HomeMy WebLinkAbout02142022 City Council LAYDOWN - Sturgeon Contract signed9A�
L *JA�zwti'
CONSTRUCTION AGREEMENT
THIS AGREEMENT is made this 15th day of February 2022 by and
between the Owner: City of Seward, 416 Adams Street, Seward, AK 99664 and the
Contractor: Sturgeon Electric Company, 1301 E..64' Ave. Anchorage Alaska.99515, The
Project is: Nash Road Electric Transmission Rebuild, The Owner and Contractor agree as set
forth below.
ARTICLE 1
THE CONTRACT DOCUMENTS
1.1 The Contract consist of this the Contract Documents. These form the Contract, and
are as fully a part of the Contract as if attached to this Agreement or repeated herein, The
Contract Documents, except for Modifications issued after execution of this Agreement, are
enumerated as follows:
1.1.1 The Construction Agreement is this executed Construction Agreement between Owner
and Contractor, which shall take precedence over the Supplemental Conditions and General
Conditions in the event of any conflict among the Contract Documents;
1.1.2 The Supplemental General Conditions, which shall take precedence over the General
Conditions in the event of any conflict among the Contract Documents;
1.1.4 The General Conditions;
1.1.5 The Technical Specifications included in the Project ITB;
1.1.6 Performance and Payment Bonds, substantially in the form contained in the Project ITB;
1A.7 Davis -Bacon Minimum Rates of Pay, http: Ilia bor_state. ak.usllsslpamp6Q0.htm; and
1.1.5 The addenda, if any, are as follows:
1.2 The Contract represents the entire and integrated agreement between the parties hereto
and supersedes prior negotiations, representations or agreements, either written or oral.
ARTICLE 2
THE WORK OF THIS CONTRACT
The Contractor shall fully execute the entire Work described in the Contract Documents,
or reasonably inferable by the Contractor as necessary to produce the results intended by the
Contract Documents, except to the extent specifically indicated in the Contract Documents to
be the responsibility of others. Th Contractor has reviewed all pertinent project requirements
and criteria and shall include all materials, labor, equipment, oversight and ail other cost items
needed to safely and efficiently execute the work. The Contract is for a complete project_
ARTICLE 3
DATE OF COMMENCEMENT AND COMPLETION
Construction Agreement Nash Road Electric Transmission Rebuild
AG-1 February, 2022
3.1 The date of commencement of the Work is the date from which the Contract Time of
Paragraph 3.2 is measured, and shall be the date of this Agreement, as first written above,
unless a different date is stated below or provision is made for the date to be fixed in a notice to
proceed issued by the Owner.
3.2 The Contractor shall diligently prosecute the Work and achieve Substantial Completion
of the entire Work not later than December 31, 2022 for all work subject to adjustments of this
Contract Time as provided in the Contract Documents. Final Completion shall be achieved by
March 31, 2023.
3.3 Time is of the essence for all obligations of the Contractor contained in the Contract
Documents.
ARTICLE 4
CONTRACT SUM
The Owner shall pay the Contractor in current funds for the Contractor's performance of
the Contract the Contract Sum of Two million nine -hundred and ninety-seven thousand nlne -
three dollars and forty-six cents Dollars ($2.,997,093.46), subject to additions and deductions as
provided in the Contract Documents.
ARTICLE 5
PROGRESS PAYMENTS
6,1 Based upon Applications for Payment, including all supporting documentation, submitted
to the Owner and the OR by the Contractor and Certificates for Payment issued by the OR, the
Owner shall make progress payments on account of the Contract Sum to the Contractor as
provided below and elsewhere in the Contract Documents.
5.1.2 The period covered by each Application for Payment shall be one calendar month
ending on the last day of the month, or as follows:
5A.3 Owner shall make payment to the Contractor pursuant to an application for payment that
complies with the Contract within thirty calendar days of the date that the Owner receives the
OR's certificate for payment and Federal Aviation Administration's written consent to the
payment. Notwithstanding the foregoing, if Owner is going to use State grant or Federal money
to make the payment, the Owner shall have the longer of twenty-one calendar days from the
date that the Owner receives the OR's certificate for payment or twenty-one calendar days from
the date the Owner actually receives the State grant or Federal money with which to make the
payment.
If part or all of a payment is going to be withheld for unsatisfactory performance, or if the
Contractor's application for payment does not comply with the requirements of the Contract,
Owner shall within ten working days after receipt of the application for payment notify the
Contractor in writing. This notice shall state specifically why part or all of the payment is being
withheld and what remedial actions may be taken by the Contractor to receive the full payment.
The withheld portion of the payment shall then be paid within twenty-one calendar days after
the Contractor satisfactorily completes the remedial actions identified in that notice.
Notwithstanding the foregoing, if Owner is using State grant or Federal money for the Contract,
Owner shall have the longer of twenty-one calendar days after the Contractor satisfactorily
Construction Agreement Plash Road Electric Transmission Rebuild
AG-2 February, 2022
completes the remedial actions identified in the notice or twenty-one calendar days after the
Owner actually receives the State grant or Federal money with which to make payment.
5.1.4 Each Application for Payment shall be based upon the schedule of values submitted by
the Contractor in accordance with the Contract Documents, The schedule of values shall
allocate the entire Contract Sum among the various portions of the Work and be prepared in
such form and supported by such data to substantiate its accuracy as the OR may require. This
schedule, unless objected to by the OR, shall be used as a basis for reviewing the Contractor's
Applications for Payment.
6.1.5 Applications for Payment shall indicate the percentage of completion of each portion of
the Work as of the end of the period covered by the Application for Payment.
5.1.6 Subject to the provisions of the Contract Documents, the amount of each progress
payment shall be computed as follows:
1. Take that portion of the Contract Sum properly allocable to completed Work as
determined by multiplying the percentage completion of each portion of the Work by the share
of the total Contract Sum allocated to that portion of the Work in the schedule of values, less
retainage of 10%. Pending final determination of cost to the Owner of changes in the Work,
amounts not in dispute may be included as provided in Article 7.3.7 of the General Conditions
even though the Contract Sum has not yet been adjusted by Change Order;
2. Add that portion of the Contract Sum properly allocable to materials and equipment
delivered and suitably stored at the site for subsequent incorporation in the completed
construction (or, if approved in advance by the Owner, suitably stored off the site at a location
agreed upon in writing), less retainage of ten percent (10%);
3. Subtract the aggregate of previous payments made by the Owner; and
4. Subtract amounts, if any, for which the OR has withheld or nullified a Certificate for
Payment as provided in Paragraph 9.5 of the General Conditions.
5.1.7 The progress payment amount determined in accordance with Paragraph 5.1_6 shall be
further modified under the following circumstances:
1. Add, upon Substantial Completion of the Work, a sum sufficient to increase the total
payments to 95 percent (95%) of the Contract Sum, less such amounts as the OR shall
determine for incomplete Work and unsettled claims; and
2. Add, if final completion of the Work is thereafter materially delayed through no fault of
the Contractor, any additional amounts payable in accordance with Subparagraph 9,10.3 of the
General Conditions.
6.1.5 Owner shall have the option, but not the obligation, to reduce the retainage
requirements of this Agreement or release any portion of retainage prior to the date specified in
the Contract Documents. Any such reduction or release of retainage or portion thereof,
however, shall not be a waiver of any of the Owner's rights to retainage in connection with other
payments to the Contractor, or any other right or remedy that the Owner has under the Contract
Documents. Interest shall be paid on retainage 1) at the rate of 1% per annum or 2) if and to
Construction Agreement gash Road Electric Transmission Rebuild
AG-3 February, 2022
the extent required by applicable law or grant agreements. Otherwise, interest shall not be paid
on retainage.
5.1.9 Except with the Owner's prior approval, the Contractor shall not make advance
payments to suppliers for materials er equipment which have not been delivered and stored at
the site.
5.2 FINAL PAYMENT
5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be
made by the Owner to the Contractor when (1) the Contract has been fully performed by the
Contractor except for the Contractor's responsibility to correct nonconforming Work as provided
in Subparagraph 12.2.2 of the General Conditions and to satisfy other requirements, if any,
which necessarily survive final payment; (2) a final Certificate for Payment has been issued by
the OR, and (3) Owner has received verification from the State of Alaska Department of Labor
and Workforce Development ("the Department") that: (i) Contractor has complied with AS
36.05.045(a) and (b); (ii) the Department is not conducting an investigation and (iii) the
Department has not issued a notice of a violation of AS36.05 to Contractor or any subcontractor
working on the Project.
5.2.2 The Owner's final payment to the Contractor shall be made not more than 30 days after
the receipt of verification from the Department; or, if State grant or Federal money will be used
to make the payment, within 21 calendar days of the date that the City receives the payment
request or the State grant or Federal money, whichever is later.
ARTICLE s
TERMINATION OR SUSPENSION
6.1 The Contract may be terminated by the Owner or the Contractor as provided in Article
14 of the General Conditions.
6.2 The Work may be suspended by the Owner as provided in Article 14 of the General
Conditions.
ARTICLE 77
MISCELLANEOUS PROVISIONS
7.1 Where reference is made in this Agreement to a provision of the General Conditions or
another Contract Document, the reference refers to that provision as amended or
supplemented by other provisions of the Contract Documents_
7.2 Payments due and unpaid under the Contract shall bear interest from the date payment
is due at 1.5% per annum.
7.3 Lad_y own. Owner will provide a sufficient outdoor laydown area in reasonable proximity
to the worksites for poles, wire and other large materials and equipment as well as warehouse
space for items needing to remain secure_ The laydown area and warehouse space will be
available beginning April 1, 2022 and run 30 days after the date of Substantial Completion,
Owner is also assessing potential shorter -term laydown areas along the project route so that
materials are readily available near the actual work sites.
;orxstruction Agreement Nash Road Electric Transmission Rebuild
AG-4 February, 2022
7.4 Work, by Owner. Owner shall be responsible for providing those services specified to by
provide by Owner in the Technical Specifications
7.6 Liquidated Damages, Time is of the essence for completion of the Work. The Work
under this Contract is one phase of a multi -phase electrical distribution upgrade project. Delay
in completion of the Work may cause Owners electrical utility additional operating expense and
costs associated With delay in further phases of the multi -phase project. Actual damages would
be difficult to ascertain. Accordingly, the parties agree that liquidated damages in an amount
equal to $2:500 per day for each day Substantial Completion is delayed beyond the contracted
date for Substantial completion is a reasonable forecast of damages likely to occur as a result
of said breach. Owner shall be entitled to payment of liquidated damages without having to
prove or quantify loss or damage suffered as a result of Contractor's failure to meet the
obligations to which such liquidated damages relate.
M; P"k
ARTICLE 8
SPECIAL PROVISIONS
8.1 EEQlect Start-IJ�- A Notice to Proceed shall be issued by the Owner.
1 0 L
8.2 Pre -Construction Conference. Prior to the start of the work, a conference which shall be
attended by the Contractor and the Owner's Representative shall be arranged. The purpose of
the conference shall be to discuss any items that may require clarification. Also. the procedure
for distribution of all documents and correspondence related to the Contract shall be
established at the conference. The pre -construction conference shall be held at a mutually
agreed -upon location. At this conference, the Owner shall designate the OR and may delegate
duties to the OR. and the Contractor shall abide by the Owners delegation in performing the
Contractor's duties and responsibilities under the Contract Documents, The Owner may waive
the pre -construction conference, in which case designation of the OR shall be made in writing
to ContrarItO`!'r. No statement, informal agreement or understanding nor any events occurring at
the Pre -Construction Conference shall be deemed an amendment or modification of the
contract terms, plans and specifications, or Contractors obligations unless specifically
incorporated in a written change order to the Contract. The extent of such change or limitation
shall be limited to that expressly and specifically contained in the change order,
8.3 Eakneer. Owner may designate the Owner's Representative as the Engineer, as used
m the Contract Documents provide that the Owner's Representative is qualified for the duties of
the Engineer.
OWNER CONTRACTOR
17-, ,V Of Seward
Janette Bower
City Manager
(Signature} ----- z ------ _
(Printed Nanr?e and Title)
Construction Agreement Nash Road Electric Transmission Rebuild
AG-5 February, 2022