HomeMy WebLinkAboutRES2026-080 GHEMM Company LLC - Shore Power & Cruise Ship DockSponsored by: Sorensen
CITY OF SEWARD, ALASKA
RESOLUTION 2026-080
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA,
AUTHORIZING THE CITY MANAGER TO ENTER INTO AN INITIAL DESIGN -BUILD
AGREEMENT WITH GHEMM COMPANY, LLC FOR THE SHORE POWER AND
CRUISE SHIP DOCK EXPANSION PROJECT IN AN AMOUNT NOT TO EXCEED
$2,127,700 FUNDED THROUGH THE ENVIRONMENTAL PROTECTION AGENCY
CLEAN PORTS GRANT PROGRAM
WHEREAS, the City of Seward has identified implementation of shore power at the Seward
Cruise Ship Passenger Terminal as a critical infrastructure project to reduce air emissions, support
environmental sustainability, and enhance the economic vitality of the port; and
WHEREAS, by Resolution 2025-016, the City Council accepted $45,732,040 in grant funds from
the U.S. Environmental Protection Agency (EPA) Clean Ports Grant Program for implementation
of shore power at the Seward Cruise Ship Terminal and appropriated those funds according to the
budget established in the grant narrative; and
WHEREAS, Resolution 2025-016 established Fund 15360, Port of Seward Vessel Shore Power
Project, for grant -related revenues and expenditures and authorized the City Manager to execute
documents and take actions necessary to administer the EPA grant; and
WHEREAS, the EPA grant award provides 90 percent of the approved project cost, with the
required 10 percent match committed by The Seward Company, as described in Resolution 2025-
016; and
WHEREAS, on February 2, 2026, the City issued a Request for Proposals for the Shore Power
and Cruise Ship Dock Expansion as a design -build project, with the successful Design -Builder
responsible for design, procurement, construction, installation, and commissioning of the shore
power system; and
WHEREAS, the Request for Proposals established Project Milestone 1 to advance the design
sufficiently to enable procurement of long -lead items, with the 30 percent design of the Shore
Power System identified as the initial design milestone; and
WHEREAS, the Request for Proposals further anticipates a collaborative design -build process in
which the City and Design -Builder review design progress, schedule risks, dependencies, and
project requirements as the design advances; and
WHEREAS, the City received one proposal in response to the solicitation, from GHEMM
Company, LLC, with a total proposed Base Bid plus Additive Alternate 1 amount of $23,927,300,
consisting of a $22,910,000 Base Bid and a $1,017,300 Additive Alternate; and
WHEREAS, GHEMM has teamed with Watts Marine as the dedicated Shore Power System
Provider, with GHEMM managing overall design -build delivery and Watts Marine responsible for
CITY OF SEWARD, ALASKA
RESOLUTION 2026-080
Page 2 of 3
equipment procurement, system engineering, commissioning, and related shore power system
services; and
WHEREAS, GHEMM's proposal states that, upon award, Watts Marine will immediately begin
design toward the 30 percent Concept Design package while refining the transformer package to
allow early procurement of long -lead equipment; and
WHEREAS, the City desires to authorize an initial phase of the design -build contract rather than
authorize the entire construction amount at this time, allowing the City and Design -Builder to
advance design, further define project scope, cost, and schedule, and protect the procurement
schedule for critical -path equipment; and
WHEREAS, the City intends to return to the City Council for authorization of additional design,
equipment procurement, and construction costs after the design has advanced sufficiently to
establish an agreed -upon project scope, price, and schedule.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SEWARD, ALASKA:
Section 1. The City Council hereby authorizes the City Manager to enter into an initial design -
build agreement with GHEMM Company, LLC for the Shore Power and Cruise Ship Dock
Expansion Project in an amount not to exceed $2,127,700.
Section 2. This initial authorization does not constitute authorization of the full $23,927,300
proposal or the remaining design and construction costs. The City Manager shall return to the City
Council for additional authorization after the design has advanced sufficiently to establish an
agreed -upon project scope, price, and schedule, or as otherwise required to maintain the project
schedule.
Section 3. Funding in an amount not to exceed $2,127,700 is authorized from Fund 15360, Port
of Seward Vessel Shore Power Project, using funds previously accepted and appropriated through
Resolution 2025-016 from the U.S. Environmental Protection Agency Clean Ports Grant Program.
Section 4. The City Manager, or designee, is authorized to negotiate and execute the initial
contract, notices to proceed, equipment commitments, and other documents necessary to carry out
this resolution, subject to final contract terms acceptable to the City and compliance with
applicable EPA grant requirements.
Section 5. This resolution shall take effect immediately upon its adoption.
CITY OF SEWARD, ALASKA
RESOLUTION 2026-080
Page 3 of 3
APPROVED BY THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA THIS 28th
DAY OF SEPTEMBER 2026.
5'-{A—Me
Sue McClure, Mayor
AYES: Osenga, Warner, Draper, Calhoon, McClure
NOES: None
ABSENT: Barnwell, Crites
ABSTAIN: None
ATTEST:
Kris Peck
City Clerk
City Council Agenda Statement
Meeting Date: September 28, 2026
To: City Council
Through: Kat Sorensen, City Manager
From: Brian Hickey, Electric Manager
Subject: Resolution 2026-080: Authorizing the City Manager to Enter into an Initial
Design -Build Agreement with GHEMM Company, LLC for the Shore
Power and Cruise Ship Dock Expansion Project in an Amount Not to Exceed
$2,127,700 Funded through the Environmental Protection Agency Clean
Ports Grant Program
Background and justification:
Approval of this resolution will allow the City to continue moving the Shore Power Project forward
through the collaborative design -build process, allowing the City and design -builder to refine the
project scope, cost, and schedule as the design progresses.
The project will provide modern, reliable port infrastructure, reduce emissions from cruise ships
while in port, and support the long-term economic and environmental sustainability of Seward's
waterfront and community. Moving forward now will also help protect the project schedule and
ensure the City can effectively utilize the EPA Clean Ports Grant funding available for this
important community infrastructure project.
IOW
Fiscal Impact:
Funding Source:
X
X
X
Yes — Amount: $
No
General Fund:
Budgeted:
Yes
No
N/A
Enterprise Fund: 15360 — Port of Seward Vessel Shore Power Project
Grant: EPA Clean Ports Grant 5YO2J92001
Other:
Finance Director Signature: plated Suraedeiuteeaa (acting)
Comprehensive and Strategic Plan Consistency Information
This legislation is consistent with (citation listed):
Comprehensive Plan:
City Council Agenda Statement
Strategic Plan:
Other:
Attorney Review
X
Yes
Attorney Signature:
Not applicable Comments:
Administration Recommendation
X
Approve
Other:
CONTRACTORS LICENSE #199219
September 17, 2026
GHEMM
COMPANY LLC
City of Seward
PO Box 167
Seward, AK 99664-0167
Re: Shore Power and Cruise Ship Dock Expansion, Seward, AK
RFP for Design -Build General Construction Services
To whom it may concern:
GHEMM Company is pleased to provide you with the requested, updated cost proposal
including design fees, and early procurement of long lead materials necessary to begin
the captioned Seward Shore Power project. We very much appreciate this opportunity
and look forward to discussing our proposal in further detail with you.
Per your request, pricing for this early package is:
Inclusions
• 30% design package
• Design management
• Cost estimate for 30% design package
• Down payment to secure two (2) transformers
• Down payment to secure PEMB shop drawings and engineering
Exclusions
• Design and/or engineering beyond 30% design
• Procurement of materials beyond what is mentioned above
• Construction of any kind
GHEMM expects the 30% design process to take approximately five (5) months to
complete. Based upon this duration, we see the schedule as follows:
• Notice to Proceed for 30% Design
• Contracts, Material Procurement Starts
• 30% Design Complete
October 2, 2026
October 9, 2026
February 5, 2027
31361 SCHACHT STREET FAIRBANKS ALASKA 99701 T 907.452.51 91 F 907.451 .7797 E GHEMM@GHEMM.COM
GHEMM
COMPANY LLC
City of Seward
September 17, 2026
Page 2
GHEMM Company will supply all project management, labor, materials and
design/engineering necessary to complete this early, limited scope of work at a total cost
of $2,127,700.00.
Again, we thank you for this opportunity to be of service to the City of Seward. We are
available to discuss this project in further detail and look forward to hearing back from you
soon.
Sincerely,
GHEMM Company, LLC
;Me-� 012(
President
Cc: Matt Chacho, PE, Vice President, GHEMM Company, LLC
3861 SCHACHT STREET FAIRBANKS ALASKA 99701 T 907.452.5191 F 9❑7.451 .7797 E GHEMM@GHEMM.COM