HomeMy WebLinkAbout09242018 City Council Laydown - PND Engineers - Cruise Ship Dock Project Presentation for Seward City Council 24th September 2018 FUTURE CRUISE 1 Why Now? Cruise Ships under Construction for delivery in the next 10 years. 110 2 Alaska Cruise Opportunities Why Seward Discussion on: Larger and Higher Capacity Ships entering the market Existing cruise ship stops saturated Growing expectations of Cruise Passengers Market ownership is changing (Carnival bought most Skagway) Attraction of the ‘Open Jaw’ itinerary 3 Scenic Train ride from Anchorage – Experience starts here! Programming in Port Icy Strait and proposed Southeast Alaska locations. Strategic Location Open Jaw Itineraries 4 Today’s Agenda: AK Current Cruise Industry Economic Status and Forecast Seward Current and Future Opportunities Approach to Project Implementation Team Introductions 5 I. AK Current Cruise Industry Economic Status and Forecast 6 AK Cruise Passengers Demand / Projections Ketchikan, AK Aerial and Visitor Data (Typical 4 Ship Day – 5 Days per Week) Data from: Ketchikan Summer Visitor Profile and Economic Impact Analysis, April 2018 by McDowell Group 7 Seward Cruise Ship Statistics Seward Marine Terminal Expansion Planning-Master Plan-2017 8 Seward Cruise Passengers History Seward Marine Terminal Expansion Planning-Master Plan-2017 9 Downtown Options 10 Three Potential Piers 11 Option 1 12 Option 2 13 Option 3 14 Railroad Terminal Option 15 Railroad Site Dock Replacement 16 Trolley Connection to Downtown 17 Boutique Terminal at Sealife Center 18 The Big IDEA Enhancement and extension of the Sea Life Centre Pier as part of the exhibit Floating ‘Islands’ of development mixing the natural surroundings into the arrival or departure experience with decks and gangways part of the Sea Life narrative. 19 Phasing Approach Pier by Pier approach allows the infrastructure and facilities to grow as demand increases Buildings as landscape Marine elements as Islands 20 Tentative Schedule Begin early Phase Planning/Stakeholder Engagement: October 15, 2018 Planning Complete: January 31, 2019 10% Design-Concept Development/ROM Cost Estimate: April 17, 2019 Present Concepts to City/Stakeholders: April 22, 2019 Begin Permitting: May 1, 2019 35% Design/Cost Estimate: July 3, 2019 65% Design/Cost Estimate: September 30, 2019 95% Design/Cost Estimate: January 15, 2020 Present Plans to City/Stakeholders: January 30, 2020 IFC Plans: March 1, 2020 Issue for Bid: March 31, 2020 Review bids: May 15, 2020 Award Construction Contract: June 15, 2020 Begin Fabrication: July 15, 2020 Obtain Permit: October 1, 2020 Begin Construction: October 15, 2020 Construction Complete: May 1, 2021 21 III. Approach to Project Implementation 22 Align Community Values Making a significant and positive difference in the lives of the local community. Based on teamwork and clear vision with one mission. Committed to clear and open communications. Use of sound business practice and careful management of assets. Right resources to the right customers – going the extra mile. Based on solid long lasting relationships. 23 Public Private Partnership/ Project Finance The Project could be structured as self-financing, under a Public Private Partnership (“PPP”) structure. No direct fiscal impact to the City, but will enhance “head tax” revenue improving the future fiscal position. The Development Team  will raise the debt and equity capital necessary for the Project. The Development Team will negotiate berthing and/or  Take or Pay priority contracts. Multi- year concession to be agreed upon by all parties. The City and the Development Team with other third party investors will then create a Special Project Vehicle - SPV  - to develop, construct,  and own the Project. The City will retain the land equity position in the SPV as required. 24 IV. Team Introductions 25 IDEA, Inc. Founded in 1995 by Themed Entertainment Expert Hugh Darley Orlando Based International design and Planning firm that oversees the conceptual design and production of branded destinations for the hospitality, entertainment and tourism Industries. Custom tailored project teams selectively drawn from talented multi disciplinary network of industry leading planners, designers and artists. A signature approach to each project that ensures branded destinations are both innovative and commercially viable. IDEA have instigated and delivered award winning ports worldwide. 26 Founded in 1979 in Alaska Alaska Based Corporation with offices in Anchorage and Juneau Alaska, Seattle Washington, Houston Texas, and Vancouver, BC Canada Currently employs just under 100 individuals Full services civil, structural and geotechnical engineering Award-winning, practical designs Extensive design and planning experience in Seward Working with the team on port of call concepts that would support this project Led the Seward Marine Terminal Expansion Planning-Master Plan 2017 PND Engineers, Inc. 27 Bazarian International Financial Assoc., LLC Originally founded as East-West Financial Services, Ltd., in 1984 in Washington, DC Florida based company Performing the necessary financial engineering to determine the most efficient development plan Seeking out the appropriate brands/operator for the project and advising/representing the client in negotiations Arranging debt and equity finance for the project using our extensive network of international and domestic contacts Bazarian International             Financial Associates, LLC 28 Panorama International, Inc. International Resort and Attraction Development 55+ years in business spanning missions in over 75 countries Activities in Development, Finance, Marketing, Design, Planning, Consulting Current activities include Resorts, Port Development, Hotel finance Project Management 29 30