HomeMy WebLinkAboutRES2025-029 Police Dept 15 Percent1
1
Sponsored by: Sorensen
CITY OF SEWARD, ALASKA
RESOLUTION 2025-029
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD,
ALASKA, AUTHORIZING THE CITY MANAGER TO EXECUTE TASK
ORDER 2734.35 WITH R&M ENGINEERING FOR THE 15% DESIGN
AND ENGINEERING OF THE POLICE DEPARTMENT FACILITY IN AN
AMOUNT NOT TO EXCEED $297,994 AND APPROPRIATING FUNDS
WHEREAS, in 2023 a Public Safety Feasibility Study was completed; and
WHEREAS, it was determined that the current Police Department Facility was outdated,
undersized, inefficient, has no public access, and does not meet current code; and
WHEREAS, the City has missed opportunities for funding because we did not have a
"ready" project; and
WHEREAS, a 15% design and engineering proposal would make us eligible for funding.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY
OF SEWARD, ALASKA, that:
Section 1. The City Council hereby authorizes the City Manager to execute Task Order
2734.35 with R&M Engineering.
Section 2. Funding in the amount of $297,994 is hereby transferred and appropriated in the
Capital Acquisition Fund 80010-1210-8102-0092 New Police Department Facility Building
expense account.
Section 3. This resolution shall take effect immediately upon adoption.
PASSED AND APPROVED by the City Council of the City of Seward, Alaska this 10d'
day of March 2025.
THE CITY OF SEWARD, ALASKA
Sue McClure, Mayor
AYES: Warner, Barnwell, Crites, Osenga, Wells, McClure
NOES: None
ABSENT: Finch
ABSTAIN: None ++++i��rse�
`bf SEryq•.
ATTEST: :O.. OAp o•� �% 6 ##
- �-- t
to: SEAL: • -
Y 1 -
;(/-ffiv..-4—.E..1..'f•,:t..."1/1
%�rE OF P`-`..•
Kris Peck, City Clerk
City Council Agenda Statement
Meeting Date: March 24, 2025
To: City Council
Through: Kat Sorensen, City Manager
Subject: Resolution 2025-029: Authorizing the City Manager to Execute Task Order
2734.35 with R&M Engineering for the 15% Design and Engineering of the
Police Department Facility in an Amount Not to Exceed $297,994 and
Appropriating Funds
Background and justification:
The City Council authorized a Public Safety Feasibility Study in 2023 for both the Fire
Department and Police Department facilities. The Police Department services that would be in a
new facility include Police, Dispatch, Community Lost and Found, and would act as the
Emergency Operations Center (EOC). That Feasibility Study revealed that the current Police
Department Facility is significantly undersized, inefficient, is unsafe, and does not meet current
code.
The Feasibility Study information for the Police Department was presented to the Planning and
Zoning Commission for review.
We have missed out on funding opportunities in the past because a facility project was not at a
ready status. For us to be ready to receive funding, we need to have a 15% Design and Engineering
proposal completed.
Comprehensive and Strategic Plan Consistency Information
This legislation is consistent with (citation listed):
Comprehensive Plan: 3.1.1.7, 3.7.1.3
Strategic Plan:
Other:
Total amount of funds listed in this legislation: $ 297,994
This legislation:
Creates revenue in the amount of:
Creates expenditure in amount of:
Creates a savings in the amount of:
Has no fiscal impact
Funds are:
Budgeted Line item(s):
Not budgeted
X
X
$
$
$
Not applicable
Fund Balance Information
Affected Fund:
General
Boat Harbor
Motor Pool
X
Available Fund Balance
SMIC
Parking
Other
Electric
Water
Wastewater
Healthcare
Note: amounts are unaudited
Finance Director Signature:
5�
X
Yes
Attorney Signature:
Not applicable Comments:
Attorney Review
Mli
Administration Recommendation
X
Adopt Resolution
Other:
PeA&
R&M CONSULTANTS, INC.
ANCHORAGE I FAIRBANKS I JUNEAU
February 28, 2025 R&M No. 2734.35
Jason Bickling
Deputy City Manager
City of Seward, Alaska
410 Adams St., City Hall Building
Seward, Alaska 99664
RE: Task Order 35 - Police Station Site Selection & 15% Design
Dear Mr. Bickling,
R&M Consultants, Inc. (R&M) is pleased to submit this fee proposal to the City of Seward under our On -Call Engineering
Services contract to provide 15% design services for a new Police Station, including consideration of three sites for locating
the new station. This proposed task order is in response to request from you and Police Chief Alan Nickell. R&M will provide
project management, planning, and civil engineering services. R&M is assisted by the multi -discipline team of Integrus
Architecture and KPB Architects for architectural design, preliminary cost estimating, and public safety facility expertise.
Reid -Middleton will provide structural engineering and RSA is prepared to provide electrical engineering services. Specialty
cost estimation and geotechnical investigation are not in the proposed contract.
The following scope of work has been developed from information provided by the Assistant City Manager via email and
during subsequent conversations informed by the results of the 2024 Public Safety Building Needs Assessment & Site
Selection Study, as well as the recently completed process for the 15% design of the proposed new Fire Station. A Time and
Expense (T&E) fee estimate for the services described below is enclosed with all subconsultant proposals.
Task i. Site Analysis and Selection
Up to three sites will be analyzed using the process and criteria established in the Public Safety Needs Assessment
& Site Selection study. R&M's planners will conduct desktop research on up to three site and analyze them using
the locational criteria and methodology established in the Site Selection Study. Initial results will be presented to
the Assistant City Manager and Police Chief and collaboratively discussed in an in -person work session to arrive at
a preferred or recommended site. Results will be compiled into a new report along with results of Task 2.
RMCONSULT.COM 19101 VANGUARD DRIVE, ANCHORAGE, AK 995071 907.522.1707
Page 2 of 2
Task 2. Concept Development (15% Design)
A concept design will be developed for a new police station for the preferred site identified in Task 1. It will build on the
programming recommendations from the Public Safety Needs Assessment and will include the following efforts and
deliverables:
• Code review, easement and platting research and recommendations
• Diagrammatic floor plans and layouts
• Site master planning and diagramming
• Massing study
• Aesthetic and materials concepts
• Design discipline narratives: Planning, Civil, Architectural, Structural, Mechanical, and Electrical
Two on -site coordination meetings with project management, architects and civil site engineers will be held to
workshop site selection, floor plans, site diagramming and other details.
Task 3. Project Management, Presentations
R&M will provide project management, quality -assurance and quality -control on deliverables, lead consultant
coordination, and serve as the main point of contact for the City of Seward. Our team will present in -person at work
sessions to the Planning Commission and Seward City Council once a preferred site is selection and again to City
Council when pre -final 15% design has been developed.
All deliverables noted in the efforts above will be packaged into a final report to be submitted to the Assistant City Manager
and Policy Chief following City Council comments at an informational work session and staff review and approval.
Attached is a proposal cost breakdown for the task to be invoiced on a Time and Expense basis.
Please contact me at toleson@rmconsult.com or 646-9645 if you have questions.
Sincerely,
R&M CONSULTANTS, INC.
Taryn Oleson-Yelle, AICP
Senior Planner, Project Manager
(Signature) (Date)
Accepted by the City of Seward
Kat Sorensen, City Manager
Jason Bickling, Deputy City Manager
urd
ive
Anchorage, AK 99507
R&M CONSULTANTS, INC. 2122 Front 9StreetD#r150'. Fairbanks, AK 99701 •'907452. 907.522.1707
Engineering and Planning Cost Estimate
FIRM: R&M Consultants, Inc. CLIENT:
City of Seward
Project Name: Police Station Site Selection & 15% Design Project No: 2734.35
Date: Feb 28, 2025
Task Department Task Description Labor Subs
Expenses
Total Cost
1
Planning
Site Analysis & Selection
$ 18,228
$ 26,053
$ 44,280
2
Planning
Concept Development (15% Design)
$ 25,128
$ 208,295
$ 233,422
3
Planning
Project Management & Presentations
$ 18,371
$ 1,920
$ 20,291
Total
$ 297,994
3/3/2025 City of Seward_Police Station15% Design_Draft 2-27-25 1 of 4