CPI adjustment for 2021 only
o Other adjustments
• Individual Rate Class. How close each rate class' rates are set to cost-of-service will
be determined by comparing the revenue requirements allocated to the rate class to
the projected collected revenues from the rate class. Revenues will be based on the
adjustments described above.
- 2 -
214
Industrial Rate. As described in Task 3, the option of establishing an Industrial rate
for very large customers shall be included in the model. The analysis and summary
of findings will include both with and without a new Industrial rate.
In order to facilitate the understanding of overall rate adequacy and the comparison to
other rates (Task 5), an analysis shall be performed that shows how budgeted revenue
requirements must change for each $0.025/kWh in rates. In other words, if existing rates
were to be reduced by $0.025/kWh, the budget must be decreased by "x amount" to
maintain adequate revenues.
Task 5 — Other Rates. Rates of the Railbelt utilities and selected other utilities within the
State will be collected and a comparison made to those of Seward. The comparison will be
made for each rate class of Seward and will show monthly bills for various usage levels. The
comparison will separate base rates and fuel cost adjustments in the event inferences can
be made.
If the rates developed in Task 4 are higher than other utilities, a summary shall be provided
that shows the budgetary reductions required for rate parity.
Task 6 — Written Report. A written report describing the analysis and findings will be
prepared. The report shall also make reference to industry-accepted practices so that the
reader will know that the analysis was performed with no hidden agendas and would meet
the requirements of an RCA review. The report shall be written such that those not
knowledgeable of the electric utility industry can understand the work performed.
Task 7 — Presentations. A virtual presentation shall be made to the City Council. The
presentation shall summarize the report and provide the Council and public opportunities to
have any questions and concerns addressed. The presentation will include a review of
curront and proposed rates and the calculation of a customer's bill for each rate class.
Task 8—Refinement. The analysis, rate development, and report will be refined, if required,
based on any concerns of the Council.
BUDGET
A budget to perform the scope of work has been prepared and is summarized in
Attachment 1. The budget is based on two site visits (preliminary and presentation).
Should a second meeting with Council be required, costs for that work and meeting are
separately identified. The work can be performed on a fixed-fee basis or a time and
materials with the total billing not to exceed the amount shown in the Attachment.
- 3 -
215
Approved by:
Michael D Hubbard Cory R. Borgeson
the Financial Engineering Company City of Seward
Approved by the Seward City Council on
- 4 -
216
CITY OF SEWARD-ELECTRIC DEPARTMENT
RATE STUDY
Budget
TASK HOURS Labor Expenses Total
1 Data Request/Initial Analysis 32 $ 6,400 $ 6,400
2 Initial Meeting/Data Refinement 8 1,600 1,600
3 Model Modification/Update 40 8,000 8,000
4 Rate Design 54 10,800 10,800
5 Other Rate Review 8 1,600 1,600
6 Report 24 4,800 4,800
7 Presentations 4 800 800
TOTAL 170 $ 34,000
$ 34,000
8 Second Presentation
Preparation 16 $ 3,200 $ 3,200
Presentation 2 400 400
Subtotal 18 $ 3,600 $ - $ 3,600
TOTAL 188 $ 37,600 $ - $ 37,600
- 5 -
217