HomeMy WebLinkAboutRes2021-115 CITY OF SEWARD,ALASKA Sponsored by: Bower RESOLUTION 2021-115 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA, AUTHORIZING THE CITY MANAGER TO ENTER INTO A CONSTRUCTION CONTRACT WITH GLOBAL DIVING & SALVAGE INC.,FOR THE REPLACEMENT OF SACRIFICIAL ANODES CATHODIC PROTECTION SYSTEM ON THE CONCRETE SECTION OF THE SEWARD HARBOR FLOAT SYSTEM IN AMOUNT NOT TO EXCEED $150,477.80, WHICH INCLUDES A 10% CONTINGENCY, AND APPROPRIATING FUNDS WHEREAS,in 1999,the Seward Boat harbor went out to bid for engineering and design for the replacement of E,F,H,J and a portion of G-float,in which council approved resolution 99-028 authorizing Tryck Nyman Hayes INC (TNH)to perform these services; and WHEREAS,in Resolution 2000-147 Seward City Council approved Swalling Construction to replace these old wooden floats with concrete floats along with galvanized metal piling with sacrificial anodes; and WHEREAS, in 2020, the harbor had some underwater water line breaks on the concrete section of the harbor while the diver was on site the harbor requested the diver to look at and report how much of the sacrificial anodes were remaining, and WHEREAS, the diver reported over half of the anodes were deteriorated and some were more that 50%gone,this is when they start deteriorating faster as there is less anodes protecting the piling; and WHEREAS,the City developed a scope of work with the assistant of utilizing the R&M on call engineering contract requested R&M to design a Cathodic protection system for this section of the harbor(Task Order No 11)and advertised a competitive bid package according to SCC 6.10.210 and SCC 6.10.215; and WHEREAS,four bids were received by the required deadline of 3:30pm on September 24, 2021: and WHEREAS,the City and R&M engineering reviewed all bids and concluded Global Diving & Salvage Inc., was the lowest, most qualified and responsive bidder with a bid amount of $136,798.00; and WHEREAS,R&M request a 10%contingency for this project in the amount of$13,679.80 to cover any issues that arise: and CITY OF SEWARD, ALASKA RESOLUTION 2021-115 WHEREAS, the not-to-exceed construction cost will be $150,477.80 which needs to be appropriated from the Seward Harbor unassigned fund balance. NOW,THEREFORE,BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA that: Section 1. The City Council hereby authorizes the City Manager to enter into a construction contract with Global Diving & Salvage Inc., in the not-to-exceed amount of $150,477.80 in substantially the form attached hereto, for the Seward Harbor Cathodic Protection Project. Section 2. Funding in the amount of$150,477.80 is hereby appropriated from the Harbor Unassigned Fund Balance account no. 11000-0000-3400 to the Cathodic Protection Project infrastructure account no. 11440-0000-8101. Section 3. This resolution shall take effect immediately upon its adoption. PASSED AND APPROVED by the City Council of the City of Seward, Alaska, this 1 Ph day of October, 2021. T E CI ' OF S/7' ARD . l t..i erii A A 4 111111 "isty Terry, :yor AYES: Baclaan, McClure, Seese, Osenga, DeMoss, Casagra►• NOES: None ABSENT: None ABSTAIN: None ATTEST: Brenda J. Ball , MC City Clerk ...........,• ♦.•• pF SEyy'•„ (City ORPo1,T,q •% I. J • y_ O • . . SEAL • • . b r♦. k sti�rF O f" A'p'S ♦ City Council Agenda Statement Meeting Date: October 11, 2021 To: City Council From: Janette Bower, City Manager Agenda Item: Resolution 2021-115: Authorizing the City Manager to Enter into a Construction Contract with Global Diving & Salvage Inc., for the Replacement of Sacrificial Anodes Cathodic Protection System on the Concrete Section of the Seward Harbor Float System in an Amount not to Exceed $150,477.80,which includes a 10%Contingency, and Appropriating Funds Background and justification: In 1999,the Seward Boat harbor went out to bid for engineering and design for the replacement of E, F, a portion of G-float along with H and J-dock, in which council approved Resolution 99-028 authorizing Tryck Nyman Hayes INC (TNH) to perform these services. In Resolution 2000-147 Seward City Council approved Swalling Construction to replace these old wooden floats with concrete floats along with galvanized metal piling. This project was completed in 2001 with 20-year sacrificial anodes installed. In 2020, the harbor had some underwater water line breaks on the concrete section of the harbor while the diver was on site the harbor requested the diver to look at and report how much of the sacrificial anodes were remaining.The diver reported over half of the anodes were deteriorated and some were more that 50% gone,this is when they start deteriorating faster as there is less anodes protecting the piling. With the G, K & L-float project underway in 2021 and 2022, the harbor recommends replacing the anodes at this time, we could piggyback off this project to save on mob and demob cost due to the contractor for the G, K and L-float project will have divers weld anodes onto the new G, K and L- float pilings. The harbor is utilizing the R&M on call engineering contract requested R&M to design a cathodic protection system for this project (Task Order No 11). Once again with R&M being on site for the G, K & L-float construction project this again is saving city funds. The City, along with R&M drafted and finalized a competitive bid package based on the City's standard construction agreement,the scope of work and the availability of funds. This project was advertised according to SCC 6.10.210 and SCC 6.10.215. Four bids were received by the deadline of 3:30 pm on September 24, 2021. The City along with R&M reviewed all bids and concluded Global Diving & Salvage, Inc., was the lowest, most qualified and responsive bidder with a total bid amount of $136,798.00, a 10% contingency of $13,679.80 is requested to ensure the project moves forward without any delays if any unforeseen issues arise. The city needs to appropriate $150,477.80 which includes a 10% contingency to complete this project. The project consists of adding new 130 lb. anodes to all the steel piling on E, F, H, J and a portion of G-float, this will add years of service life to the galvanized metal piling. The bid tabulation follows: Seward Harbor Cathodic Protection Project Engineers Global Diving Resolve Highmark American Estimate & Salvage Marine Marine Marine Corp Group Fabrication Bid 1 $220 800.00 1 $136 798.00 1 $352 120.20 1 $393 989.60 1 $222 433.00 Consistency checklist: Comprehensive Plan: Maintain a thriving port of Seward through harbor improvements, infrastructure expansion, and implementation of management plans. (Page 16 3.5.1) Strategic Plan: Complete the renovation of the Boat Harbor. (Page 7) Other: Fiscal note: Funding will come from Harbor Fund reserves and expensed to the Cathodic Protection Project infrastructure account no. 11440-00-00�-811001. Finance Department approval: Attorney Review: Yes X❑ No ❑ Not applicable ❑ Recommendation City Council approve Resolution 2021-115. 9Io1 Vanguard orive-Anchorage,Al 995a7•90752_'.1707 ° R&M CONSULTANTS, INC. 2Y2 Front Sheet"'0•Fairbanks.AK 49701.9G7.4S2.5270 -m.-— TASK ORDER NO.ii: Harbor Cathodic Protection This task order is subject to the terms and conditions of the Agreement for On-Call Engineering Services between R&M Consultants, Inc. (Engineer) and City of Seward (Owner) dated April 15, 2019 and any amendments thereto. This task order shall not be binding until it has been properly signed by both parties. Upon execution,this task order shall supplement the Agreement as it pertains to the task described below. i. Task Order Name: Harbor Cathodic Protection 2. Description of Services to be Performed by Engineer: Design a sacrificial anode cathodic protection system for a portion of the small boat harbor as described in attached proposal letter. 3. Owners Responsibilities for task order completion: provide information needed to complete work requests. Provide notice to proceed on or before September 1, 2021. 4. Deliverables and Schedule: Bid ready documents by October 1, 2021, 5. Payments to Engineer: Owner shall pay Engineer on a T&M basis in accordance with the contract rate schedule. Total Not-To-Exceed budget is $16,529 and will not be expended without prior written approval and task order amendment. IN WITNESS WHEREOF,the parties have executed this Task Order as of the Effective Date first above written under the hands of their duly authorized representatives. R&M CONSULTANTS, INC. City of Seward Len Story, CEO Janette Bower, City Manager / ?� �r (Signature) (Sin ture) 08/09/2021 (Date) (Date) �Jw y forAlaska's Tomorrow SECTION 00030 - PUBLIC NOTICE - INVITATION TO BID CITY OF SEWARD, ALASKA Public Notice— Invitation for Bids Seward Harbor Cathodic Protection Project The City of Seward desires to receive bids from contractors to construct the Seward Cathodic Protection Project in the Small Boat Harbor Seward, Alaska. The City of Seward wishes to enter into an agreement with a qualified, experienced contractor familiar with commercial diving and installation of sacrificial anodes to complete the work as outlined in the plans and specifications. The scope of work generally includes furnishing and installing aluminum alloy sacrificial anodes on piling in a portion of the existing small boat harbor. Due to the heavy public use of the Seward Harbor in the summer months, no on site work will be allowed between May 1 and September 15. All work under this contract must be completed by April 30, 2022. An optional pre-bid conference will be held in the Seward City Council Chambers (5th Avenue & Adams Street), on September 15, 2021 at 10:30 a.m. The bid documents are available at the office of the Engineer. Electronic copies are available for no charge. Paper copies can be made available from a local reproduction company at the Contractor's expense. To receive a copy of the bid documents contact Jessica Koloski at 907 646-9600 or by email at JKoloski@RMConsult.com All bids including any amendments or withdrawals must be received and time-stamped at the City of Seward prior to 3:30 p.m. on September 24, 2021. Electronic or faxed bids will not be accepted. Bids shall be submitted on the forms furnished and must be in a sealed envelope marked as follows: BID FOR: CITY CLERK City of Seward P.O. BOX 167 Seward Harbor Cathodic Protection Project 410 ADAMS STREET SEWARD, ALASKA 99664 The bids will be opened publicly in the City Council Chambers located at 410 Adams Street Seward, AK 99664 beginning at 3:30 p.m. on September 24, 2021. The contract shall be let by the Seward City Council to the lowest qualified responsive and responsible bidder. The selection of the qualified bidder will be at the sole discretion of the City of Seward, and the City reserves the right to reject any and all bids or not to award a contract if deemed in the best interest of the City. This solicitation does not commit the City of Seward to pay any costs incurred in the preparation of the bid or to award any contract. All questions relating to technical matters, bid procedures or other aspects of the project should be directed to the following: Jean Cumlat, E.I.T. (Phone: 907 646-9697 or by e-mail:JCumlat@RMConsult.com). All questions must be received no later than 4:00 p.m. on September 21, 2021. Seward Harbor Cathodic Protection Project PUBLIC NOTICE - INVITATION TO BID Page 00030 -1 9101 Vanguard Drive•Anchorage,Alaska 99507•rmconsult.com R&M CONSULTANTS, INC. phon 40e: 7.522.1717•fax:407.522.3403•ema l@rmmnsult.com SEWARD HARBOR CATHODIC PROTECTION PROJECT TO: All Plan Holders of Record Date: 09-27-2021 SUBJECT: Bid Results Bid Closing: 3:30pm September 24,2021 A Bid Opening was held in Seward on Friday, September 24, 2021 at 3:30 PM. Below are the preliminary results: Contractor Estimate Base Bid Global Diving& Salvage, Inc. $136,798.00 Resolve Marine Group (Resolve Alaska Holdings, Inc.) $352,120.20 Highmark Marine Fabrication, LLC $393,989.60 American Marine Corp. $222,433.00 Global Diving & Salvage, Inc. is the apparent low bidder. Thank you for your interest in the project. SECTION 00500- CONTRACT CITY OF SEWARD, ALASKA Seward Harbor Cathodic Protection Program [PROJECT NAME AND NUMBER] CONTRACT ("Contract"), between the City of Seward, Alaska, herein called the City, acting by and through its City Manager, and upon signing; this document shall serve as the notice to proceed, and Global Diving&Salvage, Inc. Company Name 5304 Eielson Street,Anchorage,Alaska 99518 Company Address (Street or PO Box, City, State, Zip) a/an ❑ Individual ❑Partnership ❑Joint Venture ❑Sole Proprietorship ❑X Corporation incorporated under the laws of the State of Washington , its successors and assigns, herein called the Contractor, is effective the date of the signature of the City Manager on this document. The Contractor, for and in consideration of the payment or payments herein specified and agreed to by the City, hereby covenants and agrees to furnish and deliver all the materials and to do and perform all the work and labor required in the construction of the above-referenced project as bid by the Contractor, which bid and prices named, together with the Contract Documents (as hereinafter defined) are made a part of this Contract and accepted as such. It is distinctly understood and agreed that no claim for additional work or materials, done or furnished by the Contractor and not specifically herein provided for, will be allowed by the City, nor shall the Contractor do any work or furnish any material not covered by this Contract, unless such work or materials is ordered in writing by the City. In no event shall the City be liable for any materials furnished or used, or for any work or labor done, unless the materials, work, or labor are required by the Contract or on written order furnished by the City. Any such work or materials which may be done or furnished by the Contractor without written order first being given shall be at the Contractor's own risk, cost, and expense and the Contractor hereby covenants and agrees to make no claim for compensation for work or materials done or furnished without such written order. Notwithstanding the foregoing, payment under this Contract shall not exceed One Hundred Thirty Six Thousand and Seven Hundred Ninety Eight dollars ($ ) for all base items, additional work, and change orders. The Contractor further covenants and agrees that all materials shall be furnished and delivered and all work and labor shall be done and performed, in every respect, to the satisfaction of the City, on or before: April 30,2022 or within N/A calendar days following the date of notice to proceed. It is expressly understood and agreed that in case of the failure on the part of the Contractor, for any reason, except with the written consent of the City, to complete the furnishing and delivery of materials and the doing and performance of the work before the aforesaid date, the City shall have the right to deduct from any money due or which may become due the Contractor, or if no money shall be due, the City shall have the right to recover One Thousand dollars ($1,000.00 ) per day for each calendar day elapsing between the time stipulated for the completion and the actual date of completion in accordance with the terms hereof; such deduction to be made, or sum to be recovered, not as a penalty but as liquidated damages. Provided, however, that upon receipt of written notice from the Contractor of the existence of causes over which the Contractor has no control and which must delay furnishing of materials or the completion of the work, the Contracting Officer may, at his or her discretion, extend the period specified for the furnishing of materials or the completion of the work, and in such case the Contractor shall become liable for liquidated damages for delays commencing from the date on which the extended period expires. The bonds given by the Contractor in the sum of$ 136,798.00 Payment Bond, and $ 136 798.00 Seward Harbor Cathodic Protection Project CONTRACT Page 00500-1 SECTION 00500-CONTRACT Performance Bond, to secure the proper compliance with the terms and provisions of this Contract, are submitted herewith and made a part hereof. The Contractor further covenants and agrees that the entire construction will be done under the administration of and to the complete satisfaction of the City subject to the inspection at all times and approval by any regulatory agency of the Local, State, or Federal Government of the United States of America, and in accordance with the laws of the State of Alaska and the City of Seward. For purposes of this Contract, Contracting Officer means or any other person designated by the City Manager. The Contractor is an independent contractor and not an employee or agent of the City. Contract Documents shall have the meaning ascribed by the General Conditions of the Construction Contract, and include but are not limited to this Contract, the General Conditions of the Construction Contract, the Supplementary Conditions, and the following listed documents: (1} (2) IN WITNESS WHEREOF the parties hereto have executed this Contract and agree to its terms and conditions. CONTRACTOR Global Diving&Salvage, Inc. Company Name Signature of Authorized Company Representative Kendra Bulawa,Alaska Business Manager Typed Name and Title 10/1/2021 Date CITY OF SEWARD Signature of City Manager Typed Name Date City Clerk (ATTEST) Seward Harbor Cathodic Protection Project CONTRACT Page 00500-2