HomeMy WebLinkAboutRES2026-083 Cornerstone General Contracting - Harbor Test PileSponsored by: Sorensen
CITY OF SEWARD, ALASKA
RESOLUTION 2026-083
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA,
AUTHORIZING THE CITY MANAGER TO SIGN CONTRACT DOCUMENTS
ASSOCIATED WITH DRILLING A TEST PILE FOR THE HARBORMASTER'S
OFFICE FOR AN AMOUNT NOT TO EXCEED $286,061 AND APPROPRIATING FUNDS
WHEREAS, Cornerstone General Contractors was selected as the successful candidate for the
Construction of the Harbormaster's Office and South Uplands Development; and
WHEREAS, Cornerstone is working at sizing the project to the budget and minimizing risk (i.e.,
added costs); and
WHEREAS, a test pile needs to be driven to determine what the best solution is for the foundation
of the building on the uplands; and
WHEREAS, this cost will be incorporated into the overall project cost.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF
SEWARD, ALASKA:
Section 1. The resolution acts as a notice to proceed and authorizes the City Manager to sign any
intermediate contracts for this limited early work necessary to mobilize, install, and independently
test one test pile.
Section 2. Funding in the amount of $286,061 is hereby appropriated from the designated
Harbormaster Office Building Project Fund 11433-0000-8101 Infrastructure Expense Account and
shall be paid from the revenue bond proceeds.
Section 3. This resolution shall take effect immediately upon adoption.
APPROVED BY THE CITY COUNCIL OF THE CITY OF SEWARD, ALASKA THIS 12th
DAY OF OCTOBER 2026.
Sue McClure, Mayor
CITY OF SEWARD, ALASKA
RESOLUTION 2026-083
Page 2 of 2
AYES: Warner, Barnwell, Draper, Calhoon, Osenga, McClure
NOES: None
ABSENT: Crites
ABSTAIN: None
ATTEST:
Kris Peck
City Clerk
City Council Agenda Statement
Meeting Date: October 12, 2026
To: City Council
Through: Kat Sorensen, City Manager
From: Jason Bickling, Deputy City Manager
Subject: Resolution 2026-083: Authorizing the City Manager to Sign Contract
Documents Associated with Drilling a Test Pile for the Harbormaster's
Office for an Amount Not to Exceed $286,061 and Appropriating Funds
Background and justification:
The Harbormaster Facility and Uplands Development project is currently in the preconstruction
phase. Cornerstone Contractors is working with potential subcontractors to get actual costs for the
project. The goal of the preconstruction process is to right -size the project to the budget. The
original costs of the potential subcontract work were about $20,000,000. Cornerstone is working
with R&M and KPB to make changes to the project to ensure it stays within budget (roughly
$12,000,000 for the structure). As such, some preliminary testing is necessary to mitigate risk and
effectively manage costs.
The area where the harbormaster's office is being constructed is manmade, on top of what used to
be open water. A breakwater was on the northside, and an additional breakwater was built on the
south side, then filled in with dredged sediment to create the uplands parking area. Even with the
geotechnical work that has been done (bore hole drilling), it cannot be fully determined what
approach to take for the foundation that will minimize cost at an acceptable risk. A test pile is
needed to determine how deep the pile will need to be driven. This test pile will be integrated into
the foundational structure of the building. Strata Deep Constructors are already mobilized on the
Kenai Peninsula and able to do the work.
This resolution will authorize the City Manager to sign any intermediate contracts for this test pile
and authorize the limited early work necessary to mobilize, install, and independently test one test
pile so the project team can confirm pile performance and advance production foundation decisions.
This will scaffold the project until the larger contract with Cornerstone is signed with the
Guaranteed Maximum Price (GMP). The cost of this work will be included in the overall cost
(Guaranteed Maximum Price) of the project, and it will be brought forward at a future meeting for
final contract authorization. As we are scaling the project down, we are going to be in the same
ballpark of cost per square foot ($1500/sq ft) that Providence discussed at the work session last
month. The Harbormaster's Office and Uplands Development Project will be slightly higher due
to the complexity of the foundation work.
City Council Agenda Statement
Fiscal Impact:
Funding Source:
X
X
X
Yes — Amount: $286,061 Budgeted:
No
General Fund:
Enterprise Fund:
Grant:
X
Yes
No
N/A
11433-0000-8101 Harbormaster Office Building Project Fund
Other: Revenue Bond Proceeds/CPV Funds
Finance Director Signature:
5
Comprehensive and Strategic Plan Consistency Information
This legislation is consistent with (citation listed):
Comprehensive Plan: 3.7.1.5 Plan to relocate and rebuild selected city facilities to improve
compatibility with land uses and increase cost effectiveness of services.
Strategic Plan:
Other:
X
Yes
Attorney Signature:
Not applicable Comments:
Administration Recommendation
X
Approve
Other: