HomeMy WebLinkAboutRes2015-071 Sponsored by: Hunt
CITY OF SEWARD,ALASKA
RESOLUTION 2015-071
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF SEWARD,
ALASKA, AUTHORIZING THE CITY MANAGER TO ENTER INTO A
CONSTRUCTION CONTRACT WITH HAMILTON CONSTRUCTION,
LLC IN AN AMOUNT NOT TO EXCEED $15,032,101.80 FOR THE
PHASE 1 HARBOR IMPROVEMENTS AT THE SEWARD MARINE
INDUSTRIAL CENTER AND AN ADDITIONAL $1,503,210 AS A
PROJECT CONTINGENCY AND APPROPRIATING FUNDS
WHEREAS, the City of Seward, using State of Alaska funds, hired R & M Consultants
in 2011 to design a new breakwater at SMIC; and
WHEREAS, the breakwater will be of the rubble mound type and it will be partially
constructed using locally produced rock; and
WHEREAS, the project requires the blasting and sorting of rock into different size
classifications; and
WHEREAS, the project requires the transportation of remaining rock into different size
classifications from geographically separated sources; and
WHEREAS, the City developed a scope of work with the assistance of R & M
Consultants, Inc. and advertised a competitive bid package according to SCC 6.10.210 and SCC
6.10.215; and
WHEREAS, six bids were received by the required deadline of 3:00 p.m. July 7, 2015;
and
WHEREAS, the City and R & M Consultants, Inc. reviewed all bids and concluded
Hamilton Construction, LLC was the lowest, most qualified and responsive bidder with a base
bid amount of$14,317,855.50 and two Alternate bid amounts totaling$714,246.30; and
WHEREAS, the City and R & M Consultants agree that a ten percent contingency is
necessary for a project of this magnitude to address the potential for unforeseen project costs.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF THE
CITY OF SEWARD,ALASKA that:
Section 1. The City Manager is hereby authorized to enter into a construction contract
not-to-exceed $15,032,101.80 with Hamilton Construction, LLC, including both the Base Bid
and two Alternates in substantially the form as presented at this meeting, for the Phase 1 Harbor
Improvements for the Seward Marine Industrial Center.
CITY OF SEWARD,ALASKA
RESOLUTION 2015-071
Section 2. Funding for this contract in an amount not-to-exceed $15,032,101.80 was
previously appropriated from State of Alaska DCCED grant fund account 12331-0000-5922, and
will be charged to SMIC Breakwater Infrastructure account no. 12331-0000-8101.
Section 3. Funding in an amount not-to-exceed $1,503,210.00 representing a ten percent
contingency, was previously appropriated from State of Alaska DCCED grant fund account no.
12331-0000-5922 and will be charged to the Phase 1 Harbor Improvements contingency account
no. 12331-0000-7807. The contingency will be utilized only if authorized by the City Manager
in writing, in advance, due to change in project scope on unanticipated costs agreed to by the
City.
Section 4. This resolution shall take effect immediately upon its adoption.
PASSED AND APPROVED by the City Council of the City of Seward, Alaska, this
10th day of August 2015.
THE CITY OF SEWARD, ALASKA
�IIL tidt.. 4/
•an Bardarson,Mayor
AYES: Keil, Casagranda, Terry, Squires, Butts,Darling, Bardarson
NOES: None
ABSENT: None
ABSTAIN: None
ATTEST:
-4///
ohanna Kinney, CMC
City Clerk
ssssssssss
•,�Of SEW .'+.
(City Seal) ..••- K...
•■ : SEAL •
•
.
�. .�� -.w
••
.
Nalit OF W*
Agenda Statement
of sFly
Meeting Date: August 10, 2015 •'�{�
To: City Council 1 `'
Through: City Manager Jim Hunt i1
From: Harbormaster Norm Regis
Agenda Item: Authorizing the City Manager to enter into a construction contract with
Hamilton Construction, LLC., the most qualified and responsive bidder,
for the SMIC Phase 1 Harbor Improvements (breakwater construction,
dredging, turning dolphin construction, and other harbor improvements)
Project and appropriate funds.
BACKGROUND & JUSTIFICATION:
Beginning in 2011 the City of Seward has focused public attention on the completion of
the breakwater along with other vital harbor improvements at the Seward Marine Industrial
center (SMIC). The design process has focused on finalizing the rubblemound breakwater, a
replacement turning dolphin, relocation of two outfall pipes, and other harbor accessories. A
2014 rock production contract failed to provide the rock for the breakwater under a separate
contract.
The City is working with R & M Consultants on this project and who drafted and
finalized the competitive bid package based on the City's standard construction contract, the
scope of work and the availability of funds. This project was advertised according to SCC
6.10.210 and SCC 6.10.215. Six bids were received by the City by the deadline of 3:00 p.m. on
July 7, 2015. The City and R & M reviewed all bids and concluded Hamilton Construction,
LLC. was the lowest, most qualified and responsive bidder with a total bid amount of
$15,032,101.80 including the Base Bid and two Additive Alternates.
The project consists of a new 960 foot rock breakwater totaling nearly 251,000 tons of
several classes of rock materials along the west side of the SMIC harbor basin and 111,500 cubic
yards of dredging to provide a new channel into the basin from the north to an elevation of-20
feet MLLW and associated navigational aids and marker piles. In addition, the existing sewer
and seafood outfalls will be relocated to accommodate the breakwater and dredging work. The
two Additive Alternates include removing and replacing the turning dolphin and catwalk at the
Syncrolift pier, and furnishing and stockpiling additional Class A and Class B Primary Armor
Rock.
The bid tabulation follows:
SMIC Phase 1 Harbor Improvements Project
Contractor Base Bid Additive Additive Total Bid
Amount 1 Amount 2
Engineers $23,540,650.00 $480,540.00 $355,000.00 $24,376,190.00
Estimate
Hamilton $14,317,855.50 $406,246.30 $308,000.00 $15,032,101.80
Construction,
LLC
Pacific Pile & $19,698,596.00 $755,200.00 $337,500.00 $20,791,296.00
Marine, LP
Granite $20,565,278.00 $652,475.00 $180,000.00 $21,397,753.00
Construction Co
Kiewitt $20,022,740.00 $1,177,570.00 $315,000.00 $21,515,310.00
Infrastructure
West Co
Orion Marine $27,909,491.20 $977,735.00 $369,000.00 $29,256,226.20
Contractors, Inc
The Dutra Group $39,828,627.50 $1,394,400.00 $936,000.00 $42,159,027.50
INTENT:
Enter into a construction contract not-to-exceed $15,032,101.80 with Hamilton Construction,
LLC for Phase 1 Harbor Improvement at SMIC and appropriate funds.
CONSISTENCY CHECKLIST: Yes No N/A
Comprehensive Plan (document source here): Plan for adequate port
1 infrastructure that will serve the needs of users...at the Seward Marine X
Industrial Center (SMIC), sustain an increase above the current
activity, and attract new business. (page 24)
2 Strategic Plan (document source here): Develop infrastructure X
expansion plans for currently underdeveloped property.(page 5)
3. Other (list):
FISCAL NOTE:
All of the cost of the engineering and construction work will be paid from grants from the State
of Alaska. Additional funds are required to be appropriated in the amount of $1,503,210
representing a 10% contingency on the construction project, and will be utilized only if required
by justifiable change orders approved in advance by the City Manager.
Approved by Finance Department: _, n►
ATTORNEY REVIEW: Yes No
RECOMMENDATION:
Council support Resolution 2015- 011 authorizing the City Manager to enter into a
construction contract with Hamilton Construction, LLC, the most qualified, responsive and
lowest bidder, for Phase 1 Harbor Improvements at the Seward Marine Industrial Center and
appropriate funds.