HomeMy WebLinkAboutRES2025-011 RM Harbormaster Building DesignSponsored by: Sorensen
CITY OF SEWARD, ALASKA
RESOLUTION 2025-011
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD,
ALASKA, AUTHORIZING THE CITY MANAGER TO EXECUTE TASK
ORDER 2734.34 WITH R&M ENGINEERING FOR THE
HARBORMASTER BUILDING AND UPLANDS SCOPING AND
CONCEPTUAL DESIGN IN AN AMOUNT NOT TO EXCEED $95,530 AND
APPROPRIATING FUNDS
WHEREAS, the Harbormaster's office was constructed in 1968 as part of the Harbor
Reconstruction Plan after the 1964 Good Friday earthquake; and
WHEREAS, the building has been remodeled a number of times, required major repairs,
and is beyond its useful life; and
WHEREAS, this is the next step to put the project in.a ready status and make the City of
Seward eligible for state and federal funding.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCILOF THE CITY
OF SEWARD, ALASKA, that:
Section 1. The City Council hereby authorizes the City Manager to execute Task Order
2734.34 with R&M Engineering.
Section 2. Funding in the amount of $95,530 is hereby transferred and appropriated in the
Harbor Major Repair and Replacement Fund Account no.11001-0000-8101 Infrastructure Expense
Account.
Section 3. This resolution shall take effect immediately upon adoption.
PASSED AND APPROVED by the City Council of the City of Seward, Alaska, this 27th
day of January 2025.
THE CITY OF SEWARD, ALASKA
j u4*'W C A
Sue McClure, Mayor
CITY OF SEWARD, ALASKA
RESOLUTION 2025-011
Page 2 of 2
AYES: Barnwell, Finch, Crites, Osenga, Wells, Warner, McClure
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST:
Kris Peck
City Clerk
(City Seal)
City Council Agenda Statement
Meeting Date: January 27, 2025
To: City Council
Through: Kat Sorensen, City Manager
From: Jason Bickling, Deputy City Manager
Subject: Resolution 2025-011: Authorizing the City Manager to Execute Task Order
2734.34 with R&M Engineering for the Harbormaster Building and Uplands
Scoping and Conceptual Design in an Amount Not to Exceed $95,530 and
Appropriating Funds
Background and justification:
The Seward Harbormaster's Office was originally constructed in 1968 as part of the 1965 Harbor
reconstruction project in the aftermath of the 1964 Good Friday earthquake. The Seward Boat
Harbor has grown significantly since that time with multiple expansions.
The building itself has had several remodels and major repairs but is far beyond its useful life. The
building has many challenges including lack of space for personnel and equipment, the inability
to see the harbor from the building, and the lack of nearby parking for people who want to do
harbor business.
The Port and Commerce Advisory Board, within the Seward Boat Harbor Master Plan, has
recommended that the facility be moved to the South Harbor Uplands where there is space for a
larger footprint. This location would also allow for a direct view of the harbor itself, the entrance
to the harbor, and Resurrection Bay.
In order for the city to be ready to receive funding, a 15% design and engineering needs to be
completed. The city's investment in this facility will create the opportunity for a strong return on
investment.
In the Municipal Land Inventory and Use Plan, the recommendation for the South Harbor Uplands
parcel is to, "...retain land ownership and continue public uses. This may also be a potential site
for a new Harbormaster's office."
Comprehensive and Strategic Plan Consistency Information
1
This legislation is consistent with (citation listed):
Comprehensive Plan: 3.1.1.7 Encourage and assist in the development of new public services and
facilities
Strategic Plan:
Other:
3.7.1.3 Continue to improve the quality and efficiency of governmental
services
Certification of Funds
Total amount of funds listed in this legislation: $ 95,530
This legislation:
Creates revenue in the amount of:
Creates expenditure in amount of:
Creates a savings in the amount of:
Has no fiscal impact
Funds are:
Budgeted Line item(s): 11001-0000-8101
X
X
Not budgeted
Not applicable
$
$ 95,530
$
Affected Fund:
General
Boat Harbor
Motor Pool
X
Available Fund Balance
SMIC
Parking
Other
Electric
Water
$
Wastewater
Healthcare
Note: amounts are unaudited
Finance Director Signature:
'1 9"e4tt*
X
Yes
Attorney Signature:
Not applicable Comments:
Administration Recommendation
X
Adopt Resolution
Other:
R&M CONSULTANTS, INC.
ANCHORAGE I FAIRBANKS I JUNEAU
October 17, 2024
Jason Bickling
Assistant City Manager
City of Seward, Alaska
410 Adams St., City Hall Building
Seward, Alaska 99664
RE: Task Order 34 - South Uplands Plan Scoping
Dear Mr. Bickling,
R&M No. 2734.34
R&M Consultants, Inc. (R&M) is pleased to submit this fee proposal to the City of Seward under our On -Call Engineering
Services contract to provide scoping of the South Harbor Uplands Plan, including consideration and concept design of a
future Harbormaster Office. This proposed task order is in response to request from you and the Seward Harbormaster -
Tony Sieminski.
We reviewed the South Harbor Up/ands P/an and associated figures, which provides guidance on how the land should be
developed for economic and recreational use. We understand the city's request is for R&M, supported by KPB Architects, to
provide planning, surveying, engineering, and architectural services at a concept level. We propose the following for the
South Uplands Plan Scoping task:
• Harbormaster Facility Concept Design (KPB/ead)
o Programming & Concept Design Options for the Harbormasters Facility
o Building massing study to define form and function of the new Harbormaster Office
o Deliverables building massing models & bubble diagrams, architectural design narrative
• South Uplands Land Use Planning and Analysis (R&MLead)
o Review existing Uplands Plan, conduct existing condition analysis and land use code review
o Concept planning for redevelopment, reuse, improvements, or modifications
o Deliverables.: narrative of findings and recommendations
• Site Plan Concepts (R&MLead)
o Plat Review and Research
o Utility planning and concept engineering
o Preliminary Design Concept Development
RMCONSULT.COM 1 9101 VANGUARD DRIVE, ANCHORAGE, AK 99507 1907.522.1707
Page 2 of 2
o Deliverables: concept site plans, concept for preliminary plan, engineering narrative
• Scoping Charrette in -person over two days with stakeholders to define needs of the building and site amenities
• Several virtual meetings with City Staff
• Presentation of final deliverables in -person to City Council
All deliverables noted in the efforts above will be packaged into a final report to be submitted to City Council as an
informational item following staff review and approval.
Attached is a proposal cost breakdown for the task to be invoiced on a Time and Expense basis.
Please contact me at toleson@rmconsult.com or 646-9645 if you have questions.
Sincerely,
R&M CONSULTANTS, INC.
Taryn Oleson-Yelle, AICP
Senior Planner, Project Manager
(Signature) (Date)
Accepted by the City of Seward
Kat Sorensen, City Manager
Jason Bickling, Deputy City Manager
1
Anchorage, AK 99507 •
R&M CONSULTANTS, INC. 2122FontgStreet#150uard Drive '• Fairbanks, AK99701.907452. 907.522.1707
Engineering Fee Estimate
FIRM: R&M Consultants, Inc. CLIENT:
City of Seward
Project Name: South Uplands Plan & Harbormaster Concept Des Project No: 2734.34
10/16/2024
Task Department Task Description Labor Expenses
Total Cost
1
Engineering
Plan Scoping & Facility Concept Design
$ 46,230
$ 28,347
$ 74,577
2
Survey
Preliminary Plat Concept
$ 20,953
$ -
$ 20,953
$ -
$ -
$ -
$ -
$ -
$ -
Total
$ 95,530
10/17/2024 TO 34 R&M Fee Proposal_South Uplands Plan Harbormaster Office - Scoping 1 of 8
A
7
R&M CONSULTANTS INC. I 2122 F oTsui
5 treet #150'. Fai banks, KK99701: 990077.
07 525.1277007
Engineering Cost Estimate
FIRM:
R&M Consultants, Inc.
CLIENT: City of Seward
Task: 1
Plan Scoping & Facility Concept Design
Project No: 2734.34 10/16/24
SUB -TASK SUB -TASK DESCRIPTION
1.1 Project Management and Coordination
LABOR HOURS PER JOB CLASSIFICATION
Project
Manager/
Senior
Planner Prof
2
Site Devel.
GM Prof 4
Utilities Staff
GM Prof 5 Engineer
Eng 1
Project Senior
Engineer Planner
Prof 2 Prof 2
Senior
Land
Surveyor
(PLS)
16 8 2
1.2 Research & Plans, Code, As-Builts Review 8 2 8 2 8
1.3 Preliminary Uplands Design Concept
Zoning
40 10 8 40 16 24
Land Use
Parking
Public Facilities
Utilities
Community Appearance
Report
1.4 Scoping Charrette (2 days in person) 24 10 4
Prep & Attendance
1.5 Draft Deliverable Review & Comments 4 4 2 4 2
QC Review of Final Deliverables 4 4 1
Client review, respond to review comments 6 4 2 2
1.6 Presentation to City Council (in person) 10 6
Prep & Attendance
TOTAL LABOR HOURS 112 44 13 56 20 40 0
LABOR RATES ($/HR) $152.38 $207.00 $241.50 $112.13 $158.13 $186.88 $201.25
LABOR COSTS ($) $17,066 $9,108 $3,140 $6,279 $3,163 $7,475 $0
EXPENSES
DESCRIPTION QUANTITY UNIT
PRICE
PRICE MARKUP
TOTAL
PRICE
Misc. Field Supplies 1 $ 150.00 $ 150.00 $ $ 150.00
R&M Vehicle Milage 512 $ 0.75 $ 384.00 $ - $ 384.00
Lodging & Meals (2 days, 1 night) 4 $ 343.00 $ 1,372.00 $ - $ 1,372.00
$ - $ - $ -
SUB -CONTRACTORS
SUB -
TASK
DESCRIPTION
FIRM
TOTAL
PRICE
COMMENTS:
1. Scoping Charrette will be over 2 days in City of
Seward, PM will attend both days, Site
Development GM and Surveyor will attend one day
focused on Uplands Planning
2. KPB will lead Harbormaster Facility concept
design, R&M will lead South Uplands land planning
and site development concepts.
3.
4.
Harbormaster Facility Concept Design
KPB
$ 24,037 TOTAL LABOR $ 46,230
TOTAL EXPENSES $ 1,906
SUBCONTRACTORS $ 24,037
SUBCONTRACTORS MARK-UP $ 2,404
TOTAL SUB-
$ 24,037 TOTAL T&E COST $ 74,577
TO 34 R&M Fee Proposal_South Uplands Plan Harbormaster Office - Scoping 2 of 8
9101
uard
ve • Anchorage,
R & M CO N S U LTA N TS, INC
. 212 Front Street #150 •Fairbanks, AK 970°1'907.452.5270907.522.1707
°
Engineering Cost Estimate
FIRM:
R&M Consultants, Inc.
CLIENT: City of Seward
Task: 2
Preliminary Plat Concept
Project No: 2734.34 10/16/24
SUB -TASK SUB -TASK DESCRIPTION
LABOR HOURS PER JOB CLASSIFICATION
rroJect
Manager/ Site Staff Project Senior
Senior Devel. GM Utilities Engineer Engineer Planner
Planner Prof 4 GM Prof 5 Eng 1 Prof 2 Prof 2
Prnf 9
Senior
Land
Surveyor
(PLS)
2.1 Project Management and Coordination 8 4
2.2 Research & Utilities
Perlimiary Design Concept
8
4 40
Review & Comments
2 8
Final Concept for Preliminary Plat
2 16
2.3 Scoping Charrette (in -person) 8
2.4 Presentation to City Council
8
TOTAL LABOR HOURS 16 0 0 0 0 0 92
LABOR RATES ($/HR) $152.38 $207.00 $241.50 $112.13 $158.13 $186.88 $201.25
LABOR COSTS ($) $2,438 $0 $0 $0 $0 $0 $18,515.00
EXPENSES
DESCRIPTION QUANTITY UNIT
PRICE
PRICE MARKUP
TOTAL
PRICE
Misc. Field Supplies
R&M Vehicle Milage
$ 150.00 $
$ 0.75 $
COMMENTS:
This estimate is to produce a concept design for the
subdivision of Tract H, Seward Original Townsite Waterfront
Park Replat (Plat No. 2012-4). The concept will subdivide the
existing tract into lease lots and a larger lot to facilitate the
construction of a new Harbor Master's building.
$ $ $ No fieldwork or platting services are included in this estimate.
Expenses are included in Task 1.
SUB -CONTRACTORS
SUB -
TASK
DESCRIPTION
FIRM
TOTAL
PRICE
TOTAL LABOR
TOTAL EXPENSES
SUBCONTRACTORS
SUBCONTRACTORS MARK-UP
$ 20,953
TOTAL SUB- $
TOTAL T&E COST
TO 34 R&M Fee Proposal_South Uplands Plan Harbormaster Office - Scoping
$ 20,953
3 of 8
KPB
August 26, 2024
Don Potter
Project Manager
R&M Consultants, Inc.
9101 Vanguard Drive
Anchorage, AK 99507
RE: South Uplands Plan
Seward Harbormaster Building - Concept Design Fee Proposal
Dear Don:
ARCHITECTS
Thank you for the opportunity to provide a proposal for concept design efforts for the South Uplands Plan
— Harbormaster Building in Seward, AK. Please find below our understanding of the scope of work as well
as our fee proposal.
Scope of Work:
1. Attend scoping Charrette in Seward with client (2-days)
2. Assist with the development of a facility program for Harbormaster building and site amenities
3. Prepare multiple Concept design drawings (massing Models) and design narrative
4. Attend virtual meetings with client and R&M to address questions and discuss development of
concept designs ((2) 2-hour meetings)
5. Post-charrette development of drawings/design narrative and minutes
6. Develop package for presentation to City Council
7. Present concepts to City Council
Deliverables:
1. Building massing models & bubble diagrams
2. Site plans — By R&M
3. Architectural Design narrative
4. Architectural components of the Presentation package
Schedule:
• Draft Deliverables —10 business days from Scoping Charrette
• Final Deliverables — 5 business days from City Council Presentation
Fee Summary:
• Scoping Charrette in Seward
o 2-days (includes mtg/travel & reimbursables) $4,733
• Draft Concept Designs, narratives and presentation materials $12,520
• City Council Presentation & Final Report
o 1-day (includes mtg/travel and reimbursables) $6,784
Total Fee: $24,037
500 L Street, Suite 400 Anchorage, AK 99501
P: 907.274.7443 F: 907.274.7407 www.kpbarchitects.com
KPB
Exclusions & Assumptions:
• Fees are Time and Expense T&E (NTE)
• Travel mileage based @ $.067/mile
• KPB Architects are only providing architectural conceptual design/scope
• Project Management by R&M
• Concept cost estimate (if required via R&M by sub -consultant)
• Other required engineering not included in KPB's fee proposal
ARCHITECTS
Thank you for the opportunity and please feel free to contact us should you have any questions. We look
forward to working with R&M Consultants again!
Sincerely,
KPB Architects
.Y6
Michael A Prozeralik, AIA
President/Managing Principal