HP SIGNAGE PROJECT Tanguy Libbrecht
TIMELINE (WORKING PLAN) 6/10121
DATE
TIMELINE
WHO
Notes
Research and Collaboration with Property Owners
Property load to be shared amongst
Ongoing
MB, CS, SW, TL, FW
commissioners. Ongoing task.
Ongoing
Finalize Priority List
MB, CS, SW, TL, FW
Completed
Weekly Work Session (publicly noticed) every
Friday @ 10AS AM-11:45 AM. Started on this date:
Separate doc.
Standing agenda by committee being created by
Libbrecht to detail agenda of weekly meetings
Any laydowns to be submitted before meeting.
1/22/2021
HP Commission
Notes will be kept for legislative history
Vote on and finalize list above funding line at the
Mary Ann will present latest recommendations
2/11/2021
Feb. 11 HP Meeting
HP Commission
from the committee.
Send letters-- To Let people know they are above
funding line for a sign or on list for next grant but
will be on tour.
We can still collect their info to work on signs and
info for tour after we finish the 25.
Alert people of sign permit (PC F from Andy Bacon)
and terms of sign agreement (TYL to develop 1
Letter ready for approval at Feb 11 Meeting.
2/18/2021
a er).
Tanguy
Both for above and below funding line.
No intent to put people into a 20' Setback.
Bigger concern is city of right of way (Street)
Identify where line is. On second between
washington and adams, houses are built right
up into street. Granfathered. Tricky part is
looking at a case by case basic. Setback is
defined as required minimum difference from
right of way or lot line only landscapting,
Send list of properties to receive signs, emails,
partking, etc is permitted. Will send letter and
addresses to Andy Bacon for sign permits which he
properties and permit. Does not need to know
2/25/2021
will email out for electronic signatures.
Mary Ann
size.
Ms. Kingsland noted this as a reasonable
2/28/2021
Grant Report (Progress) to State of AK
Valarie
timeline, Need to verify report was received.
All photo requests in to Mary Ann (SCLA needs
Cannot guarantee sign will be complete if not
3/3/2021
them by the 5th to meet our timeline).
All Commissioners
received by this time. Ongoing requests.
Order all pictures and pay for them: SCLA, UAA,
Ongoing orders. May take a couple of days to a
Ongoing
Anchorage Museum, State of AK
Mary ann to provide to Tanguy order
couple of weeks: Time sensitive
Sign Creation- Initial and edits with Mary Ann,
Cannot guarantee sign will be complete if not
3/21/2021
review with RBHS and Doug, Lee.
MB, CS, SW, TL
received by this time. Ongoing requests.
14 DAY REVIEW PERIOD STARTS FOR SHPO STAFF
Ongoing review. Katie at state has been
3/31/0221
TO REVIEW AND ACKNOWLEDGE
reviewing in batches.
all materials received back to Mary Ann for any
4/12/21
final review and sent to CORVUS.
Mary and committee Ann
Per Peter as Corvus
Review budget and send updated request to SHPO
Tanguy spoke to state and they will increase
as needed
budget by to $24,000 reimbursed to City.
Match has already been met. Will not result in
4/15/21
Tanguy
extra funding needed by city.
Corvus to review and starts to produce artwork
Mary Ann has provided all revisions to Peter for
review. Once complete will need final review by
4/19/21
Peter and Mary Ann
property owners.
4/30/21
Grant progress report due to SHPO
Valarie Kingsland
Need to let Valarie know this is due
Walking tour narrative is complete and sent to
Cost of map design is going to be included in
5/3/21
Peter, They are going to complete the map
Tanguy is working on this
the orginal design cost
All artwork provided to I -Zone, pre -production and
5/15/2021
fabrication starts
Peter Briggs-Corvus
On Track
Order posts once after reconfirming type of post
Will order next week per Peter, They have
5/20/2021
and number needed
Tanguy and Peter
some in house
6/1/2021
Walking tour map design complete
Peter Briggs-Corvus
In Review
Equipment reserved for install.
City has indicated possible use for Auger for at
least some signs on city property (Parks and
REC) Have reserved equipment at
Ressurection Bay Tool rental. Need to
purchase SONO Tubes and concrete before
Mini Excavator or Auger?
EOM and possible delivery by Home Depot
Manufacturing of signs complete (tentative) and
6/10/2021
shipped (tentative)
I-Zone/Peter to verify
Waiting on Peter to verify shipping date
Engage in fundraising activity to cover any budget
Dndraising commitee is working on this.
shortfall
Committe member/Commissioner Sue Ward
has been working with Volunteer (Former
Commissioner) Iris Darling to fundraise. Rotary
donated $1500 as well. Tanguy is compiling
list of current donors with Finance Dir. Naneth.
Ambrosiani. Total to date including Rotary
Donation is $4600, On top of $24,000 CLG
6/10/2021
Grant, should be fully funded.
Signs received (Tentative)
Sent to Cable House. Could be held with city if
6/21/2021
Received c/o?
they need to be.
Printed maps recevied
Color on one side, black and white narrative on
other, Peter will order and invoice, Tanguy will
qj
pick up. Narrative led by Mary Ann is pretty
6/27/2021
5,000 Maps estimated
much done and in review.
Sign Installation Complete/may require volunteers
May require equipment rental and volunteers
or city collaboration.
coordination. City does not have capacity to
GRANT PERIOD ENDS
help. Will need to find in kind. We are working
on some possibilities dependent on when signs
arrive. Rotary, Commissioners, Open call to
6/30/2021
Volunteer/In Kind Committees
public, LDS?
7/31/2021
IFinal Grant Report Due
IValarie Kingsland