HomeMy WebLinkAboutRES2026-037 KPFF Consulting Engineering Amendment 1Sponsored by: Sorensen
CITY OF SEWARD, ALASKA
RESOLUTION 2026-037
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA,
AUTHORIZING THE CITY MANAGER TO EXECUTE AMENDMENT NO. 01 TO THE
PROFESSIONAL SERVICES AGREEMENT WITH KPFF CONSULTING ENGINEERS
FOR EMISSIONS INVENTORY SERVICES FOR AN AMOUNT NOT TO EXCEED
$284,995 WHICH IS FULLY FUNDED BY THE EPA GRANT AS PART OF THE SHORE
POWER PROJECT
WHEREAS, the City of Seward was awarded a $45.7 million EPA Clean Ports Program grant to
develop shore power infrastructure at the Port of Seward, enabling cruise vessels to connect to the
local electrical grid instead of running diesel generators while docked; and
WHEREAS, on April 15, 2025, the City entered into a Professional Services Agreement with
KPFF Consulting Engineers (KPFF) for project management services for the shore power project;
and
WHEREAS, pursuant to City Code Section 6.10.020, the contract amendment to include
emissions inventory support services qualifies as a justified exemption from competitive
procurement, subject to applicable federal, state, and local regulations; and
WHEREAS, the EPA grant requires the City to conduct a Port of Seward Vessel Shore Power
Implementation Emissions Inventory as specified in the Project Quality Assurance Project Plan
(QAPP); and
WHEREAS, KPFF has submitted Amendment No. 01, dated March 27, 2026, to expand the scope
of services to include emissions inventory support, consisting of five tasks: (1) Project Planning
and Data Scoping, (2) Baseline Emissions Inventory Development, (3) Future Shore Power Use
and Emissions Savings Modeling, (4) QA/QC Activities, and (5) Emissions Inventory Report
Generation and Submission, with work to be completed by Q2 2028; and
WHEREAS, the additional fee for Amendment No. 01 is $284,995 on a time -and -materials basis;
and
WHEREAS, the original contract for $398,039 passed by Resolution 2025-044, included a 5%
contingency of $19,902. This was added to the $683,034 revised project budget for the City,
bringing the total amount not to exceed $702,936; and
WHEREAS, funds for this amendment are available within the existing EPA grant budget.
CITY OF SEWARD, ALASKA
RESOLUTION 2026-037
Page 2 of 2
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SEWARD, ALASKA:
Section 1. The City Manager is hereby authorized to execute Amendment No. 01 to the
Professional Services Agreement with KPFF Consulting Engineers for emissions inventory
support services for the shore power project, in an additional amount not to exceed $284,995, for
a revised total contract amount not to exceed $702,936.00
Section 2. Funding in the amount of $284,995 is hereby appropriated from the EPA grant funds
allocated specifically for the Port of Seward Vessel Shore Power Fund contracted services expense
account 15360-0000-7009.
Section 3. This resolution shall take effect immediately upon approval.
APPROVED BY THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA THIS 13th
DAY OF APRIL 2026.
&AAA -Me
Sue McClure, Mayor
AYES: Osenga, Warner, Draper, Barnwell, Crites, Calhoon, McClure
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST:
Kris Peck
City Clerk
City Council Agenda Statement
Meeting Date: April 13, 2026
To: City Council
From: Kat Sorensen, City Manager
Subject: Resolution 2026-037: Authorizing the City Manager to Execute Amendment
No. 01 to the Professional Services Agreement with KPFF Consulting
Engineers for Emissions Inventory Services for an Amount Not to Exceed
$284,995 which is Fully Funded by the EPA Grant as Part of the Shore
Power Project
Background and justification:
On April 15, 2025, the City entered into a Professional Services Agreement with KPFF Consulting
Engineers for project management services supporting the EPA Clean Ports grant -funded Shore
Power project.
As a condition of the $45.7 million EPA Clean Ports grant, the City is required to conduct a vessel
emissions inventory documenting baseline air emissions from cruise ships hoteling at the Port of
Seward, as well as projected emissions reductions resulting from shore power implementation.
KPFF has submitted Amendment No. 01, dated March 27, 2026, to expand their scope of services
to include management and delivery of this emissions inventory, encompassing project planning,
data collection, baseline emissions calculations, future emissions modeling, QA/QC review, and
preparation of a final report meeting EPA grant requirements. The amendment is structured as a
time -and -materials contract with a not -to -exceed fee of $284,995, bringing the total contract
amount to $702,936.
The KPFF amendment lists the total contract amount as $683,034. The original contract for
$398,039 passed by Resolution 2025-044, included a 5% contingency of $19,901.95. This was
added to the project budget for the City, bringing the total amount not to exceed $702,936.
liComprehensive and Strategic Plan Consistency Information
This legislation is consistent with (citation listed):
Comprehensive Plan:
Strategic Plan:
Other:
EPA Grant Requirements
Total amount of funds listed in this legislation: $ 284,995
This legislation (✓):
Creates revenue in the amount of:
$
x
Creates expenditure in amount of:
Creates a savings in the amount of:
Has no fiscal impact
Funds are (✓):
x
Budgeted Line item(s): Grant funded
Not budgeted
Not applicable
$ 284,995
$
Affected Fund (✓):
General
Boat Harbor
Motor Pool
X
Available Fund Balance
SMIC
Parking
Other
Electric
Water
EPA Grant Fund
Wastewater
Healthcare
Note: amounts are unaudited
$ [intentionally left blank]
Finance Director Signature:
9"4"to
Yes
Attorney Signature:
Not applicable Comments:
Administration Recommendation
x
Adopt Resolution
Other:
kpff
Consulting Engineers
1601 5^ Avenue, Suite 1300, SEATTLE, WA 98101 P: 206-382-0600 F: 206-382-0500 WWW.KPFF.COM
AMENDMENT TO EXISTING
AGREEMENT FOR PROFESSIONAL SERVICES
DATE OF AMENDMENT:
March 27, 2026
DATE OF EXISTING AGREEMENT:
April 15, 2025
JOB NUMBER:
2500051
CLIENT:
City of Seward
PROJECT NAME:
Shore Power and Cruise Ship
Expansion — Project Management
Dock
LOCATION:
Seward, AK
SCOPE OF SERVICES: Emissions inventory support, detailed in the KPFF Amendment
No. 01 Proposal, dated March 27, 2026, attached as Attachment "A"
SCHEDULE: Work to complete is Q2 2028
FEE: Additional fee for services provided in this amendment of $284,995. Budget for this
project not to exceed $683,034.
The existing Agreement dated April, 15, 2025 remains unchanged except as specifically
modified in this Amendment.
Offered By KPFF, Inc. Accepted by City of Seward
,
(Signature) (Signature)
Rob Price, Principal, 3/27/26
Kat Sorensen, City Manager 4/15/26
(Print Name/Title) (Print Name/Title)
City of Seward
March 27, 2026
Page 1
1601 Fifth Avenue, Suite 1300, Seattle, WA 98101 1206-382-0600 I kpff.com
March 27th, 2026
Kat Sorensen I City Manager
City of Seward
410 Adams St
P.O. Box 167
Seward, AK 99664
Re: Shore Power and Cruise Ship Dock Expansion — Project Management
Amendment No. 01
KPFF Project No. 2500051
Dear Kat,
kpff
KPFF is providing this Scope and Fee supplement proposal for additional Grant Administration Project
Management, Emissions Study, as part of the City of Seward Shore Power and Cruise Ship Dock Expansion
project. This proposal addresses the project needs for management of an emissions study to support
requirements called out in the Project QAPP.
Emissions Inventory Support
KPFF will support the development of a Port of Seward Vessel Shore Power Implementation Emissions
Inventory (emissions inventory) in alignment with EPA Grant requirements. Per the scope in the project
QAPP, this emission inventory will be focused exclusively on identifying emissions from vessels hoteling
at the Port of Seward, and identified emission types will include:
• Greenhouse gases (CO2)
• Criteria air pollutants including particulate matter (PM2.5), carbon monoxide (CO), nitrous oxides
(NOX), Sulfur dioxide (SO2)
All of the emissions inventoried will be from cruise ships docked at either of the berths at the Port of
Seward located at the head of Resurrection Bay in the city of Seward, Alaska.
Task 1: Project Planning and Data Scoping. KPFF will first host an online project kickoff with City of Seward
and Port of Seward Operations staff to ensure alignment with project goals and schedule, review current
data availability, and identify key data sources. Based on the kickoff discussion, the KPFF team will develop
a Data Collection Plan that identifies key data needs, data sources for each need, along with a data
collection methodology. Data needs are expected to include:
City of Seward
March 27, 2026
Page 2
• Vessel characteristics including vessel name, type, and diesel generator characteristics, such as
fuel, power rating, and engine tier
• Vessel activity information, including duration of hoteling per vessel call, electric hoteling loads,
and number of calls per year per vessel
• Fuel type used for each vessel
• EPA emissions factors
KPFF anticipates that the Data Collection Plan will include outreach to vessel operators and Port of Seward
Staff, including requests for information, virtual meetings, and follow-up emails as needed. As part of Data
Collection Plan development, KPFF, in collaboration with City and Port Staff, will develop a contact list for
vessel operators and other stakeholders who were not yet identified in the QAPP.
Deliverables
• Project Kickoff Presentation
• Data Collection Plan
Assumptions
• Project kickoff meeting will be virtual and one hour in duration.
Task2: Develop Baseline Year Emissions. As part of this subtask, KPFF will first execute the Data Collection
Plan developed in Task 1. As part of this effort, KPFF will partner with City of Seward and Port of Seward
Operations Staff to organize and format vessel activity data, as needed. In addition, KPFF will conduct
phone and virtual outreach with vessel operators and industry trade organizations as needed to collect
new primary data regarding vessel characteristics, fuel type, or other data per procedures listed in the
Data Collection Plan. A log of data collection activities will be maintained to record what outreach
occurred, what data was received, and when it was received.
Using EPA emissions factors and in alignment with EPA guidance on Port Inventories, KPFF will then
develop an emissions calculation methodology using the collected data, identifying necessary
assumptions, quality assurance and quality control checks, and documentation procedures. KPFF will then
carry out the methodology and conduct calculations to identify baseline emissions. As needed, KPFF will
coordinate with EPA and Port of Seward grant staff to ensure alignment and approval of the identified
calculation methodology and to ensure all grant requirements are met.
Deliverables
• Data Collection Log
• Baseline Emissions Inventory Methodology Memo
• Baseline Emissions Inventory Calculation Spreadsheet
City of Seward
March 27, 2026
Page 3
Assumptions
• Inventory will use 2024 as the baseline year for emissions calculations.
• Any coordination with EPA regarding grant requirements will be via either virtual meetings or
email correspondence. KPFF will not conduct any coordination with EPA without consulting
the City of Seward Project Manager.
Task 3: Model Future Shore Power Use and Emissions Savings. To understand the potential emissions
savings of the new shore power installation, KPFF will also develop a model to project potential future
shore power use and associated emission reductions. This model will project annual electricity used via
shore power in the first full year of shore power operation using a three -step approach.
1. Model future vessel activity at the port along based on recent activity trends, including estimates
of which visiting vessels are expected to be compatible with the shore power system after the
project is complete. KPFF will develop these estimates based on vessels that are currently shore
power capable, as identified in Task 2, and will also estimate any reasonable increases in the shore
power capability of visiting vessels based on current market trends and input from vessel
operators.
2. Identify likely shore power electricity use and power needs for each port call based on vessel
characteristics and activity data identified in Task 2.
3. Calculate shore power related emissions from the utility grid and compare them to baseline
emissions to quantify projected emissions savings on an annual basis.
KPFF will document the model's assumptions and calculations in a consolidated spreadsheet.
Deliverables
• Future Shore Power Use Model & Emissions Calculation Spreadsheet
Assumptions
• Inventory will use 2024 as the baseline year for emissions calculations.
Task 4: QA/QC Activities. Andy Bennett at KPFF will be the dedicated KPFF staff member to serve as
Project Quality Assurance Manager and will complete QA/QC activities of both the baseline emissions
calculations and the future shore power use model. Key activities that the Project Quality Assurance
Manager will conduct include:
• Cross-checking reported vessel activity with independent sources.
• Performing internal consistency checks on calculation outputs.
• Assigning QA ranks to all data inputs (Ranks A—E) per EPA guidance.
City of Seward
March 27, 2026
Page 4
The Project Quality Assurance Manager will document QA rankings and justifications in a memo for easy
verification with EPA.
Deliverables
• Memo Documenting QA Rankings for Data Inputs
Assumptions
• The Project QA manager will maintain the approved QA Project Plan.
Task 5: Report Generation & Submission. KPFF would prepare the final Emissions Inventory Report,
focusing on meeting grant requirements and communicating the emissions inventory methodology and
findings in a clear, easy to understand, and visually appealing manner. The Emissions Inventory Report
will include, at minimum, the following sections:
• Introduction & Project Purpose
• Methodology
• Summary of QA Activities
• Baseline Emissions (including applicable data tables and visualizations)
• Future Shore Power Use and Emission Reductions (including applicable data tables and
visualizations)
Deliverables:
• Emissions Inventory Report
Assumptions:
• The City of Seward will complete final submission of report materials to EPA.
Project Management
KPFF will conduct project management activities as needed to support successful completion of this
project. Tasks will include meeting preparation, attendance, and follow-up; budget and schedule tracking;
and preparation of monthly invoices.
Project management meetings will be held with Port of Seward bi-weekly to discuss project status and
key tasks.
Deliverables:
• Detailed project schedule with tasks, roles, and timeline
• Monthly invoices
City of Seward
March 27, 2026
Page 5
Assumptions:
• One -hour, biweekly check -in meetings will be held virtually.
• Two staff from KPFF will attend all meetings and will bring in other specialized staff, as
needed.
• Assumes a 10-month project duration.
Fee
KPFF proposes a time and materials contract, with the not -to -exceed budgets by task for the amount of
$284,995.
If after your review of this proposal you have any questions, please contact me at your earliest
convenience. We look forward to continuing working with you and City of Seward on this critical
project.
Sincerely,
Robert Price, PMP
Principal
KPFF Consulting Engineers
Attachments:
Fee Spreadsheet
Sub consultant Scope Proposal
Consultant Fee Estimate
Summar
Project Name
Fee Estimate
KPFF
1.0000
DSC+OH Mult.
Principal
ciA
Manager
Planner II
Planner II
Planner I
Prog
Support
Admin
Graphics
SR. Graphics
Task
Description
$ 285
$ 285
$ 175
$ 175
$ 105
$ 155
$ 130
$ 110
$ 190
Fee
0
Project Management
0.1
Meetings
10.0
20.0
20.0
40.0
14,050
0.2
General PM
40.0
20.0
60.0
19,800.00
Subtotal
0.0
10.0
60.0
40.0
40.0
60.0
0.0
0.0
0.0
$ 33,850
1.0
Project Planning and Data Scoping
1.1
Kickoff
1.0
2.0
4.0
4.0
8.0
3,095.00
1.2
Develop Data Collection Plan
20.0
4.0
24.0
24.0
32.0
18,600.00
1.3
-
Subtotal
21.0
6.0
28.0
28.0
40.0
0.0
0.0
0.0
0.0
$ 21,695
2.0
Develop Baseline Emissions Inventory
2.1
Outreach & Data Collection
24.0
2.0
24.0
120.0
80.0
41,010.00
2.2
Model Methodology & Template
8.0
2.0
32.0
100.0
25,950.00
2.3
Baseline Year Emissions Calculations
40.0
80.0
140.0
35,700.00
2.4
EPA Coordination
10.0
10.0
10.0
20.0
8,450.00
Subtotal
42.0
4.0
106.0
310.0
240.0
0.0
0.0
0.0
0.0
$ 111,110
3.0
Model Future Emissions
3.1
Future Shore Power Use
40.0
2.0
24.0
40.0
60.0
29,470.00
3.2
Emissions Projections
16.0
40.0
60.0
16,100.00
3.3
EPA Coordination
8.0
8.0
8.0
16.0
6,760.00
Subtotal
48.0
2.0
48.0
88.0
136.0
0.0
0.0
0.0
0.0
$ 52,330
4.0
QA/QC Activities
4.1
QA/QC Inventory
48.0
20.0
15,780.00
4.2
QA/QC Future Emission Model
48.0
20.0
15,780.00
Subtotal
0.0
96.0
0.0
0.0
40.0
0.0
0.0
0.0
0.0
$ 31,560
5.0
Emissions Inventory Report
5.1
Draft
16.0
4.0
32.0
16.0
80.0
22,500.00
5.2
Final
8.0
2.0
16.0
12.0
40.0
11,950.00
Subtotal
24.0
6.0
48.0
28.0
120.0
0.0
0.0
0.0
0.0
$ 34,450
6.0
6.1
-
Subtotal
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
0.0
$ -
Labor Total
135.0
124.0
290.0
494.0
616.0
60.0
-
-
-
$ 284,995
Other Direct Costs
Description
Qty
Unit
Cost
Mileage (2025)
miles
$ 0.725
$ -
ODC1
night
$ 275
$ -
ODC2
each
$ 100
$ -
ODC3
day
$ 100
$ -
ODC4
Is
$ 200
$ -
Expense Subtotal:
$ -
KPFF TOTAL:
$ 284,995.00