HomeMy WebLinkAboutRES2024-051 Second Ave Culvert1 1 1 Sponsored by: Sorensen CITY OF SEWARD, ALASKA RESOLUTION 2024-051 A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA, AUTHORIZING THE CITY MANAGER TO USE GRANT FUNDS FOR PROFESSIONAL DESIGN AND ENGINEERING SERVICES FROM PND ENGINEERS, INC, IN THE AMOUNT OF $117,673, FOR THE DESIGN OF THE SECOND AVE FISH PASSAGE CULVERT WHEREAS, in 2020 the Pacific States Marine Fisheries Commission allocated grant funds from the Pink Salmon Fishery Disaster Relief Fund to communities in the Gulf of Alaska affected by the Pink Salmon Fishery Disaster; and WHEREAS, with Resolution 2022-110, City Council accepted a grant in the amount of $118,914 for the purpose of adding culverts to improve salmon access*'from the lagoon to stream water; and "•. WHEREAS, Pacific States Marine Fisheries Commission has e3(1ded the deadline to use grant funds to March of 2025; and • '' "• WHEREAS, PND Engineers, Inc has created a.comprehensive scope with a proposal for the design and engineering and writing the RFP for construction of tiie:fish..passage culvert for streams from First and Second Lakes across Second Ave to the lagoon foifixed fee of $117,673; and WHEREAS, PND Engineering, Inc has proven expertise designing fish passage culverts and local experience, including excellent engineering services for the 2017 storm surge damage on Lowell Point Road; and WHEREAS, staff have reviewed the proposed project scope with listed deliverables and approved it as written. NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA, that: Section 1. The City Council hereby approves the use of grant funds for the Second Ave fish passage culvert design proposal by PND Engineers, Inc. Section 2. Funding in the amount of $117,673 is hereby accepted in 2016 Alaska Pink Salmon Fishery Disaster Relief Fund 80022-0000-8101 infrastructure expense account. Section 3. This resolution shall take effect immediately upon adoption. PASSED AND APPROVED by the City Council of the City of Seward, Alaska this 23rd day of September 2024. CITY OF SEWARD, ALASKA RESOLUTION 2024-051 Page of 2 of 2 AYES: NOES: ABSENT: ABSTAIN: ATTEST: THE CITY OF SEWARD, ALASKA Sw.lJ M'C9AtM Sue McClure, Mayor Finch, Barnwell, Crites, Calhoon, Osenga, Wells, McClure None None None Kris Peck City Clerk (City Seal) City Council Agenda Statement Meeting Date: September 23, 2024 To: City Council From: Doug Schoessler, Public Works Director Sponsored By: Kat Sorensen, City Manager Subject: Resolution 2024-051: Authorizing the City Manager to Use Grant Funds for Professional Design and Engineering Services from PND Engineers, Inc, in the Amount of $117,673, for the Design of the Second Ave Fish Passage Culvert Background and justification: The Pink Salmon Disaster Relief Fund, administered through the Pacific States Marine Fisheries Commission, provided grant funding to be used for the design and engineering costs for the installation of a fish passage culvert under Second Ave at the lagoon. Water flowing from First and Second Lakes passes under Second Ave through two culverts. The culverts are rusting out and partially clogged. Additionally, they are undersized and skewed along the road, resulting in an excessive length of pipe. Most importantly, they were not designed for fish passage. A new structure would improve the flow of water to alleviate flooding at nearby properties, reduce the length of pipe, and improve ecological function for fish passage. This project also creates the opportunity to design a viewing platform at the Rotary Pavilion for educational opportunities and public enjoyment. This proposal will provide the engineering and design necessary to complete an RFP for construction. Comprehensive and Strategic Plan Consistency Information This legislation is consistent with (citation listed): Comprehensive Plan: I-Pg 4, 15, Natural Environment, II -Page 15 Quality of Life Strategic Plan: 2.25 Education, 3.9.2.2 Preserve and protect, Other: Total amount of funds listed in this legislation: $ 117,673 This legislation (✓): Creates revenue in the amount of: Creates expenditure in amount of: Creates a savings in the amount of: Has no fiscal impact x Funds are (✓): x $ $ $ Budgeted Line item(s): Pink Salmon Grant Fund Not budgeted Not applicable Affected Fund (✓): General Boat Harbor Motor Pool x Available Fund Balance SMIC Parking Other Electric Water Pink Salmon Grant Fund Wastewater Healthcare Note: amounts are unaudited Finance Director Signature: Yes Attorney Signature: Not applicable Comments: Attorney Review Administration Recommendation Adopt Resolution Other: D ENGINEERS, INC. August 13, 2024 PND 24A-102 Doug Schoessler Public Works Director City of Seward 434 6th Avenue Seward, AK 99664 SUBJECT: SEWARD SECOND AVENUE FISH PASSAGE DESIGN FEE PROPOSAL Doug: PND Engineers, Inc. (PND) is pleased to provide a fee proposal for design for this fish passage culvert replacement project. We understand that the City of Seward has funding for design services to provide fish passage at the crossing of an unnamed tributary to "The Lagoon" and Second Avenue. The current crossing consists of two 24-inch-diameter corrugated metal pipe (CMP) culverts and a 36-inch-diameter CMP overflow culvert. The existing 24-inch CMPs are undersized and skewed along the road resulting in excessive length of pipe. We understand that the City's objective is to install a new structure to provide fish passage and improved ecological function. In addition to the fish passage structure, the City desires to have a viewing platform constructed adjacent to the culvert outlet and restored channel as an educational area for viewing fish moving upstream. The size and location of the proposed new hydraulic structure is limited due to adjacent utilities, including a water main located approximately 11 feet below top of road and a sewer main located approximately 6 feet below top of road. The proposed structure must fit between these two mainline utilities. While onsite, we discussed installing a new, shorter structure, and reconstructing the channel adjacent to Rotary Park (see Figure 1). This alternative would provide additional stream channel habitat and provide a public viewing location and potential educational opportunities at the proposed platform. PND will investigate this option during the concept development and through coordination with environmental permitting agencies. This proposal presents design and permitting fees to provide a bid -ready set of documents for this project. We propose to complete the following tasks: 1) Site Visit & Survey PND will conduct a hydrologic site assessment to gather necessary data for stream simulation design and hydraulic modeling and verification of the U.S. Fish & Wildlife Service (USFWS) analysis. PND will also collect topographic and bathymetric survey to supplement existing USFWS survey data around the proposed crossing location and observation platform over the channel reconstruction area. It is assumed that depths of the water and sewer mains will be verified by the City. 1506 WEST 36TH AVENUE • ANCHORAGE, AK 99503 • P: 907.561.1011 • F: 907.563.4220 AUGUST 2024 2) Hydrologic & Hydraulic (H&H) Report SECOND AVENUE FISH PASSAGE DESIGN FEE PROPOSAL PND will prepare a draft H&H report to include 35% concept design plans and hydraulic analysis for the City's review. As part of this initial phase, design criteria will need to be developed and agreed upon. Based on review of previous analysis and considering site constraints, it is likely that typical hydraulic design criteria will not be achievable. Upon approval of the concept design, PND will progress design, preparing plans, specifications, and construction estimates. ff Proposed crossing location and channel reconstruction Proposed viewing platform off of Rotary boardwalk Figure 1: Proposed Crossing Replacement and Platform Location 3) Plans, Specifications, & Estimates After preparation of the H&H Report and a 35% concept design, additional design packages, including plans, specifications, and construction cost estimates, will be prepared at the 65%, 95%, and 100% design milestones. After each package has been reviewed by the City, PND will conduct a comment resolution meeting to review comments and ensure design acceptance prior to progressing to the next milestone. 4) Permitting At the 65% level, PND will develop environmental permit drawings and applicable permit applications for review and comment. After incorporating the City's comments, PND will finalize applications and either return them to the City for submission to agencies, or PND can submit them as the City's agent. It is assumed that the City will cover any permit fees directly. D 2 AUGUST 2024 5) Bid Support SECOND AVENUE FISH PASSAGE DESIGN FEE PROPOSAL After completion and acceptance of all project documents, PND will prepare a construction bid package, conduct an on -site pre -bid meeting, and be available during the bid process for review and response to questions as necessary. Enclosed, please find a detailed breakdown of PND's fee proposal to complete the work described above. PND proposes a fixed fee of $117,673 for design, permitting, and assistance during bidding. If desired, PND can provide construction administration services for an additional fee. Services will commence immediately upon receipt of notice to proceed (NTP) with site reconnaissance tentatively scheduled for August or early September. The remainder of the tasks will follow a schedule that is to be coordinated and agreed upon between PND and the City of Seward. We appreciate the opportunity to propose on this project. Feel free to contact us any time if you have further questions. We look forward to working with you. Sincerely, PND Engineers, Inc. Alexandra Jefferies, PE Principal Engineer ✓ E1456 Doug Kenley, PE Vice President D 3 D ENGINEERS, INC. FEE PROPOSAL PROJECT TITLE: Second Ave Fish Passage CLIENT: City of Seward PROPOSAL NUMBER: 24A102 Prepared by: 8/13/2024 AJ FEE SUMMARY TASK DESCRIPTION 1 Site Visit & Survey $19,875 2 H&H Report $19,093 3 Plans, Specifications, & Estimate $65,286 4 Permitting $9,304 5 Bid Support $4,116 SUBTOTAL $117,673 Notes: 1. See notes each tab. ENGINEERS, INC. PROJECT TITLE: Second Ave Fish Passage Task: Site Visit & Survey CLIENT: City of Seward PROPOSAL NUMBER: 24A102 FEE PROPOSAL 8/13/2024 Prepared by: AJ LABOR: Task Sr Engr Sr Engr Sr Engr Staff Engr Staff Engr Scientist Scientist Sr Surveyor Sr Surveyor CAD Design Technician VII VI IV V III V III III II VI VI Total Labor $251.00 $235.00 $198.00 $150.00 $137.00 $189.00 $152.00 $150.00 $137.00 $144.00 $165.00 Hours Cost 1.1 H&H Site Visit 1.1a Project Management 1 1 $251 1.1b Desktop Research 2 2 $396 1.1c Site Visit 12 12 24 $4,176 1.1d 0 $0 1.1e 0 $0 Subtotals 1 0 14 12 0 0 0 0 0 0 0 27 $4,823 1.2 Survey 0 $0 1.2a Field Prep and Research 10 4 14 $2,048 1.2b Site Survey 24 24 48 $6,888 1.2c Base Map Preparation 4 24 28 $4,392 Subtotals 0 0 4 0 0 0 0 58 28 0 0 90 $13,328 Total Labor $18,151 EXPENSES: Item a b c d e Units Unit Cost Quantity Total Cost Per Diem Meals (75% of DoD Rate for Seward; 2 people, 2 days) days $131.00 4 $524 Per Diem Meals (75% of DoD Rate for Seward; 2 people, travel days) days $98.25 2 $197 Mileage (Anchorage to Seward; 2 trips) miles $0.67 500 $335 Lodging (DoD Rate for Seward); 2 surveyors nights $284.00 2 $568 Survey Consumables Each $100.00 1 $100 Exps. Total: $1,724 NOTES: 1. Site visit to be conducted by two PND hydrologist/design engineers. 2. Survey to include topo and stream cross -sections around the project area. It is assumed that the City will verify utility elevations. 3. 4. 5. Labor and Expenses Total: $19,875 ENGINEERS, INC. PROJECT TITLE: Second Ave Fish Passage Task: H&H Report CLIENT: City of Seward PROPOSAL NUMBER: 24A102 FEE PROPOSAL 8/13/2024 Prepared by: AJ LABOR: Task Sr Engr Sr Engr Sr Engr Staff Engr Staff Engr Scientist Scientist Sr Surveyor Sr Surveyor CAD Design Technician VII VI IV V III V III III II VI VI Total Labor $251.00 $235.00 $198.00 $150.00 $137.00 $189.00 $152.00 $150.00 $137.00 $144.00 $165.00 Hours Cost 2.0 H&H Report 2.1 Project Management 1 1 $235 2.2 Concept Plans 1 8 12 40 4 65 $9,675 2.3 Hydraulic Analysis 4 20 24 $3,532 2.4 Draft Report 1 4 24 29 $4,315 2.5 Final Report 1 2 6 9 $1,336 Subtotals 0 4 18 12 90 0 0 0 0 4 0 128 $19,093 Total Labor $19,093 EXPENSES: Item a b Units Unit Cost Quantity Total Cost $0 $0 Exps. Total: so Labor and Expenses Total: NOTES: 1. Concept plans are to approximately a 35% design level, and include alternatives assessment of the proposed realignment of the crossing and channel. 2. Fee assumes that the USFWS-identified reference reach stream is appropriate for use in the design. 3. Hydraulic analysis to be conducted using FHWA's HY-8 one-dimensional culvert model. 4. H&H report to build on USFWS's 2020 report and analyses. 5. Fee assumes flexibility in hydraulic design criteria due to physical site constraints. $19,093 ENGINEERS, INC. PROJECT TITLE: Second Ave Fish Passage Task: Plans, Specifications, & Estimate CLIENT: City of Seward PROPOSAL NUMBER: 24A102 FEE PROPOSAL 8/13/2024 Prepared by: AJ LABOR: Task Sr Engr Sr Engr Sr Engr Staff Engr Staff Engr Scientist Scientist Sr Surveyor Sr Surveyor CAD Design Technician VII VI IV V III V III III II VI VI Total Labor $251.00 $235.00 $198.00 $150.00 $137.00 $189.00 $152.00 $150.00 $137.00 $144.00 $165.00 Hours Cost 3.1 Fish Passage PS&E 3.1a Project Management 1 2 3 $721 3.1b 65% PS&E 6 24 40 80 12 162 $24,850 3.1c 95% PS&E 4 20 20 48 6 98 $15,340 3.1d 100% PS&E 2 4 12 16 1 35 $5,398 3.1e QC Reviews 1 8 4 12 25 $4,063 Subtotals 1 15 56 76 156 0 0 0 0 19 0 323 $50,372 3.2 Platform PS&E 3.2a Project Management 1 1 2 $486 3.2b 65% PS&E 1 4 16 12 33 $4,963 3.3c 95% PS&E 1 6 24 6 37 $5,591 3.3d 100% PS&E 1 2 8 1 12 $1,887 3.3e QC Reviews 1 6 4 11 $1,987 Subtotals 5 1 18 0 52 0 0 0 0 19 0 95 $14,914 Total Labor $65,286 EXPENSES: Item b Units Unit Cost Quantity Total Cost so $0 NOTES: 1. It is assumed that the City of Seward will verify and provide utility elevations within the project area. 2. No modifications to utilities are proposed. 3. Platform will be accessed via existing Rotary pavilion boardwalk, but will be standalone structure. 4. 5. Exps. Total: so Labor and Expenses Total: $65,286 ENGINEERS, INC. PROJECT TITLE: Second Ave Fish Passage Task: Permitting CLIENT: City of Seward PROPOSAL NUMBER: 24A102 FEE PROPOSAL 8/13/2024 Prepared by: AJ LABOR: Task Sr Engr Sr Engr Sr Engr Staff Engr Staff Engr Scientist Scientist Sr Surveyor Sr Surveyor CAD Design Technician VII VI IV V III V III III II VI VI Total Labor $251.00 $235.00 $198.00 $150.00 $137.00 $189.00 $152.00 $150.00 $137.00 $144.00 $165.00 Hours Cost 4.0 Permitting 4.1 Project Management 2 1 3 $659 4.2 USACE Nationwide Permit Application 4 12 1 12 29 $4,605 4.3 KPB Multi -Agency 1 1 4 6 $995 4.4 ADF&G 2 1 4 7 $1,193 4.5 DNR 1 1 2 4 $691 1.6 Meetings/Coordination 1 2 2 1 6 $1,161 Subtotals 0 2 10 12 0 5 23 0 0 0 0 55 $9,304 Total Labor $9,304 EXPENSES: Item a b Units Unit Cost Quantity Total Cost $0 so Exps. Total: so Labor and Expenses Total: NOTES: 1. If NEPA documentation is required, it is assumed that it would be completed by others. 2. Permit fees to be paid by the City of Seward. 3. 4. 5. $9,304 ENGINEERS, INC. PROJECT TITLE: Second Ave Fish Passage Task: Bid Support CLIENT: City of Seward PROPOSAL NUMBER: 24A102 FEE PROPOSAL 8/13/2024 Prepared by: AJ LABOR: Task Sr Engr Sr Engr Sr Engr Staff Engr Staff Engr Scientist Scientist Sr Surveyor Sr Surveyor CAD Design Technician VII VI IV V III V III III II VI VI Total Labor $251.00 $235.00 $198.00 $150.00 $137.00 $189.00 $152.00 $150.00 $137.00 $144.00 $165.00 Hours Cost 5.0 Bid Support 5.1 Bid document preparation 1 4 5 $835 5.2 RFI review 1 6 7 $1,135 5.3 On -site Pre -bid meeting 8 8 $1,880 5.4 0 $0 5.5 0 $0 Subtotals 0 10 0 10 0 0 0 0 0 0 0 20 $3,850 Total Labor $3,850 EXPENSES: Item a b Units Unit Cost Quantity Total Cost Per Diem Meals (DoD Rate for Seward; 75% of total for travel day) day $98.25 1 $98 Mileage (Anchorage to Seward) miles $0.67 250 $168 NOTES: 1. 2. 3. 4. 5. Exps. Total: $266 Labor and Expenses Total: $4,116