Loading...
HomeMy WebLinkAbout02242025 City Council Work Session Laydown - UtilitySeward Electric System City of Seward City Council Infrastructure Project Update February 24, 2025 1 Electrical Infrastructure Project Objectives Scope Project Schedule Status, Estimates, Costs to Date Required Additional Funding Questions 2 Objectives 3 Address Address Safety Issues •Replace inadequate ground grids •Replace compromised structures •Improved operator situational awareness Replace Replace equipment which is at the end of its useful life •Aged and ineffective transformation, protection, and metering equipment Upgrade Upgrade voltage from 69kV to 115kV •Lower losses •Improved emergency response through increased Railbelt interoperability •Increased capacity for future load growth •Integration with Shore Power and Battery Energy Storage (BESS) Scope-Nash Road and Fort Raymond- Seward Highway O.H Conversion •Replace structures •Reconductor transmission circuit •Reconductor distribution under-build •Add Air-break Switch Nash Road and Seward Highway 4 Scope-Fort Raymond Substation Conversion Upgrade ground grid and fencing •To meet current National Electrical Safety Code (NESC) 01 Improve control and protective selectivity •Replace end of life control and protection •Add 115kV circuit breaker 02 Upgrade power transformers 03 Upgrade feeder breakers 04 Improve operator situational awareness 05 5 Scope-Lawing Substation Conversion Replace ground grid and fencing •To meet current National Electrical Safety Code (NESC)Replace Improve control and protective selectivity •Replace end of life control and protectionImprove Upgrade power transformers Convert from 69 kV to 115 kVPower Add remotely operated load break tap switch Add Improve operator situational awarenessImprove 6 Scope-Spring Creek Substation Conversion Replace Replace ground grid and fencing •To meet current National Electrical Safety Code (NESC) Improve Improve control and protective selectivity •Replace end of life control and protection Power Upgrade power transformers Convert from 69kV to 115kV Improve Improve operator situational awareness 7 Scope-Cruise Ship Shore Power 115 kV line from Fort Raymond to Cruise ship dock via AKRR New 115 kV -12.5 kV substation north side of Ship Avenue AKRR 2-feeder breakers to cruise ship dock 12MW 2-hour Battery Energy Storage System (BESS) 8 Advanced Metering Infrastructure (AMI) 9 Enhanced Data Visibility: AMI provides real-time or near-real-time data on energy usage, allowing utilities to monitor consumption patterns, quickly detect anomalies, and improve load forecasting. Accurate Billing: With detailed usage data, billing becomes more accurate. Time-of-use rates can be implemented, ensuring customers are charged based on actual consumption patterns. Operational Efficiency: Automated meter readings reduce the need for manual visits, lowering labor costs and minimizing errors. Remote connect/disconnect capabilities also streamline customer service and maintenance. Improved Outage Management: The system can quickly identify and locate outages, helping utilities to respond faster and reduce downtime for customers. Enhanced Grid Reliability: Better data enables proactive grid management and more efficient integration of renewable energy sources, supporting a more stable and resilient electrical grid. Customer Empowerment: Access to detailed consumption data allows customers to make informed decisions about their energy use, potentially leading to cost savings and more sustainable practices. Project Schedule 10 Infrastructure Project -Financial Overview Budget and Status 11 Project sub component 2022 Estimate 2025 Actual/Estimate Status 2022 Est. To 2025 Actual/Estimate Nash Road Phase 1 4,568,969$ 4,140,254$ Complete 91% Nash Road Phase 2*1,285,724$ 2,447,011$ 95% Design Bid Package Complete 190% Seward Highway 619,565$ 619,565$ Complete 100% Fort Raymond 7,165,582$ 6,776,525$ Complete 95% Lawing 3,272,727$ 3,500,000$ At 25% Design Rev. includes 10% Infl- contingency 107% Spring creek 3,960,419$ 4,356,461$ At 10% Design Rev. includes 10% Infl- contingenc 110% Shore Power**1,436,000$ -$ Feasibility Design- Clean Ports Grant Grant and CIAC funded AMI -$ 1,200,000$ Budgetary quote New Project Total 22,308,986$ 23,039,816$ 103% Current Funding 14,290,726$ Required Additional Funding 8,749,090$ * Final design required significanly more pole replacements than preliminary design ** Shore power estimate (electrical infrastrucuture +BESS) is ~ $30M; however, EPA grant and Seward Co. contribution will cover 100% Funding plan 12 Bond for remaining project costs: •Initial bond request in March 2022 was for $19.5 million •Resolution 2022-023 was amended by Council and approved bond for $10 million in order to break the project into parts, to move forward efficiently and ensure that the amounts bonded would cover project. We are now at the next phase in the project. •Current remaining balance on the project is $8,749,090 with the inclusion of AMI metering project •No rate increase required Funding plan 13 Bond Assumptions: •20-year term •$10 million (project cost + reserve amount to be held) •Issued through Alaska Municipal Bond Bank •Rates as of 2/13/25 are 3.9% with a .25% cushion Funding plan 14 Additional Considerations •Internal Loan from General Fund Investments •Typically we would do a 12.5% interest rate for an internal loan this high, since we would have to liquidate and drawn down from the city’s investments •Not our recommendation since its more fiscally responsible to preserve the value and security of investments as it is the basis of our fiscal health as a municipality Questions? 15